The flexible layer at LUMC

Hospitals planning renovations and facing a temporary or longer-term shortage of space are increasingly turning to temporary or semi-permanent accommodation. This allows healthcare providers not only to create much-needed floor space quickly, but also to benefit from facilities that are now of a very high standard.
Modular construction for temporary emergency department and outpatient clinic expansion
Directbouw, part of Dutch Cabin Group, recently built temporary accommodation in Hilversum for Tergooi’s dialysis centre, provided The Hague-based HMC with a Mother and Child Centre, and installed ambulance stations across the country. In Leiden, the modular construction specialist delivered temporary accommodation this year for the Emergency Department and an extension to the outpatient building for Surgery, Orthopaedics and Plaster Rooms, both for LUMC.

On site
For Gert Plas, Director of Directbouw, modular construction for healthcare providers is a specialist field. “For most other sectors, such as education and offices, the modules we use are up to 90 per cent complete before they are transported to site. At LUMC’s outpatient clinic and Emergency Department, we had to leave all the walls open on one side so that everyone who needed to install something in them, and there could be many different contractors, could inspect the inside and sign it off once approved. Only then could we close up the wall. On projects like these, we still have a relatively large amount of work to do on site. That mainly means plenty of consultation and collaboration with installer Unica, as they had to incorporate the building services and medical facilities into our modules. Thanks to good preparation, everything went smoothly.”
Emergency Department and outpatient clinic
Directbouw erected two buildings on the site. One is an Emergency Department on the station side, with two storeys, which is expected to remain in use for two and a half years, until the renovation is complete. This temporary Emergency Department is connected to the hospital by a direct, level corridor. The compact 21 by 21 metre building houses a CVA room (for stroke and cerebral haemorrhage), a radiology section with X-ray and CT scanning, an ultrasound room and two family rooms on the ground floor. The upper floor contains offices, a coffee room and a meeting room. A covered ambulance bay has been added to the Emergency Department. A little further away, the single-storey outpatient clinic has been built for Surgery, Orthopaedics and Plaster Rooms, and is expected to remain in use for longer. It has 25 consultation rooms, four plaster rooms, several larger treatment rooms, a radiology section and staff facilities (offices, canteen, changing room, etc.). Most of the building services are housed in a separate extension.

Construction
Because of the adjacent railway line and the large number of cables and pipes underground, neither building has piled foundations. The outpatient clinic rests on large foundation slabs, while a 25-centimetre-thick concrete slab was poured for the Emergency Department. Directbouw then placed the modules on top, most measuring 3 x 6 metres at ground level, with a limited number measuring 3 x 9 metres. “We use high-quality systems that fully meet all the client’s requirements,” Plas continues. “The well-insulated modules are built from steel frames and concrete floors, with SAB sandwich panels on the façades and 15-centimetre-thick sandwich panels for the roofs. The interiors are finished with suspended ceilings and ready-to-install Agnes wall panels with water-resistant, wipe-clean decorative foil.”
Fire safety and radiation shielding
“As well as incorporating numerous technical services in the walls and ceilings, we also had to deal with three fire compartments in the outpatient clinic, radiation-producing equipment in both radiology sections and heavy installations,” says Plas. “The required fire compartmentation was 30 minutes, but we extended this to 60 minutes using 12.5 mm plasterboard on both sides, which also provides significant sound insulation. To shield against radiation, the rooms concerned were fitted with plasterboard walls containing 2 to 2.5 mm of lead, in accordance with all the strict regulations. All these rooms were, of course, tested for radiation leakage. Where necessary, heavy medical equipment was suspended from the structural roof using threaded rods. The heat recovery ventilation units were mounted on steel frames supported by columns. The units were also finished to the client’s interior specifications and colour schemes.”
“All in all, it’s a great project that gives LUMC some breathing space,” Plas concludes. “One thing you notice with projects like these is how important it is to work with companies that specialise in hospitals. That’s how you achieve the best result for the end user.”
A business enquiry for Unica? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeHospital construction and refurbishment
- SubjectGeneral
- CompanyUnica