Designing hospitals with BIM:

Translating and testing expectations.
For Wiegerinck, designing with BIM comes naturally. This is a valuable asset for a practice that is highly active in healthcare and has a number of high-profile hospitals on its project list. Examples include the Amsterdam UMC Imaging Center, Amphia in Breda, the Oncology Centre at University Hospitals Leuven and the Tergooi Hospital in Hilversum, which is currently under construction. Each is a complex project where BIM is not only an indispensable design tool, but also the ideal way to coordinate and visualise the entire design with all partners in the construction chain.

Wendy van Rosmalen, project manager at Wiegerinck, also observes (see the preceding article on TNO) that making optimum use of BIM starts with a client who has a long-term vision and sees the bigger picture. “You need people who dare to look ahead. That allows you to implement BIM systematically, so that in time you can use it throughout the entire management process. Using BIM systematically is particularly worthwhile for hospitals, with their large amount of complex and often highly specialised property, as it can provide a basis for management and maintenance. The same applies to our clients in education and research.”
BIM in the design phase: testing against requirements and aspirations
At Wiegerinck, expectations play an essential role in the design phase. Van Rosmalen: “We involve the client and users in the design process. Healthcare professionals provide very important input. In the past, we would explain and review a design using 2D drawings, such as floor plans and sections. Now we can also show the spatial translation of the design in 3D. We walk through the design together, looking at how, for example, the logistics work, and showing what can be seen from a nurses’ station, how much daylight enters the building, and so on. In effect, we test whether the design meets their wishes and make adjustments where necessary. BIM also enables effective information exchange within the design team and with the client.”
From broad outline to fine detail
The design is also developed in BIM, from broad outline to fine detail. It is important that the shell, primary structure and overall layout of the building services allow for flexibility to accommodate different functions and layouts in the future. Van Rosmalen: “Hospitals need to adapt, although ideally you leave the primary structures untouched. We think about how to group functions intelligently, taking account of how spaces are used and their level of complexity. The design is refined from the primary structure, through layouts, to room-level design. You want to develop in detail the many recurring spaces, such as patient rooms or consultation and examination rooms, as well as complex spaces such as operating theatres. These standard room types are ideal for reviewing with users to optimise the layout. This can go as far as a fully fitted-out room, including building services components and fixed and loose furnishings. BIM is an excellent medium for this. You can show everything and make changes in real time. That gives you the best possible representation of reality and avoids differences in interpretation. Using a browser, BIM 360 gives us an environment where everyone involved can easily view the model without specialist software.”
Tendering in Belgium and the Netherlands
Once the design has been technically completed, the tendering process begins. Van Rosmalen: “That is when you see an interesting difference with Belgium. There, you are required to include quantities in the tender documents, from the amount of concrete to the number of metres of skirting. Here, we aim for maximum transparency by supplying the model as well. Every element is assigned a unique code, so the client and contractor can use a free application to view the model, click on elements and see where they are located. To price the work, the contractor only needs to set the unit prices. This system is very useful and transparent for all parties, and works very well for the construction of complex buildings such as hospitals and laboratories. It also makes it much easier for the client to assess the tender documents. There are fewer queries about quantity measurement, prices are easy to compare and the process runs very smoothly. This is not a requirement in the Netherlands, but we can of course do the same here. What we do see more often here is specification information and quality requirements being added to the model. Our aim is to create a model that remains valuable after the design is complete, during construction, and can be used by the contractor to continue developing the engineering and optimising construction processes.”
Learning from practice
Once the building has been handed over, it enters use. “As architects, our primary task, designing the building, is then complete,” says Van Rosmalen. “But we think it is important to contact the client some time after the building comes into use to ask whether everything meets expectations, whether it functions as designed and whether the design still fits the intended working practices. We are keen to learn from our clients. Our BIM model can be very valuable during the operational phase. The building, its fixed, loose and medical furnishings, and information assigned to each room, such as floor, wall and ceiling finishes, can all be used for maintenance planning. A good as-built model also provides a sound starting point for future modifications. The key is to make that information as useful as possible. Alongside good long-term design, that is where much of the value for the client lies. And creating value for the client is our top priority.”