Building on Roman history: transparent and solution-focused

De polikliniek is gebouwd op de resten van een Romeinse nederzetting (en op de kelder van het oude zusterhuis).
De polikliniek is gebouwd op de resten van een Romeinse nederzetting (en op de kelder van het oude zusterhuis).

Before EGM’s preliminary design was even ready, Du Prie bouw & ontwikkeling joined the construction team for the outpatient clinic in Voorburg. According to Martijn du Prie, owner of the Leiden-based construction company, joining at this early stage is essential to keeping the construction process on track.

Du Prie: “We have considerable experience with hospitals, laboratories and healthcare-related construction, where it is complicated to define everything in advance. For the outpatient clinic, we were already able to prepare cost estimates, request quotations and enter data before the preliminary design was ready. From that point, we worked with the team to develop the detailed design and specifications, making adjustments to ensure they were practical to build and within budget. Whenever we encountered an issue, we shared it with the client. This meant we could work transparently and focus on solutions. That is particularly relevant in a changing healthcare sector.”

The clinic is not an especially complex building. Project manager Hans van Es: “The building itself is a relatively simple, transparent structure, with 68 concrete columns and cast-in-situ floors.” The façades are made up of timber-frame elements with timber cladding, using slats of treated Fraké wood, and an open-pattern glazed wall on the ground floor.

Uplift

The foundations presented a greater challenge. Because the area has UNESCO archaeological status, piling was not permitted, so the building had to be constructed on the existing basement structure of the nurses’ residence. Van Es: “To prevent the basement structure from floating up when the nurses’ residence was removed, we filled it with water before demolishing the old building. It was not until the new first-floor slab had been cast that there was sufficient counterpressure to pump out the basement. The building has a larger footprint than the demolished nurses’ residence, projecting 2.5 metres on the long sides and more than 6 metres at the ends.” 

Airtightness

Du Prie was also responsible for the interior fit-out. “There were no structural complications, as the Bucky was the heaviest piece of equipment. In the fit-out, we took account of the laboratory’s airtightness requirements and installed lead shielding in the walls of the Bucky room. Most of the building services have been concealed in the plant room on the roof.”

“But even when it looks straightforward, you need to know what you’re talking about,” Du Prie concludes. “Even if you don’t understand how a piece of equipment such as a scanner works, you still have to take account of the conditions required for its use. If you specialise in this kind of work, you are much better placed to keep the client’s objectives in view and maintain quality on a limited budget. Even during the coronavirus pandemic.”     

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectHospitals
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.