Imposing tower gives hospital campus a new face

With its ‘Project U’ masterplan, UZ Gent is forging ahead with plans for the hospital of the future. The first embodiment of this vision will be the multifunctional Nobel I building, which from summer 2024 will become a dynamic hub for innovation, research and development. The 62-metre-high tower will have twelve floors and, with its sustainable, high-tech appearance, will mark the entrance to the site. Two energy-generating façades will produce green electricity, while the impressive roof garden will literally and figuratively crown the project.

‘Project U’ encompasses all of UZ Gent’s plans for the future, aimed at creating a hospital campus that is pleasant and efficient for patients, staff and local residents. Alongside the construction of a new central hospital, numerous other construction and renovation projects are planned. Together, they are intended to form a true ‘living lab’ where UZ Gent, UGent and various spin-offs and research organisations can join forces. “The construction of Nobel I officially marks the start of the redevelopment of our site,” says Geert De Waele, Head of Facility Management at UZ Gent. “The complex will be built between three existing buildings bordering the main entrance, including the UZ Gent catering building, which will connect to the podium of Nobel I. The tower will become a new landmark on the Ghent skyline and, with its striking presence, will serve as a kind of gateway to our
campus.”
Design & Build
As UZ Gent wanted to put the Nobel I building into use as quickly as possible, it opted for the Design & Build model. “This allowed us to run several processes in parallel and achieve results in a very short time. In just two and a half years, we will go from a blank sheet to completion. We could never have managed that through a conventional tender,” explains De Waele. “This is a project that places a strong emphasis on sustainability and innovation, complementing the neighbouring UGent buildings. We also applied several other important award criteria, including design quality, considered use of materials, integration of greenery, speed of construction and planning, … Ultimately, the consortium of MBG, Wiegerinck and LOW Architecten emerged as the winner.”
Future-proof, flexible and robust
The construction of Nobel I, of course, serves a greater purpose. The imposing complex not only symbolises UZ Gent’s lofty ambitions for the future, but will also enable certain functions on the healthcare and science campus to relocate temporarily. This will free up space through the demolition of outdated buildings, making way for a green science park with a state-of-the-art hospital. However, this meant that the specific use of Nobel I was not yet known when the design process began. “First and foremost, it therefore had to be a future-proof, flexible and robust building that could readily adapt to the changing needs of the hospital, the university or external research companies and organisations,” says Tim Loeters, architect and partner at Wiegerinck. “That is why we opted for a central functional core surrounded by column-free floors with generous floor-to-ceiling heights. This makes the building suitable for a wide variety of functions and layouts, without compromising on spatial or building-services quality. Nobel I can accommodate both low- and high-complexity departments. This is already reflected in the first functions to be housed there: on the one hand, a training centre, outpatient clinics and ICT offices; on the other, research facilities for the D.R.U.G., including several laboratories. In the long term, the complex will provide space for healthcare-related R&D companies.”
A challenging balancing act
The architects faced a challenging balancing act in terms of design: Nobel I had to become an iconic landmark with a strong visual presence, while also complementing the surrounding research buildings and blending seamlessly into the green setting at the front of the campus. “We achieved this by, as it were, tucking the volume beneath the park and reserving the roof for a garden room with tall trees and plants. In this way, we are giving back to the site the patch of nature that stood where the building now is,” explains Loeters. “There is also a strong connection with the surroundings at ground level. Welcoming colonnades with playful angled lines and an attractive patio blur the boundary between inside and outside.
The tower’s body has a formal, ‘technological’ appearance, thanks to the blue-grey colour of its façades, which are designed as a fine-mesh open grid. This gives the tower a certain lightness compared with the solid volumes on the campus.”
The Nobel I building is being constructed with a concrete frame, with main contractor MBG making maximum use of prefabricated elements (wide slab floors, prefabricated beams, prefabricated columns, …) to keep the construction period as short as possible. Project manager Hannah Van de Velde: “The ground floor and first floor, which are partly double-height, are flanked by trapezoidal façade columns. These will be cast in situ and finished with an architectural precast concrete shell, which, as mentioned earlier, will be grey-blue. From level +2 upwards, the load-bearing façade will be clad in folded aluminium cassettes in the same shade, interspersed with full-height window sections that ensure abundant natural light and panoramic views of the surroundings. The roof garden will be surrounded by a slender steel structure that will literally and figuratively crown the project.”
As sustainability and energy efficiency were key priorities and the tower’s roof area is limited, the consortium came up with an inventive solution to generate green electricity. “Thanks to the cantilevered curtain wall system, which projects 50 cm beyond the glass, we can integrate solar panels into two of the four façades while also providing sufficient solar shading. In addition, the PV elements further emphasise the forward-looking nature of the Nobel I building. That’s three birds with one stone,” Loeters stresses.
Tight lean planning
Speed was also a crucial requirement for this project. The complete design, including the technical design and cost estimate, had to be ready in just four weeks. The building permit for Nobel I came into effect on 27 March. As the first departments were expected to move in as early as summer 2024, MBG has just one year and five months to deliver the imposing building from start to finish. “The biggest challenge for us is the tight lean planning,” stresses Van de Velde. “Building the tower so quickly, combined with a basement that requires secant pile shoring and the atypical façade columns on the bottom two floors, is no easy task. What’s more, the green roof can certainly be described as ‘very intensive’. It is also a retention roof, so combining planting with water storage at that height is no child’s play, not least because of the considerable wind loads.”
“The façade concept also requires a great deal of preparation. We have made some adjustments so that we can build in horizontal layers and save time. It includes some unusual detailing on the inside: opening sashes with an acoustic partition that are invisible from the outside, but allow users to increase ventilation without creating additional noise nuisance. In short, there is no shortage of challenges, but we are confident that we will bring this prestigious project to a successful conclusion. Our project team is up and running, and twice a week we meet with all the parties involved to dot the i’s and cross the t’s. Now that the preparatory work is well and truly behind us, we are all looking forward to the actual construction!”
Question about this story? Ask your question
Wie aan Nobel I werkte
- architectWiegerinckIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectNobel I
- ThemeHospital construction and refurbishment
- SubjectGeneral
- CompanyWiegerinck