Lean construction for the Netherlands’ first all-electric hospital

Het gebouw valt volgens de ontwerpers weg in de landelijke omgeving.
Het gebouw valt volgens de ontwerpers weg in de landelijke omgeving.

The new building for Isala Diaconessenhuis and Zorggroep Noorderboog in Meppel is attracting national attention: a gas-free regional hospital with a rehabilitation clinic, designed according to lean principles and built efficiently. With construction of the new medical complex in the ‘elbow’ formed by the A28 and A32 motorways, people from the wider Meppel area will be able to use one of the most modern hospitals in the Netherlands from the second quarter of 2022.

Alongside various rooftop installations, the hospital has a roof garden.

“We built this hospital in 2 years, in line with the schedule,” says Adri van Veggel (managing director, Dura Vermeer Bouw Hengelo), speaking on behalf of construction consortium TDE. In addition to delivering the project, TDE, comprising Trebbe, Dura Vermeer and ENGIE, is responsible for the maintenance and operation of the new building for a period of 25 years.

The facilities were completed in late 2021.

Minimised circulation areas

The hospital has a gross floor area of 17,583 m²; Noorderboog’s geriatric rehabilitation clinic has 64 inpatient places and covers 5,337 m². The buildings for Isala and Noorderboog were constructed as a single complex, alongside the old hospital. “It was designed according to lean principles, meaning minimal circulation areas and walking distances for patients and staff,” Van Veggel continues. When it opens later this year, the new hospital will meet the highest standards for comfort, patient-friendliness, sustainability, hygiene and flexible use of space, according to the builders. Isala Meppel will thus become the Netherlands’ first all-electric hospital.

Aquifer thermal energy storage

Architectural practice Vakwerk designed the hospital in collaboration with engineering consultancy Deerns. Facilities will include a 7x 24-hour Accident and Emergency Department, an operating theatre complex with 4 operating rooms and 1 treatment room of operating theatre class 2, a 100-bed inpatient ward and 24 day-care beds, as well as facilities for dialysis, ophthalmology, laboratory spaces, radiology and nuclear medicine. Sustainability plays a major role in the design: the building has no gas connection and runs on solar panels and aquifer thermal energy storage. It is a ‘smartly designed hospital with highly reliable operations’, built using a relatively traditional construction method.

Efficient construction

TDE delivered the design by Vakwerk Architecten. Royal HaskoningDHV was the structural engineer for the Definitive Design; Lucassen is the design development structural engineer on behalf of TDE. “The building was contracted at Definitive Design stage and developed within the construction consortium into an Execution Design, meaning that optimisation was limited to the choice of materials. Our relationship with the hospital within the construction organisation was direct and ran smoothly.” Naturally, extensive provisions were made for the sustainable building services, and structural elements such as the operating theatre complex required extra attention. However, these presented no particular issues in the Execution Design, says Van Veggel.

A green hospital

The construction method is based on pile foundations on sandy soil, a mix of precast and cast-in-situ structural elements finished with anhydrite screeds, and aluminium folded sheet metal and profiled cladding (Aluform) as the main external finish. Most internal walls are made of metal studs. In addition to various rooftop installations and structures on the separate building sections, Isala/Noorderboog has a green roof garden on the shared podium. The architects drew inspiration from the surrounding landscape. In the new hospital, patients are surrounded by daylight and have views over the nearby Reestdal.

Maintenance

The first foundation pile was driven in February 2020; both facilities were completed in December 2021. “The schedule went entirely according to plan,” says Van Veggel. The hospital is expected to be ready for occupation in mid-March 2022. TDE will then remain responsible for building fabric and building services maintenance for another 25 years, while ENGIE will ensure the energy performance of the Netherlands’ first all-electric hospital. “In two years, we delivered a fully functioning building ready for occupation. It is a compact complex, both in design and in execution,” Van Veggel concludes.     

Question about this story? Ask your question

Wie aan Isala Meppel werkte

  1. architectVakwerk ArchitectenMentioned in Isala Meppel: one of the most sustainable hospitals
  2. engineering consultancyDeernsMentioned in Isala Meppel: one of the most sustainable hospitals
  3. construction consortium TDETrebbeIn this story
  4. construction consortium TDEDura VermeerIn this story
  5. construction consortium TDEENGIEIn this story
  6. structural engineerRoyal HaskoningDHVIn this story
  7. structural design engineerLucassenIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectIsala Meppel
  • SubjectHospitals
  • CompanyTrebbe
  • CompanyDura Vermeer
  • CompanyENGIE
  • CompanyRoyal HaskoningDHV
  • CompanyLucassen
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.