Working within existing constraints
Text Tjerk van DuinenImage CCG/RGB Producties

Six new operating theatres for OLVG Oost
Two years after two hybrid operating theatres were commissioned, OLVG Oost has recently added six new standard operating theatres. All eight are part of a major programme of renewal. As a result, OLVG’s Oost and West sites are increasingly developing distinct identities: OLVG West focuses primarily on 24/7 acute care, while Oost is chiefly a centre for minimally invasive surgery. The six latest operating theatres were delivered by a design and build team comprising EGM, Royal HaskoningDHV, Van Wijnen Lelystad, CCG, ULC and Kropman.
Space is often a problem for hospitals, but the situation at OLVG Oost is particularly acute. It is a city-centre site with no room to expand, so everything has to fit within the existing walls. A creative solution was devised for the two hybrid operating theatres: they were suspended above two outpatient clinic areas in the three-wing operating theatre complex on Eerste Oosterparkstraat. Space remained tight. The six new units were ultimately built in wing B, which had previously housed four operating theatres, a recovery room and a day treatment unit. “Together with the eight existing operating theatres in wing A, this meant that the required capacity of ten theatres was always available,” explains Milan Cuylits, Project Manager at OLVG Vastgoed. “Wing B was stripped back to its shell for the new facilities, apart from a few vital service pipes. A temporary structure was built in the courtyard to accommodate the recovery room, sterile store and changing rooms. This allowed the day treatment unit to be located where the old sterile store had been.”

Preparation
OLVG developed the brief for the six operating theatres with Royal HaskoningDHV (technical) and Roubos OK Expertise (functional). “On that basis, the design and build team got to work on the preliminary and detailed design stages,” Cuylits continues. “The consultants and architect EGM led those stages, with the construction contractors already involved. During the technical design and construction design stages, the contractors led the development of the technical and construction plans, with the consultants in a supervisory role.” The result is an efficiently laid-out first floor, with the six standard operating theatres at the centre of wing B, each with its own instrument preparation room, as well as a baby care room, storage for goods and equipment, and offices. The two hybrid operating theatres are suspended above the outpatient clinic areas on either side of wing B. “Everything directly needed for an operating theatre centre is on this floor,” says Letty Koopman, OLVG’s operations manager. “The only journey involving a move between floors is the route to the inpatient ward, which requires using the lift.”
More spacious
At over 49 and 58 m2, the new operating theatres are considerably larger than the old ones. This has been a trend for some time, according to Koopman, and represents a major improvement for OLVG. “Equipment is getting bigger and more numerous. Think of service pendants, surgical robots and all the screens and consoles, sometimes duplicated for trainee assistants. Everything is either suspended from the ceiling or built into the walls, so you won’t see cables running across the floor. Ideally, you want to keep the room as clear as possible, with only a surgical robot left in the operating theatre. The larger theatres are for robotic and cardiac surgery. Operating theatre 102 is directly connected to a baby care room where resuscitation can be carried out if necessary.”

Mock-up
The operating theatres themselves were planned down to the position of every socket, in collaboration with the design and build team and with input from operating theatre staff. Koopman: “We built full-scale mock-ups and worked through every possible scenario to determine the optimal positions for doors, service pendants, Bender panels and the operating table. We had to work with an existing column grid (6.60 by 6.60 m; ed.), which makes a mock-up especially useful for learning and assessing the risks of every scenario. Why isn’t there a standard operating theatre solution? Because everyone wants to put their own spin on it. We have to take into account specialists’ ideas, the prevailing culture in a hospital, approaches to hygiene and guidelines. And in this case, the existing grid as well.”

Minimising disruption
Working in an existing, operational hospital also required careful planning by Van Wijnen. “It’s complex, yes,” says Arnold van der Werf, project manager for the contractor from Lelystad, “but as an experienced hospital builder, we know how to carry out our work almost unnoticed. Shortly after the two hybrid operating theatres were commissioned, we started by installing dust screens and soundproof panels to seal off the work area and put it under negative pressure. The areas next to the work site, the two hybrid operating theatres, are already under positive pressure, so the work area is automatically under negative pressure. The logistical challenge was that we had no access via the façade. All movements had to go through an existing shaft from the plant floor, then over the roof and on to Eerste Oosterparkstraat, where the site cabins and lift were located. For demolition work, we used a quiet, electric mini excavator with a breaker. To keep disruption to a minimum, we agreed set working hours with OLVG, because even drilling a small hole for a plug can be too much. During critical activities in an operating theatre, the client could ask for work to stop temporarily. Thanks to good communication and close cooperation, everything went well.”

Collaboration
Van Wijnen installed all the metal stud base walls within the existing shell, created the required new openings in the shell and modified the plant room on the second floor. Van der Werf: “In other words, we did all the groundwork to enable the building services contractors to do their work and CCG to construct the room-within-a-room. Throughout the project, we worked very well with all the partners in the design and build team, with the shared aim of achieving the best possible result. It wasn’t a huge project, but when you consider that construction took two years, you can see how complex it was.”
RembrandtOK
OLVG is very pleased with the new operating theatres. Cuylits: “You build something like this based on the latest insights and technologies, with the next fifteen to twenty years in mind. We no longer use a traditional UDAF plenum, for example, but Avidicare’s TcAF Opragon system for ventilation. The system has two rings of ceiling-mounted spheres that ensure ISO class 5 conditions throughout the operating theatre. The theatres can also switch between operating theatre class 1, performance level 1 and operating theatre class 1, performance level 2. In the latter mode, 50% less air is required, which brings substantial savings. Between 19:00 and 07:00 and at weekends, the ventilation system automatically reduces output to 30%, then ramps it back up if a patient is admitted during that period.” Koopman is very pleased with the Krion® walls. “This is fairly new and is also used in the hybrid operating theatres. It looks good, is easy to clean thoroughly and is chemically resistant. The panels can be heat-bonded: sand them down and you can no longer see the join. As a result, there are only two sealant joints in the walls of each operating theatre. The floors have a semi-conductive PVC finish with coved skirting. One final plus is the cheerful colours on the outside. EGM and the operating theatre staff worked together on this, ultimately choosing Amsterdam scenes and works by Amsterdam artists, rendered as graphic designs. Staff have already started calling operating theatre 103 the RembrandtOK.”
Facts and figures
Client:
OLVG
Design and build team (design, consultancy, construction):
EGM, Royal HaskoningDHV, Roubos OK Expertise, Van Wijnen Lelystad, CCG, ULC, Kropman.
Construction management:
OLVG, Project Management Department
Construction period:
July 2022, April 2024
Gross floor area:
1,320 m2
Een zakelijke vraag aan CCG Holding? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectHospitals
- CompanyCCG Holding
- CompanyVan Wijnen