Westfriesgasthuis now fully ‘state of the art’

Westfriesgasthuis now fully ‘state of the art’

According to Nils van Mourik, facilities and property manager at Westfriesgasthuis in Hoorn, 16 February was a proud moment. That was the day the second phase of the hospital’s new-build project, covering 21,000 m2, was officially handed over. The various outpatient clinics and inpatient wards are now moving into the new building; the first patients will be treated there halfway through this year.

Years of planning went into this phase of the new-build project. Westfriesgasthuis was formed through the merger of Sint Jans Ziekenhuis and Streekziekenhuis West-Friesland in Hoorn. The 1995 masterplan envisaged a new building next to Sint Jans Ziekenhuis, right beside the NS railway station. “We decided at the time not to build everything at once, but to spread the project over several phases,” says Van Mourik. “That was because of the uncertainties and changes in the healthcare sector. Phasing the project allows you to adapt the plans as circumstances change.”

Learning from experience
The first phase of the new building, connected to the old Streekziekenhuis, was handed over as early as 2003. Preparations for the second phase began five years later. Van Mourik says: “We were able to draw on our experience from the first phase, make changes to aspects that had not quite worked as intended and incorporate changes to the building regulations. For example, the new building has wider corridors and more spacious patient rooms. We now have almost exclusively single rooms, giving our patients much more privacy. The mother and child centre, for instance, has maternity suites and incubator suites. Each baby has its own room, with private bathroom facilities for parents staying in the suite.” The new building also includes various outpatient clinics, including paediatrics, geriatrics, dermatology, rheumatology, internal medicine and neurology. There will also be inpatient units for paediatrics, oncology, neurology and geriatrics. Work on a new laboratory on the third floor will take place during the summer. The Clinical Chemistry Laboratory, the Medical Microbiology and Infection Prevention department (Comicro) and the Pathology department (Symbiant) will all be located there. All kidney care services will be brought together on the seventh floor, where patients can get answers to all their questions in one place. This new facility also has a new name: the Kidney Centre. “And with a new endoscopy centre for examinations of the stomach and bowel, Westfriesgasthuis is now fully ‘state of the art’.”

A consistent look and feel
This year, parts of the building from the first phase are also being refurbished. The surgical day unit and oncology day unit, for example, are being renovated. Van Mourik says: “We want the whole hospital to have the same look and feel, for instance by carrying the waiting-room design from phase two through to the waiting rooms in the first phase.” Westfriesgasthuis now has 327 beds, significantly fewer than envisaged in 1995. “There won’t be any more,” Van Mourik expects. “The anticipated growth proved unnecessary because of changes in healthcare. Westfriesland is still a growing region: more children are being born, while the population is also ageing. But healthcare has continued to improve in recent years, greatly reducing lengths of stay and our need for beds. In 1995, the average length of stay was still fourteen days, whereas in future we will be moving mainly towards day treatment. The first phase also included more patient rooms than we currently need. We will convert them into flexible workspaces for our care staff. The board of directors will also be based there, bringing it closer to the heart of care.” The final phase is due to start in about five years. First, the old Streekziekenhuis building will be demolished. It still houses, among other things, staff departments and support services.

Text: Henk Geist
Photography: Westfriesgasthuis

FACTS AND FIGURES
PROJECT Westfriesgasthuis new-build, phase 2
Client Westfriesgasthuis, Hoorn
Architect De Jong Gortemaker Algra, Rotterdam
Construction management Pieterse terwel grevink, Amersfoort
New-build start January 2013
Handover February 2015
Total building area 22,544 m²
Total construction costs 40 million euros including VAT

Een zakelijke vraag aan Gortemaker Algra Feenstra architects? Get in touch

Who worked on it

Westfriesgasthuis Hoorn in Hoorn, nieuwbouw

  1. architectGortemaker
  2. clientWestfriesgasthuis
  3. construction managementPieterse terwel grevink

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectWestfriesgasthuis Hoorn
  • ThemeHospital construction and refurbishment
  • SubjectGeneral
  • CompanyGortemaker Algra Feenstra architects
  • CompanyWestfriesgasthuis
  • CompanyPieterse terwel grevink
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.