From office space to specialist clinic
Text Desiree Pennings Beeld MoreCare Clinics

Work is currently well under way on the conversion of the building on Printerweg in Amersfoort. This is where MoreCare Clinics’ new clinic will be based, housing its orthopaedic and plastic surgery services. The new location is expected to open as early as February 2026, following a five-month construction period.
After working for many years as a surgeon at a leading teaching hospital, Frits Berends felt that the COVID-19 pandemic was the time to make a new choice. Together with his business partner Edo Aarts, he founded the successful specialist clinic Weightworks in 2021, specialising in bariatric surgery. “Hospitals often have cumbersome structures and operate in a traditional way. They are inefficient: everything takes longer,” he says. Things are different at the private clinic he founded in Amersfoort. The focus is on the patient experience, with processes organised to be as efficient as possible for patients. All of this takes place in a calm, comfortable environment. It offers a genuinely different experience for patients, visitors and staff.

Orthopaedic and plastic surgery
It soon became clear that patients welcomed this personal approach, and two new clinics were opened: Orthocare for orthopaedic surgery and Essenza for cosmetic surgery. All three are part of the umbrella organisation MoreCare Clinics. For now, all the clinics are based at the Ruimtevaart location in Amersfoort. “We’re now short on space. It took a while to find a suitable building for a second location, but we eventually found one on Printerweg in Amersfoort. We carried out the first conversion ourselves, but this time the work needs to be more structured. That’s why we asked Willem-Jan Hanegraaf of Hanegraaf Interimmanagement & Advies to support us,” says Berends.
Fit-out: Arsis Medical
Modular wall system allows flexible operating theatres
Arsis Medical is responsible for fitting out part of the three operating theatres at MoreCare Clinics. This includes supplying and installing advanced Ondal pendant systems, Medifa LED operating lights and the modular ADAM wall system, finished in glass.
With these high-quality, flexible solutions, Arsis Medical is helping to create an efficient, safe and future-proof operating theatre environment tailored to users’ needs. The unique Adam wall system in particular enables a flexible environment. Unlike traditional, non-modular walls, it allows for quick changes when functions change or technical upgrades are made, such as moving medical gas, electrical or data connections. This results in lower maintenance costs, less downtime and a future-proof healthcare environment.
Eric Knuiman, owner of Arsis Medical: “We’re proud that MoreCare Clinics chose our no-nonsense approach. This project gives us the opportunity to demonstrate our expertise and efficient way of working. Together with all the parties involved, we’re aiming to deliver a successful project that will serve as an example for future collaborations.”

The biggest gains
The building being converted formerly housed the Chamber of Commerce and DA’s head office. The 2,700-square-metre building is being transformed into a state-of-the-art clinic, with the same atmosphere and appearance as the Ruimtevaart location. Demolition took place in September and construction began on 1 October. In line with the schedule, the new clinic is due for completion in February 2026 and will open immediately afterwards.
According to Berends, the rapid construction is down to all the partners working in a structured way. “A similar project in mainstream healthcare would easily take twice as long and cost much more.” Hanegraaf agrees: “The difference with a large hospital is that coordination and decision-making there have to pass through many more layers. If we want to arrange something here, it takes three or four people. That makes us incredibly agile, particularly during design and preparation. We can also achieve high quality and functionality because fewer compromises have to be made to reach a choice and a decision. That’s where the biggest gains can be made.”
Construction: LiemersBouw BV
Completely stripped out and redesigned
The former Chamber of Commerce building in Amersfoort is being transformed into a modern clinic for MoreCare Clinics in record time. LiemersBouw is stripping the building back completely, after which the interior will be redesigned. Only the exterior will remain almost unchanged.
“The construction period runs from 1 September to 1 March. That’s ambitious and requires tight planning. Fortunately, we have a great team that works together seamlessly, so it’s achievable,” says Bas Sanders, owner of LiemersBouw. MoreCare Clinics’ decision to appoint this contractor was no coincidence. LiemersBouw has worked on healthcare projects in the region before and knows where the challenges lie. Sanders: “We first got into healthcare through Rijnstate hospital, and now it’s almost all we do. It suits us perfectly, which means we can respond quickly to the client.”

A mini-hospital
The three-storey building will look the same from the outside. Inside, it will have all the facilities you would expect in a clinic. There will be a spacious entrance on the ground floor, surrounded by outpatient clinics with treatment rooms. The first floor will house the inpatient ward, with fifteen beds, and the second floor will have a fully equipped operating theatre suite with three operating theatres. A radiology room is also being built in the basement. In effect, it will be a compact hospital facility with X-ray equipment, treatment rooms and facilities services.
The building is spacious, so there is room for further expansion in the future, Berends explains. “There are plans to create an MRI room in the basement, mainly for the orthopaedic surgeons. There are MRI scanners in the area, but that would mean buying in healthcare services externally. That doesn’t support MoreCare Clinics’ vision of putting the patient first and organising care around them as efficiently as possible. That’s why we have these plans. They are covered by our licence, which allows us to provide all hospital services because we meet the relevant requirements.”
Electrical and mechanical services: Megens
A completely new installation for MoreCare Clinics
The electrical and mechanical services at MoreCare Clinics are being delivered by Megens’ Apeldoorn branch. This branch specialises in adapting existing buildings for use as clinics.
Megens Installaties Apeldoorn’s close-knit, dynamic team has a major advantage on this project. Its staff are extremely flexible and communication lines are short. Frank Molenaar, operations manager: “We worked up the design in the middle of the holiday period. All the services are being renewed, from the main distribution board to the cables, pipes and air handling. Everything must comply with the applicable standards and regulations for clinics.”
After the demolition, the team assessed which elements could be reused. The amount turned out to be greater than expected. “We’re trying to adapt the design intelligently to the existing situation,” says Molenaar. “That saves money, but also time.”

Short construction period
Choosing an existing building has its advantages. Construction can proceed quickly, and facilities can be reused and expanded. Hanegraaf joined the project in April, and the construction consortium had been contracted by the start of the summer. Once the entire building has been stripped out, the interior will be rebuilt. Hanegraaf: “The walls and floors are all coming out. The building services and IT infrastructure are also being replaced. The companies that submitted prices thought about how to make the work as efficient as possible, in keeping with MoreCare Clinics’ ambitions and the image it wants to project.”
Low ceilings
An existing building also has its drawbacks, of course, particularly when converting an office building for an organisation like this. Office spaces are not immediately suitable for medical use, and the lifts cannot accommodate beds. All of this is therefore being adapted. Berends: “In the operating theatres, we have to work within certain structural constraints, while also taking account of workspaces, fire compartments and ceiling heights. Office buildings usually have suspended ceilings. These reduce the available height and don’t look good. In some rooms, for example, we’re opting for spray-applied ceilings. This gives us more height and a completely different look, without compromising functionality or patient safety. You don’t see this often in hospitals because they tend to take a more traditional approach, but it’s certainly possible.” Hanegraaf adds: “We have a team of experienced consultants and project managers who focus on what is possible rather than putting up barriers. That’s how we create a healing environment and a safe workplace where patients, visitors and staff feel comfortable and at ease.”
The operating theatres required careful consideration of various factors, including airlocks, storage, and the movement of sterile and contaminated items. The air handling system in particular must meet stringent requirements. However, a large air handling system cannot simply be installed in the building. “The systems consist of large pumps and filters that will be placed on the roof. Because the building is tall, they won’t be visible. Here too, we’re using unconventional solutions that contribute to a state-of-the-art operating theatre environment with a distinctive look,” says Hanegraaf.

A hotel-chic setting
The new layout was designed by ZEEP architects and urban designers. The client is handling the interior design in-house, using natural materials and colours, transparent spaces and plenty of light. The aim is to create a luxurious, hotel-chic setting. “Patients come here for treatment. A calm, comfortable environment contributes to their wellbeing, making the experience different and better than in a clinical setting. That doesn’t mean, for example, that we’ll be using deep-pile carpet. Everything will meet the strict requirements of healthcare while still feeling well-appointed and warm. It’s an environment where people feel warmly welcomed,” says Berends. This also means comfort, such as single rooms, smaller teams and, as a result, short communication lines and a good atmosphere.
Adequate power supply
Like so many companies looking to build or renovate, MoreCare Clinics is also facing the problem of grid congestion. At peak times during the day, demand for electricity exceeds the capacity of the grid operator’s network. The solution is to install solar panels on the roof and batteries outside in the car park. Hanegraaf: “The batteries charge throughout the day, and at night too. We can draw on this energy when demand is high. Intelligent software manages this. We are building the system on a modular basis. We can expand capacity in the future as demand requires. We are currently calculating the required capacity. MRI scans create repeated peaks in power demand. There is also a baseline level of electricity demand. We are calculating both now to determine the battery capacity.”
Operating theatre construction: CleanSpace Cleanrooms
A leading player in the Dutch cleanroom market
CleanSpace Cleanrooms designs and builds the entire operating theatre complex, including the building services. As the project is being built inside an existing building, ceiling heights have to be taken into account. These are often restricted in office buildings, whereas operating theatres need plenty of space.
“The building’s walls need to be sufficiently airtight for the operating theatres to function properly. That is why we are building a box-in-box operating theatre complex. The limited available height makes it difficult to fit everything in, particularly the clean air systems and ductwork. The existing building services for the offices will remain unchanged. So we have to fit our systems between the ceilings and on the roof,” explains managing partner Alex Jansen.
The project comprises three class 1+ operating theatres, two preparation rooms and a sterile storage room. CleanSpace Cleanrooms’ experienced staff specialise in this type of work. They build operating theatres, GMP laboratories and ultra-clean production facilities for the semiconductor and high-tech industries, both in the Netherlands and abroad.


A clinic for everyone
Once the clinic is fully operational, an average of around ten to fifteen patients will be treated in the operating theatres each day. The outpatient clinics will offer many more treatments. Around forty staff will be on site during the day. This will not be a long-stay clinic, but a facility for short procedures, after which patients can go home. The luxury may seem to be reserved for a limited group, but nothing could be further from the truth, says Berends. “Everyone can come to us. Much of what we do is covered by health insurance. Hospitals are expensive and often bureaucratic. Independent treatment clinics like ours have shorter waiting lists and take a more personal approach. That is why we are seeing more and more clinics opening, for example in ophthalmology and orthopaedics. We focus on value-based healthcare: lower costs and greater patient satisfaction. People are not just a number here, and neither is our staff.”
This is an important reason why healthcare professionals enjoy working at MoreCare Clinics. “People know each other well, and pay is in line with the market. We have little difficulty recruiting staff. The new site is similar to the old one, with the same concept. We use the same manufacturers, drawing on the experience we have gained in the past. That means we know it will be a pleasant environment for both patients and the healthcare staff who work there,” says Berends.
Facts & figures
- Client: MoreCare Clinics
- Consultant: Hanegraaf Interimmanagement & Advies
- Architect: ZEEP architects and urban designers
- Main contractor: LiemersBouw
- Electrical and mechanical services: Megens Installaties
- Operating theatre complex: CleanSpace Cleanrooms
- Operating theatre fit-out: Arsis Medical
Question about this story? Ask your question
Who worked on it
Kliniek MoreCare Clinics Amersfoort in Amersfoort, transformatie
- clientMoreCare Clinics
- architectZEEP architects and urban designers
- ConstructionLiemersBouw BV
- OK-bouwCleanSpace Cleanrooms
- Electrical and mechanical installationsMegens
- Interior designArsis Medical
Keep following this
Get an email when a new story is published. No account needed.
- ProjectKliniek MoreCare Clinics Amersfoort
- SubjectGeneral
- CompanyMoreCare Clinics
- CompanyZEEP architects and urban designers
- CompanyLiemersBouw BV
- CompanyCleanSpace Cleanrooms
- CompanyMegens