A construction team is key to the successful delivery of cleanrooms

“Building cleanrooms requires thorough preparation and extensive consultation during the works. This can only be achieved with a construction team that works very well together,” say Peter Deneut, architect-engineer at VK Architects & Engineers, Pascal Vercammen, director of Comtec, and Nancy Duchi, project manager at Wycor. Electro Entreprise (electrical), Cegelec (ventilation), CSB (finishes), Szapinsky (plumbing), Heyer (medical gases), Advipro (validation) and ACMV (health and safety coordination) were also part of the construction team.
“Based on a statement of requirements, the Ministry of Defence issued a tender for the construction of a state-of-the-art cleanroom at the Military Hospital in Neder-over-Heembeek. The VK-Wycor construction team was selected as the winner. We had previously also been commissioned to build the new burns centre. The Military Hospital is a European centre of excellence for the treatment of severe burns. The cleanrooms are used for tissue and cell culture. The cleanroom fit-out is fundamental to providing high-quality human tissue for the treatment of severe burns and chronic wounds.”
Equipment
The project involved four GMP Class B cleanrooms, with the necessary airlocks and corridors to act as separation zones, and essential adjacent spaces such as sterile rooms, specially adapted access points and storage areas. The cleanroom equipment includes laminar flow cabinets, storage, sterilisation and incubation equipment, and technical equipment. Each of the four rooms has an area of 25 m²; the whole project required an area of 1,000 m². All the cleanrooms have identical finishes. Two cleanrooms are in use, while one serves as a back-up. Whereas most cleanrooms have no natural light, staff in the cleanrooms at the Military Hospital enjoy attractive outdoor views through large windows. Only a limited number of people have access to the critical areas. Security is provided by CCTV and badge-based access control.
Working in reverse
“Unlike a ‘conventional’ construction project, we worked in reverse order. First, we installed the building services and air ducts, followed by the cleanroom ceiling and then the openings for the light fittings. We then completed the fit-out, including compact laminate walls, door frames, glazing, PU flooring, doors and furniture. We installed the plinths first, then laid the floor. Cleanrooms are working environments with stringent limits on the maximum levels of airborne particles and bacteria. One of the design principles is to minimise internal corners. This reduces the risk of stagnant air and dust build-up. By achieving a particularly flat, smooth finish, also known as ‘flush’, contamination is kept to a minimum.”
Keeping an overview
“As mentioned, a construction team is essential for a project of this kind. Each member brings specialist knowledge to the table. VK prepared a preliminary design, which the other team members developed, and this formed the basis of an overall plan. The proposed design served as the basis for drawing up the requirements. Thorough preparation limits the risk of cost overruns, and the margin for error is very small. This is therefore the stage at which the foundations for a successful project are laid. Above all, it is important to keep an overview and take one another’s needs into account. The weekly meetings with the Ministry of Defence and the end user, followed by feedback to the construction team, were part of this approach. Construction took a year, and the project was completed in February 2015. The Ministry of Defence then went on to draw up the procedures to be followed. The construction team’s final task is to inform the FPS and arrange an inspection,” conclude Peter Deneut, Pascal Vercammen and Nancy Duchi.
Text: Bert Verbeke
FACTS AND FIGURES
Client Ministry of Defence, Brussels
Construction VK and Wycor construction team, Brussels and Wetteren
Een zakelijke vraag aan VK architects+engineers ®? Get in touch
Who worked on it
Cleanrooms at Militair Hospitaal in Brussel
- voorontwerp
VK Architects & Engineers - BouwteamWycor
- elektriciteitElectro Entreprise
- ventilationCegelec
- finishingCSB
- sanitary wareSzapinsky
- medische gassenHeyer
- validatieAdvipro
- veiligheidscoördinatieACMV
- ClientMinisterie van Defensie
Keep following this
Get an email when a new story is published. No account needed.
- ProjectCleanrooms at Militair Hospitaal
- ThemeHospital construction and refurbishment
- SubjectGeneral
- CompanyVK architects+engineers ®
- CompanyWycor
- CompanyElectro Entreprise
- CompanyCegelec
- CompanyCSB