AZ Sint-Lucas Gent brings its campuses together in new care wings

AZ Sint-Lucas Gent brings its campuses together in new care wings

At AZ Sint-Lucas, they do not like to stand still. In recent years, there have already been several relocations as part of efforts to renovate and modernise parts of the hospital. The current construction project, involving the refurbishment and extension of Block C and the new Block W, together covering around 22,000 m², will among other things replace the Volkskliniek campus, which will be converted into a residential care centre.

We like to move it!

In de gangen van de operatiekamers van Nij Smellinghe wordt veel gereden met bedden en karren. Om schade aan de wanden te voorkomen, is ervoor gekozen om de wanden te beschermen met M-Wall Hygienic.

Day hospital (Image: Johan Martens)

The original master plan for AZ Sint-Lucas in Ghent was put into action in 1998 and revised in 2004 to incorporate the merger of AZ with the Volkskliniek. “The plan was to build new Blocks W and K under the VIPA framework. The Flemish Government approved the plans, but was unable to provide financial support for the project because of budget cuts,” explains Danny Van Hove, head of infrastructure and construction coordinator. “Since all hospital functions have to move out of the Volkskliniek campus and we want to bring all activities together on the AZ Sint-Lucas site, we developed a Plan B. We are using our own funds to build a new Block W and refurbish Block C. The use of Block W is now different from what was envisaged under the VIPA project, but the focus is still on day hospital activities.”

De wandbekledingen van M-Wall zijn onder andere toegepast in Nij Smellinghe.

Geriatrics. (Image: Johan Martens)

Day hospitals and more

The existing Block W made way for a new building measuring 50 by 50 metres, enclosed by the hospital’s existing buildings, a school, a square and a public road. The seven-storey building accommodates the day hospital for internal medicine, infusion therapy, the oncology day clinic and pain clinic, geriatrics with a day hospital and consultations, the surgical day hospital and operating department, palliative care, and the inpatient ward for chronic illnesses. The first departments moved into the ground and basement levels of the new wing in the middle of last year. The other floors are being completed and will open in the spring. “Each floor is designed around the needs of the department in question, and the spaces are flexible enough to be adapted easily for a different use in the future,” the head of infrastructure continues. “Strict monitoring of the schedule and budget is crucial to the
successful delivery of this project. What is more, construction is continuing in a wing where there is a great deal of activity every day. Day hospitals treat thousands of patients each year.”

kamer-nog-in-inrichtingsfase-op-2e-verdieping-met-sanitaire-cel_p1040958-kopieren

Room still being fitted out on the 2nd floor, with en-suite sanitary facilities.

Functional layout focused on patients and staff

The comfort of patients and staff was a key consideration when laying out the different floors. Calm white and light grey tones, along with wooden flooring, feature throughout. On the ground floor, patients come for infusion therapy, excluding chemotherapy, and sit in one of the private bays, each with an armchair and television. The bays are separated by a half-height partition, so patients do not feel completely ‘shut in’.

“After registering at the day hospital, patients first wait in a waiting room before being taken to one of the compact rooms. Just before their procedure in one of the two operating theatres, they are transferred on their bed to one of the five preparation bays, where they can get changed. The bed is fitted with a specially designed patient case for personal belongings. After treatment, patients spend a short time in a small recovery area before returning to their room, if necessary, and then going home or moving to another department,” explains project engineer Rik Casier. “The rooms, which benefit from plenty of natural light, are designed according to our SLiM room concept (Sint-Lucas Innovative Model Room). They contain a bed fitted with a table and chair, a TV and a small, lockable en-suite sanitary area with a toilet, washbasin and shower.”

koffertje-dagziekenhuis_foto-az-sint-lucas-kopieren

Day hospital case.

Other floors under construction

From the first floor upwards, the different spaces are arranged around a central patio, which provides much-needed natural light. The rooms are located on the outside of the building and look out over the surrounding area. Contractors are still hard at work on floors two to five. The geriatrics department on the second floor is due to open shortly. The entrance features a reception desk and a central waiting room, screened off by vertical wooden slats. The floor contains a range of single and double rooms with tall vertical windows, fitted with centrally controlled fabric blinds. As on the ground floor, the SLiM concept has been applied to the rooms. The position of the bed enables patients to reach the en-suite sanitary area without much assistance. Bespoke fixed wooden furniture and the concealment of hospital equipment wherever possible create a homely atmosphere. This floor also includes a geriatric day hospital with six positions and its own nursing station, where a large curtain wall lets in plenty of light. On the other side are four consultation rooms with their own secretarial area and waiting room.

geriatrie2_foto-johan-martens-kopieren
Het volledig ingerichte model kan ook gebruikt worden om toekomstige gebruikers te laten zien hoe hun nieuwe afdeling eruit komt te zien.

Geriatrics. (Image: Johan Martens)

“The third floor will house the surgical day hospital, with a preparation room containing eleven positions, five operating theatres, a recovery area, a range of single and double rooms, and a day room with six positions. A companion can wait in a lounge during the procedure. In this day hospital, the conventional room-based call system is being replaced by a wireless system linked to the bed. The beds are also fitted with patient cases,” concludes Van Hove. “The fourth floor will have twelve beds for palliative care, as well as a spacious veranda and outdoor terrace where patients can enjoy the fresh air. Finally, work is under way on the top floor to create an inpatient ward for patients with chronic illnesses.”    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBlok W
  • ThemeHospital construction and refurbishment
  • SubjectGeneral