New GP out-of-hours centre built in record time

It has been a challenging year for the healthcare sector, but that did not stop Noorderhart vzw from building a new GP out-of-hours centre on the site of Mariaziekenhuis in Pelt.
A race against the clock in the midst of the coronavirus crisis, which went remarkably smoothly despite the exceptionally tight schedule and logistical challenges. The fact that GPs in North Limburg were able to start using the new building as planned on 15 January, after a construction process lasting just four and a half months, is a remarkable achievement.

Since the beginning of this year, residents of Pelt and the surrounding area who need to see a GP at weekends or on public holidays have been able to visit Noorderhart Mariaziekenhuis, where a brand-new GP out-of-hours centre has been built next to the emergency department. The previous centre, on Stationsstraat in Neerpelt, had to be demolished to make way for the expansion of the local school, so the GPs began looking for another location. They found one a few kilometres away, on the hospital site. “The new GP out-of-hours centre is in a prominent and easily accessible location, which is a great advantage for patients. If they have serious symptoms, they can be referred straight to the adjacent emergency department. This has further strengthened the links between primary and secondary care. The GPs are also pleased, as we have done our utmost to create a comfortable and high-performing working environment,” says Dirk Van Gorp, Director of Facilities Services at Noorderhart.

Thinking ahead, not thinking after the fact
The new GP out-of-hours centre occupies the ground floor of a new two-storey building. It comprises four consulting rooms, a waiting room and a reception desk, and is staffed by 152 GPs on the out-of-hours rota and around twenty GP trainees. In addition, ten rooms have been provided for doctors staying overnight, while the first floor houses several hospital departments, including IT, Human Resources and the clinical workstation. “The schedule was very demanding,” says Van Gorp. “The project was awarded at the end of June 2020. Work began in mid-August and the new GP out-of-hours centre was already in use by 15 January this year. That really is a remarkable achievement. The motto at site meetings was: ‘You have to think ahead, because if you stop to think, it’s too late’. The site also bordered the hospital’s loading and unloading area, so the logistics were no easy matter either.”

“It was certainly not an easy site to set up a construction project on,” agrees Jochen Willen, COO at Houben, which was responsible not only for the construction work but also for overall coordination as part of the Design & Build team. “We had to be proactive rather than reactive, and that happens to be one of our specialities. I am also convinced that the short construction period had a positive effect. We could only complete this complex project if everyone remained focused and on the ball at all times. All the subcontractors also had to be on site continuously, because there simply was no time or space for so-called ‘dead time’. Moving forward was the only option, and that worked in our favour. The tight schedule was a major driver.”

The interplay between steel and CLT
Main contractor Houben did everything possible to deliver the new GP out-of-hours centre in record time. It opted for a steel structure, with walls and floors made from cross-laminated timber (CLT) supported by a combination of timber and steel beams. “Thanks to our meticulous planning, we were able to prepare many prefabricated elements in advance, so all we had to do on site was assemble them. We also did not have to allow for drying times. The low weight of the timber-frame structure also saved us considerable time and money, with lower material, transport and installation costs. This kept activity around the site, disruption to the hospital and CO2 emissions to an absolute minimum. Choosing a CLT structure also reflects our ambitions in ecological and circular construction. Every material in the building structure can be fully reused,” Willen emphasises.
As the building had been modelled in BIM in advance, based on a 3D scan of the surroundings, the construction process ran smoothly and the contractors encountered no unpleasant surprises. “The shell was completed in just two months, thanks to the excellent collaboration between our planners, site staff, BIM engineers and others. Noorderhart also helped improve the efficiency of the construction process by defining all the required functions and technical and energy-performance requirements very clearly and in detail in advance. This meant there was no need for last-minute changes and the Design & Build formula could deliver its full benefits.”

No additional problems caused by coronavirus
As if the tight schedule and short construction period were not challenging enough, work on the GP out-of-hours centre also coincided with the coronavirus crisis. “In spring 2020, we were working flat out to make Mariaziekenhuis safe from coronavirus, while at the same time looking at how we could build a new GP out-of-hours centre as quickly as possible,” says Van Gorp. “Those were very intense months, and the prospect of disruption due to coronavirus was always there: would the site have to shut down at some point? Would the contractor have enough materials to build at all? Would the many suppliers run into problems?” Nevertheless, construction of the new centre went surprisingly smoothly, with no major delays, says Willen. “Apart from a few minor snags, we did not face insurmountable supply problems or local outbreaks. The work by the foreign subcontractors was also completed before the Christmas break, so there were no delays due to possible quarantine periods either. In other words, we were lucky, but open communication and constructive collaboration with Noorderhart, M4 architecten en ingenieurs, Studieburo De Klerck and all the subcontractors were also crucial. Everyone was pulling in the same direction from the outset. We can be very proud of the result!”
Facts and figures
Client
Noorderhart vzw
Architect
M4 architecten en ingenieurs
Contractor
Houben
Building services consultant
Studieburo De Klerck
Electrical installation
EL systems
Climate control
Deltha
Construction period
August 2020, January 2021
Total floor area
1,200 m²
Question about this story? Ask your question
Who worked on it
Noorderhart Pelt out-of-hours GP service in Pelt
- ClientNoorderhart vzw
- ArchitectM4 architecten en ingenieurs
- Building services consultantStudieburo De Klerck
- ContractorHouben
- electrical installationEL systems
- Climate controlDeltha
Keep following this
Get an email when a new story is published. No account needed.
- ProjectNoorderhart Pelt out-of-hours GP service
- SubjectGeneral
- CompanyNoorderhart vzw
- CompanyM4 architecten en ingenieurs
- CompanyStudieburo De Klerck
- CompanyHouben
- CompanyEL systems