From a successful move to an efficient improvement cycle

AZ Sint-Maarten opened its doors in Mechelen on 15 October 2018. More than eight months after opening, it is time to look back at the logistical operation. More than 1,500 employees and 200 doctors moved from the three old campuses to their new workplace on Liersesteenweg. Speaking are Nico Garmyn, Director of Quality & Strategy, and Patrick Nieulandt, Director of Nursing and Paramedical Services.
The move and the first months of operation at AZ Sint-Maarten went smoothly. Employee and user involvement from the design phase of the construction project laid the foundations for this success. More than 45 specialist user groups contributed their input to the design. Expert groups also contributed to the composition of the teams and the development of all support and logistics processes. “Those processes had to be completely rethought,” explains Nico Garmyn. “Simply because working practices used at the old campuses cannot be copied in a new building. In addition, extensive participation by doctors, nurses, and technical, logistics and administrative staff was a common thread throughout AZ Sint-Maarten’s relocation project.”

Three years of preparation
The full preparation for the move and opening of the new hospital took three years. First, the processes that were changing were mapped out and redesigned for the new working environment as part of the project. The new organisational structure was then built up step by step. “Two years before the move, all staff knew about the new structure and the associated lead roles,” explains Patrick Nieulandt. “As well as the work schedules and staffing levels available to each team. The next focus was forming the teams: employees listed their top 3 departments and roles. Importantly, our people could opt for an entirely new job. For example, a former employee in the communications department is now head of the care support administration department. Naturally, they could also choose to keep their old role. About 85 per cent of our people got their preferred job, and 93% got a job from their personal top 3. One year before the move, every employee knew where they would be working. Once the teams had been formed, the final stage before the move was staff training. This helped employees become familiar with their new working environment and team members get used to working together before the new hospital opened.”
From relocation to evaluation
“The move itself was also a major undertaking,” says Nico Garmyn. “Of course, a logistical operation of this kind does not go entirely without a hitch. Even so, we can say that everything went exceptionally smoothly, thanks to meticulous preparation by twelve thematic teams covering areas including patient transfers, equipment, installation of medical technology equipment, and the launch of ICT, …. One of the success factors during moving week was a coordination centre staffed by four helpdesk employees, whom all staff could contact to report problems or bottlenecks. In addition, four response teams were on standby to provide support with ICT, logistics, equipment and care. These teams enabled us to respond very quickly to unforeseen problems, which always crop up during a major logistical operation. After moving week, a core group was set up to deal with all outstanding issues. Since March, we have been systematically investigating where internal processes and organisation still need adjusting.”

The existing campuses have been brought together at one new-build site.
The review is being carried out along several different lines. Patrick Nieulandt: “For example, we visit all 75 departments. Staff prepare using a questionnaire as a guide, and on that basis we have an open discussion with the whole team. We ask how they feel the start-up phase went and try to identify the priority areas for improvement. It is, of course, the teams’ own responsibility to deal with their areas for improvement. But there are often matters that are best addressed at hospital level. A second line of investigation is the evaluation of care support, facilities and logistics processes. Think of patient transport, cleaning, the supply of equipment or the distribution of medication. We asked staff to rate these processes. For example, waste management in a department: would you give it 1 out of 10 or 10 out of 10? If someone gives it a low score, we find out why. We then act immediately and in a targeted way on the basis of those findings.”
Digitalisation provides insight
Nico Garmyn: “Many processes at AZ Sint-Maarten have been digitalised, so we have a wealth of data to identify areas for improvement. Take patient transport in the hospital, for example: we know when the request is made, when the patient leaves for the examination, when the request is made to collect the patient again, and how long the patient has to wait. We have already made significant improvements to departure times for the examination departments. At the same time, we see potential to reduce waiting times between the examination department and the inpatient department.” Patrick Nieulandt: “Research and data analysis quickly reveal quick wins. These are areas for improvement that, so to speak, require just one call to the technical department. Such interventions very quickly improve staff satisfaction in the departments concerned. Other matters need to be examined in more depth, and improvements there take more time.”

Nico Garmyn, Director of Quality & Strategy.
Patient satisfaction
“Naturally, we ask patients about their experience of the new hospital. This is also done from several different perspectives. First, there is the satisfaction survey, which is conducted twice a year. The first survey took place in November, shortly after the opening. The second survey has now been carried out, and the results will be available shortly. The AZ Sint-Maarten website is also an interesting source of information, where patients can submit a rating and accompanying comments. This information goes straight to the departments concerned, so that the necessary action can be taken.” Nico Garmyn: “Our third source is the hospital’s complaints mediation service. Immediately after opening, there was a notable increase in the number of complaints. Analysis showed that these were mainly related to the change itself. For example, parking near the old campuses was free, whereas the new hospital has paid parking only. Complaints like these naturally teach us that our communication is very important too.”

Question about this story? Ask your question
Who worked on Campus AZ Sint-Maarten
- architectural practiceVK StudioMentioned in Hospital Special: New build for AZ Sint-Maarten, Mechelen
- structural works contractorMBGMentioned in Hospital Special: New build for AZ Sint-Maarten, Mechelen
- finishesJansen FinishingsMentioned in Contractor MBG draws valuable BIM lessons from construction of AZ Sint-Maarten
- ArchitectTripod architecten (Antwerpen)Mentioned in New orthopaedic outpatient clinic strengthens AZ campus
- Main contractoribens (Antwerpen)Mentioned in New orthopaedic outpatient clinic strengthens AZ campus
Keep following this
Get an email when a new story is published. No account needed.
- ProjectCampus AZ Sint-Maarten
- ThemeHospital construction and refurbishment
- SubjectGeneral