High-quality care in a welcoming setting

An outpatient clinic, a surgical day hospital with two digital operating theatres, a medical imaging department and an out-of-hours GP service: the new medical centre has given AZ Vesalius in Bilzen’s range of care a further major boost.
Built under a DBM contract, the forward-looking complex opened its doors on 16 March. The medical centre stands out not only for its state-of-the-art healthcare facilities, but also for its welcoming look and feel, generous natural light and efficient logistical flows.

Providing high-quality care in a building dating from the 1960s is an almost impossible task in an era of rising expectations for comfort, rapid technological progress and increasingly stringent standards. This had become clear in recent years at the AZ Vesalius medical centre in Bilzen, which was in a very poor state of repair. As every renovation or upgrade brought additional costs and complications, the City of Bilzen also realised that a replacement building was urgently needed to bring the hospital site into the 21st century. A brand-new medical centre with three above-ground floors and a usable floor area of 3,850 m2 was therefore built opposite the existing complex. Patients can visit GPs and specialists for consultations, undergo radiological examinations and have blood tests, or attend for day-case surgery and procedures at the pain clinic. A 44-space underground car park and bicycle parking complete the picture.

Shell operating theatre adds flexibility
Five consortia submitted bids to build the new medical centre. The contract was ultimately awarded to the team comprising Gortemaker Algra Feenstra (architect), STRABAG Belgium (main contractor), De Klerck Engineering (building services engineering consultant) and SPIE (building services subcontractor). “We were interested in working with a renowned architectural practice from the Netherlands, where healthcare is viewed from a different perspective,” says Marc Jackmaert, facilities director at AZ Vesalius. “Natural light, both in waiting rooms and consultation rooms, and the separation of the different logistical flows (patients, goods, staff, clothing, etc.) were key considerations. The medical centre has also been designed with the potential future construction of an adjoining building in mind. The two facilities could be structurally connected via the underground car park. We were also very interested in the consortium’s proposal to build a third operating theatre as a shell, alongside two fully equipped theatres. This third space is currently used for storage, but can be converted quickly and efficiently into a fully functioning operating theatre if needed. This significant advantage helped tip the balance when the project was awarded.”

DBM contract
AZ Vesalius opted decisively for a DBM project. This was a notable choice, as the model is not yet widely used in the Belgian healthcare sector. “We appreciated having a single party manage the entire construction project,” Jackmaert explains. “In turn, this gave the architect, contractors and engineering consultant greater freedom to develop innovative, efficient and cost-effective solutions within the specified requirements. They used BIM, which led to better coordination between the design and construction teams. The DBM process also guaranteed a shorter lead time, as the design and construction phases were integrated. And since the consortium is also responsible for maintenance, there was an even stronger focus on quality and durability. On the other hand, as the client, we naturally had less control because there was no extensive preliminary process. It took some getting used to at first, but in retrospect our assessment is certainly positive!”
Digital operating theatres and CBCT scans
Patient wellbeing is central to the new medical centre. This is reflected in its open, contemporary design, which immediately puts visitors at ease. The many windows provide a strong connection with the outside world, while climate ceilings ensure thermal comfort. Together, these features create a pleasant, tranquil care environment that is also highly advanced in terms of healthcare technology. “The digital operating theatres are equipped with UHD surgical displays linked to top-quality 4K surgical monitors, enabling surgeons to operate in optimal conditions. The associated administrative processes are, of course, fully digital too. The medical imaging department offers not only mammography and routine CT scans, but also CBCT scans, which require a lower dose of X-rays. These can be used, among other things, to produce a 3D image of the jaw, or parts of it, and the surrounding tissues,” Jackmaert explains.

Structural flexibility
Another major advantage of the new medical centre is its structural flexibility. The load-bearing structure, comprising 2,920 m³ of concrete and 270 tonnes of reinforcement, has a beamless design and is fitted with non-load-bearing partition walls. “This makes it much easier to reconfigure the spaces and adapt the building services as care evolves. Provision has also been made for potential future openings and service penetrations. A possible expansion of the operating suite has also been factored in,” says Jackmaert. “Construction took fifteen months, excluding two months of stoppage due to the coronavirus crisis, which certainly made things more difficult. From the first ‘lockdown’ onwards, all site meetings and consultations took place via webinars, as the Dutch architectural practice found it difficult to travel to the site under the prevention measures in force. It was no easy task, especially as we were still at the shell-and-core stage, but aside from a few adjustment issues and teething problems, the process went fairly smoothly. Both doctors and patients and visitors have praised the end result, which is naturally very gratifying. The new medical centre is a successful first step in the further development of the entire hospital site!”
Een zakelijke vraag aan Gortemaker Algra Feenstra architects? Get in touch
Who worked on it
AZ Vesalius Bilzen medical centre in Bilzen-Hoeselt
- architect
Gortemaker - clientAZ Vesalius
- main contractorSTRABAG Belgium
- building services consultancyDe Klerck Engineering
- onderaannemer techniekenSPIE
Keep following this
Get an email when a new story is published. No account needed.
- ProjectAZ Vesalius Bilzen medical centre
- SubjectHospitals
- CompanyGortemaker Algra Feenstra architects
- CompanyAZ Vesalius
- CompanySTRABAG Belgium
- CompanyDe Klerck Engineering
- CompanySPIE