AZ Herentals, Herentals | Renovation and extension of AZ Herentals

AZ Herentals has undergone a complete transformation since 2008. The hospital was completely renovated and extended in 3 phases. The final step was the construction of Block K, a new 7-storey wing replacing an old part of the hospital. The new block was completed and in use in less than 1.5 years. It marks the end of 11 years of construction.
New seven-storey wing brings eleven years of construction to a close

The first plans for the renovation and extension of AZ Herentals? They date back to 2002. The hospital drew up a strategic care plan, the master plan, which was approved by the authorities in 2006. Phase 1 of the project began in March 2008. The final phase has now been completed with the new Block K. Meanwhile, contractor DCA is extending the existing operating theatre, and an extra level is being added to the visitors’ car park. All the works will be completed by early 2020. Liesbeth Plingers, Facilities Director at AZ Herentals: “Our master plan has 5 pillars that run like a thread through all the renovations and extensions. Since the hospital dates back to the 1940s, modernisation is our top priority. Earlier additions, built without an overall vision, had left related departments spread too far apart. We have now brought them together on the same floor.”
Logistics flows
“In all the buildings, we have separated visitor and staff circulation. We also needed to drastically reduce energy consumption in the old buildings. Finally, we made sure that the hospital can be extended in the future.”

Block K, a new 7-storey wing, replaces an old part of the hospital.
“We have brought together the administration for the entire hospital in Block K. All our meeting rooms are on the ground floor. It is also home to the technical services department. The 6th floor is entirely devoted to rehabilitation, with outpatient rehabilitation and post-rehabilitation for ex-triathlete Marc Herremans’ To Walk Again project. The surgical and medical day hospitals and 1 nursing ward have also moved into the new building.”
Fast construction without delays
Project manager Nick Van Otten of contractor DCA: “Moving into Block K was a real puzzle and took place one floor at a time. Some departments moved in while we were still building the rest of the building. That was the plan from the outset. It meant we had to complete and fit out each floor one at a time, while also building quickly.”

Each floor has its own cheerful colour,
which appears throughout the corridors.
“We demolished the existing building in the second half of 2017. We poured the foundations for Block K in December 2017, and the first departments moved in at the end of October 2018. One floor was completed each month. As a result, the final floor was already in use by the end of April this year.”
Tight schedule
“Fast construction was possible because Block K is a simple rectangle that we could build in a straightforward way. AZ Herentals deliberately opted for prefabrication. As many of the internal walls as possible were built from plasterboard, and the floors and ceilings are almost identical throughout. That made our work a lot easier.”
“We started construction with a site layout prepared down to the last detail and a tight schedule that had been fully worked out right through to the end of the project. Every week, we held a site meeting and looked 5 weeks ahead. That enabled us to anticipate any changes. For example, when the windows for one floor could not be delivered on time, we sealed the window openings so we could keep working.”
Design, planning and follow-up handled in-house
Liesbeth Plingers: “Another advantage was that we worked with the same contractors and subcontractors throughout. The same project managers and foremen sat around the table every week. That helped enormously. As the client, we also kept everything in our own hands. We already had a design, which the architect developed further. We drew up the work schedule ourselves. Our technical services department worked closely with the DCA team.”

The surgical and medical day hospitals and 1 nursing ward have also moved into the new building.
“Working quickly is not a given, though, because a hospital has to operate 7 days a week, 24 hours a day. Construction work generates a lot of noise, which affects both hospital operations and patients. For example, I regularly had the work stopped for a few hours to give patients some peace and quiet.”
Cheerful colours, homely rooms
The result? It is certainly something to see. Each floor has its own cheerful colour, which appears throughout the corridors.
That makes it easy to see which floor you are on. Large, wall-sized photographs brighten up the corridors. Visitors and patients can chat quietly in corners where chairs, tables and fitted carpet create a real living-room feel.

‘Modernisation is our top priority’.
The rooms? They are designed like hotel rooms. They have a calm, homely feel. Dark brown woodwork and soothing wallpaper feature throughout. The typical medical services panel is nowhere to be seen. All switches, sockets and connections are concealed in the walls and cupboards. The ceilings contain climate-control beams that combine lighting, heating and cooling. This keeps temperatures to a maximum of 25 degrees, even on hot summer days. Half of the rooms have a patient lift.
‘Innovation leads the way’
Liesbeth Plingers: “The same design features are used throughout the hospital. When we started the master plan in 2008, we deliberately chose to standardise. I am a fan of the KISS principle: keep it simple. Everything we used then to fit out all the rooms has now been used again in Block K. The changes we have made are driven by how the spaces are used, new legislation and useful technological innovations. For example, Block K is the only building with fire detection in the suspended ceilings, as this has been compulsory since 2018. We also use energy-efficient LED lighting throughout the building. And at the patients’ request, we have equipped the double rooms with 2 televisions and digital TV. In time, we will extend all of these features to the entire hospital.”
Question about this story? Ask your question
Who worked on it
K-blok in Laakdal
- contractorDCA
- clientAZ Herentals