Good preparation is half the battle
Text Gerrit TenkinkImage Ter Steege Bouw Vastgoed

In February 2023, care organisation Zozijn opened a new, sustainable residential and day activity centre for 36 of its clients on the former Auping site on Laan van Borgele in Deventer. Ter Steege Bouw Vastgoed acted as main contractor. The client and contractor had not worked together before, but got to know each other well as the project progressed. “If everyone is pulling in the same direction and you show understanding for one another, things always work out.”

Dirk Venema is Director of Property and Business Services at the Zozijn foundation. The foundation supports adults and children with learning disabilities and acquired brain injury. It operates from several sites in Gelderland and Overijssel. Its property portfolio includes both residential facilities and day activity centres. In Deventer, Zozijn was looking for a residential and day activity centre for 36 clients. “We came across Ter Steege Bouw Vastgoed more or less by chance,” says Venema. “Ter Steege is developing the entire former Auping site and building a complete neighbourhood with 120 homes, with a village hall and several shops nearby. We were looking for a site in the neighbourhood, close to the shops. We wanted a sustainable, energy-efficient building, preferably a new-build. After a number of discussions with Ter Steege and the architect, it became clear that all of this was possible at this location. Initially, the municipality wanted part of the building to be restored, but the architect was able to show that it was structurally impossible to renovate. That brought our preference for a new-build within reach.” Andries Tolman, Commercial Director of Ter Steege Bouw Vastgoed’s Apeldoorn branch, notes that the spirit of Johannes Auping is reflected in the building. “For example, the new building’s exterior is an almost exact replica of the old one. We have added an image of the renowned bed specialist and Auping founder to the top of the façade. The building also has an extra floor. All the parties involved felt that the building’s appearance was important, because it was a distinctive building and a familiar landmark for many people in Deventer. You want to preserve that wherever possible.”

Net Zero
The 36 residential units are spread over three floors. Each resident has their own bedroom-living room with a bathroom, and each floor has a communal living room with a kitchen. The day activity space is on the ground floor. Tolman: “Ter Steege has experience building for the care sector. We know that the pre-construction phase often takes a little longer than on other projects, because many stakeholders from the care organisation have a say in the development. You also have to comply with all kinds of care-specific regulations under the Building Decree, of course, but we were familiar with those.” Venema agrees. “We involved our residents and their families, as well as our staff, closely in the building plans. Their wishes were accommodated as far as possible.”
Turnkey
“We didn’t know each other,” says Tolman, “so at first we were feeling each other out. What did the client want, and how would we approach the construction process? In the end, we worked on a turnkey basis. Everything was clearly defined and assessed in advance, so we had to make very few adjustments during construction. Naturally, we held regular coordination meetings and made a few changes here and there, but they caused hardly any problems. The gas-free, highly sustainable building, with a roof full of solar panels, achieves ‘Net Zero’. The biggest challenges for us were in the building services. There is a lot happening in care, particularly in the field of domotics. We also had to deal with peak demand in the building, for example when residents were showering. How do you deal with that? It took some working out, but we got there. Aalbers Installatietechniek from Oene provided the expertise we needed.” Tolman adds that Ter Steege Bouw is also making progress in building services. “We are currently experimenting with storing energy in batteries, but it was a little too soon for that on this project.”

Lead times
The first discussions took place in 2017. Construction began in early 2021 and the work was completed in November 2022. A successful construction process does not mean everything went smoothly. “During the Covid pandemic, material lead times were often uncertain. We were able to honour the agreed price with the client, but we did have a few tough conversations with suppliers. Fortunately, we managed to resolve those together too. You want to honour your commitments to the client,” says Tolman.
Hybrid model
Looking back, Venema and Tolman are pleased with how the project went, and especially proud that everything was delivered on schedule. Venema: “Working with a company you don’t know is quite daunting. We are used to working from detailed specifications. Ter Steege prefers a turnkey approach. Both parties had to find their feet in the run-up to the project, because both approaches have their advantages. For a future project, a hybrid model might be an option. We invested a relatively large amount of time in the preparation to get on the same page, and in retrospect that was the right choice.”
Question about this story? Ask your question
Wie aan Woon- en dagbestedingslocatie Zozijn Deventer werkte
- clientStichting Zozijn ZorgMentioned in Active cooling, heating and ventilation at sustainable Stichting Zozijn Zorg site
Keep following this
Get an email when a new story is published. No account needed.
- ProjectWoon- en dagbestedingslocatie Zozijn Deventer
- ThemeSustainable healthcare buildings
- SubjectGeneral