Building next to the ambulance entrance
Text Tjerk van DuinenImage Bouwbedrijf Kreeft

Expansion with operating theatres for Meander Amersfoort
An extension was built at the rear of Meander MC in Amersfoort in just one year, providing space for three operating theatres, the Cardiac Care Unit and the First Heart Aid department. General operating theatres and an ophthalmic operating theatre have been relocated from Meander Baarn, which will now provide outpatient care only. As with all hospital construction projects, this was no simple task. Additional challenges included the site being right next to the ambulance entrance leading to the Emergency Department. New openings also had to be made in the existing 30 cm-thick concrete walls.

One important reason for the new building was to enable more efficient working. The move brings all surgical care together in one building. Day-case and inpatient procedures will mainly take place in the new building, while complex care and emergency treatment will be carried out in the 10 existing operating theatres in the adjacent building. Meander project manager Peter Verwoerd: “This wasn’t decided in one go. Everyone has to work together, while things keep changing. One factor was that we could not secure sufficient support for retaining inpatient care in Baarn, and the ophthalmology operating theatre needed refurbishment. A nursing building that became available at Meander Amersfoort was another option. In the end, efficiency was the deciding factor. A central location in Amersfoort, next to the existing operating theatre complex, means short lines of communication and having all your staff, supplies, sterilisation facilities and so on together in one place. It also means the operating theatre refurbishment can be included. The nursing home proved unsuitable, incidentally, because its ceilings were too low. The Baarn site will now focus entirely on outpatient treatment.”

An extension in keeping with the existing style
The new building is a three-storey block raised on columns. The Cardiac Care Unit and First Heart Aid department are on the ground floor. One floor up are a general operating theatre, a hybrid operating theatre, a combined theatre for eye surgery and an ophthalmic day centre. All the building services are on the top floor, particularly the ventilation systems for the building and operating theatres, along with a spacious staff break room. Parking spaces have been created in the basement. Atelier Pro, architect of the existing complex, designed the extension in the same style, with a masonry outer leaf, continuous façade bands and large aluminium windows.

Ambulance traffic
The construction project was a complex undertaking that took two years to prepare. Verwoerd: “It starts with drawing up a Schedule of Requirements, prepared with our own working groups, consultants and Atelier Pro. Input from the contractors then goes into the specifications. In the end, the biggest challenge was the limited space and the site’s location next to the ambulance entrance to the Emergency Department.” Gert van Driesten, director at Kreeft Bouw, says that site manager William Nab had to deal with this every day: “The access road had to remain clear at all times, and beforehand there were concerns that an ambulance might arrive just as a concrete mixer was turning around. A traffic marshal and excellent cooperation with Meander helped us manage this. There was also very little room for logistics, so we kept storage to a minimum and used just-in-time deliveries.”

Sawing
The extension was designed as a stand-alone structure. To support it, 60 grout piles, each 19.5 metres deep, were screwed into the ground without causing vibration. These support a base made of in-situ concrete columns, with an in-situ concrete cross-bracing structure at the sides.
Van Driesten: “The cross-bracing is an aesthetic addition, but otherwise it is a functional, extra-heavy-duty load-bearing structure made of concrete and reinforcing steel. The floors are made of prefabricated walls and columns and wide-slab floors. Steel UNP beams were fixed to the existing outer wall, so thick concrete beams were not needed there. The windows in the outer wall had already been bricked up. Over two weekends, new openings were sawn into it: two for the Cardiac Care Unit and one by the operating theatres. We scheduled this challenging sawing work at a very early stage and prepared it thoroughly, using dust screens to seal off the existing section, which remained operational. Three openings were cut into the almost 300 mm-thick wall.”
Fit-out at breakneck speed
Once the shell was complete, building services contractor Bectro could begin installing the extensive range of systems. Van Driesten: “There was no room in the existing building, so all the systems for the extension had to be fitted beneath the new roof. A dedicated room was created in the plant room for the Philips equipment. This meant only a minimum of additional service penetrations and drilled holes were needed to connect to the existing complex. The fit-out was also our responsibility and went very smoothly (‘Incredibly fast’, according to Verwoerd), despite a large number of contractors working on site at the same time. This included specialist hospital systems from companies such as Philips, Heineman and Mach, which demand a high level of cleanliness throughout the building. The hybrid operating theatre has lead-lined plasterboard walls, which are always a concern because you only know whether they are radiation-tight once the tests have been carried out. In this case, they were.”
Hybrid operating theatre
The new section of the operating theatre complex was brought into use on the planned date. Verwoerd: “As we speak, operations are taking place in the state-of-the-art operating theatres. Ophthalmology has a standard theatre, with the addition of the microscope brought over from Baarn. The hybrid operating theatre is of course the most complex, with a C-arm for producing 3D images. In January 2022, we began the detailed fit-out of the operating tables and the precise positioning of the pendants and lights. Above the tables is the Opragon system, a temperature-controlled ventilation system in which the air outlets are concealed in spherical diffusers set into what we call ‘canoes’ (named after the sweet biscuits, ed.). Bender panels are built into the walls to control, among other things, lighting, operating theatre alarms, the resuscitation call button and air treatment. What struck me most was that the lighting in the new building is even better. LED technology has advanced considerably, and the lighting can be controlled entirely through software, using programmable presets.”
The new operating theatres are now running at full capacity. “Cataract operations are already being performed one after another in the eye clinic. Anaesthetic drops in the waiting room, a short wait, treatment in a chair, and ten minutes later the patient is already back out of the treatment room. It’s wonderful to see,” Verwoerd concludes.
Question about this story? Ask your question
Who worked on it
Meander MC Amersfoort in Amersfoort
- ClientMeander MC Amersfoort
- DesignAtelier Pro
- ConstructionKreeft Bouw
- Building servicesBectro Installaties
- FacadesGevel Design Beek BV
- FacadesMetselgilde Veenendaal BV
- Afbouw/interieurRuitenbeek Projektafbouw
- Afbouw/interieurRikkert Afbouwgroep BV
- Afbouw/interieurG&S Project BV
- Afbouw/interieurVitriwand Systeemwanden
- Afbouw/interieurGijs Zwart interieurbouw
Keep following this
Get an email when a new story is published. No account needed.
- ProjectMeander MC Amersfoort
- SubjectHospitals
- CompanyMeander MC Amersfoort
- CompanyAtelier Pro
- CompanyKreeft Bouw
- CompanyBectro Installaties
- CompanyGevel Design Beek BV