Team harmony is crucial to success
Text Sabine BisonImage Dijkxhoorn Bouw

Tight schedule met for First Cardiac Emergency department refurbishment
The DNA of The Hague-based contractor Dijkxhoorn bouwgroep is rooted in building and refurbishing hospitals. The company was awarded the contract to carry out a major refurbishment in a very short time: connecting the First Cardiac Emergency department (EHH) to the Emergency Department (SEH) at Haaglanden Medisch Centrum (HMC), Westeinde site in The Hague.
“Part of the First Cardiac Emergency department, a specialist emergency department for patients with acute heart problems, was originally located in the hospital building itself,” says project manager Stefano van Veen. “To improve this service and get patients to the right place more quickly, we were asked whether we could move the department to a site directly next to the Emergency Department. In practical terms, this meant stripping the area next to the existing Emergency Department back to the concrete and building eight fully equipped treatment rooms in its place. This will enable the First Cardiac Emergency department and the Emergency Department to work together efficiently.”

A major logistical puzzle
“The biggest challenge was not necessarily the work itself,” explains Van Veen. “It was the location and the short timeframe that made things tense. We had to work alongside one of the largest Emergency Departments in the Netherlands, which operates 24/7. There were also several outpatient clinics on the other side. That meant few quiet periods and a great many visitors. All materials had to be transported through this busy area. How could we do that while causing as little disruption as possible, particularly from dust and noise? It was quite a puzzle. We arranged most of our deliveries and collections before 07:00 or after 17:00. All materials were transported to and from their designated locations in sealed containers.”

Getting to work
The refurbishment began at the end of October 2023. Handover was scheduled for just 14 weeks later, so that the first patient could be seen two days after that. There was no time to lose. Van Veen says: “We deliberately looked at reusing materials in advance, for example reusing parts of the ceiling system and ceiling tiles. We then installed soundproof walls, floors, frames and doors. Specialist subcontractors handled the electrical work, water supply, air conditioning and medical gas systems, such as oxygen and medical compressed air. These are systems that you cannot and would not want just anyone to work on. We have been working with some of these subcontractors for 30 years.”
Dijkxhoorn bouwgroep also offers a unique service: it has its own in-house workshop. “For this project, we made and installed the bedhead panels and kitchenettes ourselves, based on a design by the regular architect who works with HMC. This also saves time in the schedule. Everything is made from materials that are easy to clean.”

A top team
Although the schedule initially looked like a major cause for concern, the project went smoothly and the deadline was met. “If only every project went like this,” laughs Van Veen. “I can put it down to one thing: harmony within the team. It is crucial to this success. Thanks to our expertise in the hospital sector, we no longer have to explain things to our people. Many challenges were resolved among the team, and at the end of the day I would get just one phone call with an update. Every single party was determined to meet the tight schedule, from subcontractors and the client to the consultant and architect. And, of course, our own people. That is one of the major benefits of working together often and over a long period: you know exactly what to expect from one another. It doesn’t get any better than that. I am incredibly proud of this top team.”