‘Renovation of Diakonessenhuis operating theatre complex completed in six months’

Technological developments in healthcare are moving fast, too fast to spend years on planning and delivery. MAS architectuur has extensive experience in dramatically shortening the lead times for design and construction preparation, without compromising the functionality and quality of the facilities. This approach, called Gezondheidzorgexpress, has also proved successful in the renovation of the operating theatre complex at Diakonessenhuis in Zeist.
The renovation involved a complete reconfiguration of the operating theatre complex and an expansion from three to five operating theatres, with the addition of a day surgery centre. Alongside the standard recovery and holding areas, a lounge was created where patients can rest after a short procedure before going home. The recovery and holding areas have been located and designed to provide a high degree of flexibility. Architect Dianta Wilmsen: “The look & feel of the entire complex is designed to create a professional and welcoming environment. The site is in woodland, and we have even provided views of it from the operating theatres. The materials used have a natural appearance, while of course meeting hygiene requirements. All the detailing is flush, with seamless finishes.” Future innovations will be possible because the design already takes account of the easy replacement and accessibility of the systems used.

Process, functionality and design
Construction preparation for this project was improved and accelerated through concurrent engineering, with the design developed as an integrated effort, working directly with the client, users and consultants, through to the permit applications and a construction-ready design. MAS also took feasibility into account. The coordination and phasing of construction work in relation to the (technical) context and possible temporary facilities were factored into the design process at an early stage, helping to prevent risks and surprises during construction. Architect Joost Berger: “Renovating an operating theatre complex is a challenge that brings together process, functionality and design. We excel at this type of complex project. By drawing on our approach, knowledge and experience, we can provide good advice and drive innovation. Our collaboration with the client, building services consultant and medical equipment suppliers was intensive throughout the design process. We then worked with a construction team in a lean process, enabling us to complete the renovation at Diakonessenhuis within six months.” Thanks to this efficient process and approach, all parties worked closely together to develop and plan the entire scheme in great detail, ensuring that every element was meticulously coordinated. The result is a fault-free, very short construction period and a neatly finished, high-quality operating theatre complex.

Focus
Gezondheidzorgexpress focuses on facilitating processes, from logistics and hospitality to technology and feasibility. The technologies to be used and their feasibility are assessed, then incorporated naturally into integrated solutions. This is important both in complex healthcare environments such as hot floors and in general and semi-public areas in hospitals. Integrated BIM techniques, 3D visualisations and one-to-one mock-ups provide clarity on the functionality of the chosen solutions.
The same construction team, MAS architectuur, Sweegers en de Bruijn, Winters Bouw & Ontwikkeling and Unica, also delivered a highly efficient process for the hybrid operating theatre at Diakonessenhuis in Utrecht. Architect Dianta Wilmsen: “A hybrid operating theatre was built in the department, which is in use 24/7, without causing disruption. Builders and surgeons worked literally side by side, greater involvement is impossible.”
Healthcare organisations have a large number of stakeholders, whose interests sometimes conflict, making them highly complex. As a full-service architectural practice with an extensive healthcare portfolio, MAS architectuur has the specialist knowledge and experience to engage with all stakeholders within healthcare organisations on how processes work and how to shape facilities that meet their needs. All relevant aspects are taken into account and managed. The pressure-cooker method, in which all stakeholders work intensively together over a very short period to develop a design with broad support, has proved successful.
Words | John Nieuwenhuize Images | René de Wit and MAS architectuur
Question about this story? Ask your question
Who worked on it
OKC Diakonessenhuis in Zeist, renovatie
- architectMAS architectuur
- construction teamSweegers en de Bruijn
- construction teamWinters Bouw & Ontwikkeling
Keep following this
Get an email when a new story is published. No account needed.
- ProjectOKC Diakonessenhuis
- ThemeHospital construction and refurbishment
- SubjectGeneral
- CompanyMAS architectuur
- CompanySweegers en de Bruijn
- CompanyWinters Bouw & Ontwikkeling
- CompanyUnica