Since 2010, HagaZiekenhuis in The Hague has been undertaking a major renovation of its high-rise building on Leyweg.
Construction of a new building right next door began last year. This will house, among other facilities, the operating theatre complex and Juliana Kinderziekenhuis. Renovating a hospital that remains in operation is a complex undertaking.

“Of the 75,000 m² due to be renovated, work has now been completed on around 55,000 m²,” says Martijn Oude Luttikhuis, construction director at project office HagaVernieuwt, which oversees all construction and renovation activities. “A renovation on this scale in a hospital that remains in operation is exceptionally complex and unique in the Netherlands.” As patient care must continue as usual and the hospital wants to make as little use as possible of temporary accommodation, the renovation is being carried out in phases. Phasing, construction, engineering, ICT and logistics are all interlinked. Detailed move and work plans have been developed for the phasing. This means, among other things, that work can start as soon as a department becomes vacant. As several departments are moving into the new building, it plays a crucial role in the renovation. Oude Luttikhuis says: “We are now completing the renovation of the fourth and fifth floors of our high-rise building, and will continue with the Intensive Care Unit next spring. As it is being built where the current operating theatres are, work cannot start until the operating theatres move to the new building in early 2015. The entire renovation will be complete by the end of 2016.”
Changes to the building services also affect the phasing. Existing central technical systems have to be disconnected and replaced with new ones. Sometimes, old and new systems have to operate together temporarily. For example, new infrastructure has been installed for energy generation using the WKO system. The heating system must be connected to it. Careful consideration is therefore needed as to when and how the contractor disconnects, reconnects or temporarily runs the systems together.
Renewed Working

The renovation was necessary not only because the building and its technical systems needed updating. The way people worked also had to change. To this end, HagaZiekenhuis introduced the Vernieuwd Werken concept. Among other things, this means that staff no longer have a permanent workstation and can log in anywhere. Many processes around the patient have also been automated, including the electronic patient record and terminals at the bedsides. The phasing of the renovation and the ICT systems therefore also have to be coordinated. Work began with the Facilities Department, an office-based department that needed only a basic ICT infrastructure. Departments with more complex systems, such as the Heart Centre and Radiology, followed later.

Safety
The phasing also takes account of the safety of hospital users, which, according to Oude Luttikhuis, always comes first. “We started by renovating areas that had the least impact on other departments. We also make sure that staff, patients and visitors are affected as little as possible by dust, vibration and noise.” This began with the tender for the contractor. The hospital had drawn up a set of house rules setting out how the contractor should work and manage safety and disruption. Bidders were asked to submit an approach plan, a kind of quality assessment. Alongside cost, the contractor’s approach to safety carried significant weight in the final selection.

Logistics
It goes without saying that logistics is also a key consideration in a large demolition and renovation project of this kind. As internal logistics processes continue as usual, the contractor and the hospital’s Logistics Department need to coordinate constantly. To minimise disruption to day-to-day operations, and because space is limited, the just-in-time method is used throughout.

Satisfied
Oude Luttikhuis is pleased and proud of how well staff and patients have coped with the renovation so far. “This is only possible when everyone shares the same ambition and determination to make the project a success!”

Question about this story? Ask your question

Wie aan HagaVernieuwt werkte

  1. clientHagaZiekenhuisMentioned in New HagaZiekenhuis in The Hague completed
  2. contractorVolkerWesselsMentioned in New HagaZiekenhuis in The Hague completed
  3. contractorBoele van EesterenMentioned in New HagaZiekenhuis in The Hague completed
  4. architectMVSAMentioned in New HagaZiekenhuis in The Hague completed
  5. loose furnishingsGispenMentioned in New HagaZiekenhuis in The Hague completed

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectHagaVernieuwt
  • ThemeHospital construction and refurbishment
  • SubjectInteriors
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.