New AZ Maria Middelares hospital offers a hotel-like experience

AZ Maria Middelares in Ghent has opened a brand-new hospital. The distinctive, compact building beside the Ringvaart, designed by EGM architecten and LLOX architecten, puts patients at the heart of its design while also ensuring efficient services and improving the hospital’s profitability.
“Patients in our new hospital do not have to stare at a table with a bunch of grapes on it. I am very happy about that,” says Professor Pascal Verdonck, managing director of AZ Maria Middelares. Every room in the new building has natural daylight. Thanks to the large windows, patients can look out over the surrounding greenery and green roofs, even from their beds. The brick façades create a homely atmosphere. The layout of the hospital building also ensures that patients have sufficient privacy.
Experience and results
The patient experience was top of AZ Maria Middelares’ list of priorities. “In 2001, when we drew up plans to bring the Ghent and Gentbrugge campuses together in a new hospital, we had already identified ‘putting patients first’ as one of the project’s four pillars. That was very forward-thinking in Belgium at the time,” Verdonck explains.
The hospital is pleased to see that patients have responded positively. “They tell me that it feels more like going to a hotel than to a hospital,” says Verdonck. The director considers this important, because the patient experience contributes to the quality of a hospital. “Quality is the product of experience and results,” the professor explains. “Both matter. If a patient receives good care but does not find their stay in hospital pleasant, then something is wrong. The reverse is also true.”
‘Three bars’
The new AZ Maria Middelares hospital opened in April 2015. The brand-new complex, with 631 beds, replaces the buildings on the nearby campus and the campus in Gentbrugge. Construction of the hospital took four years. EGM and LLOX jointly developed the masterplan for the project. They won the competition launched by the general hospital in 2002.
“I still vividly remember their proposal,” says Professor Verdonck. “They came with a model made of bars and explained that a U-shape would ensure daylight everywhere. The structure was also ideal for accommodating the difference in elevation of around 4 metres across the site. It was brilliant. What is more, they were already thinking in terms of our needs, which was refreshing.”
A logical layout
“The central atrium, with the entrance, forms the heart of the building,” explains Marijke Veryser, an architect at EGM architecten. “The three building volumes, which together form a U-shape, each house one of the hospital’s three functions. The west wing contains the medical and technical areas, such as the emergency department and operating theatres. The outpatient clinic is located in the other arm of the U. The volume containing the nursing wards runs across the two wings.”
“The layout of each floor also follows its own logic,” Veryser continues. “The day hospital and services for outpatients are on the ground floor. The treatment area, including the operating theatres and intensive care, is on the first floor. The patient rooms are on the upper floors.”
“Everything related to logistics and building services has been placed on the logistics level or in dead spaces,” she adds. Verdonck picks up the thread: “When patients look outside, they do not see building services installations. We are not a factory. The roof has a wave-like form. This creates spaces beneath the roof structure that cannot be used for patient care or other functions, the so-called ‘dead spaces’. We have put the building services equipment there, out of patients’ sight.”
New-build
“Many hospitals try to introduce this layout in their buildings, but often cannot because they are building on existing structures,” says Laurent Van Damme of LLOX architecten. “It was possible in this new-build project. The hospital management also consistently upheld the agreed philosophy. AZ Maria Middelares worked on the project for almost fifteen years.”
“The layout of the complex also keeps walking distances short,” Van Damme continues. “That was another important consideration, as was privacy. Unlike patients in the Netherlands, Belgian patients attach great importance to discretion. This is sometimes reflected in small details. For example, beds cannot be seen from the corridor, whereas this is often the case in Dutch hospitals.” But it goes further than that. “The movement of hospital beds is kept as separate as possible from other patient flows,” says Veryser. “The entrance and restaurant are the areas where privacy matters least, so they are easy to access. Waiting rooms, doctors’ rooms and operating theatres, however, are not so accessible. If you do not need to be there, you will not end up there, even if you are looking for the right department,” explains the EGM architect.
Sustainable and profitable
As well as putting patients at the heart of the design, the hospital had to be sustainable, ready for responsible growth and financially sound. “EGM and LLOX incorporated all these aspects into their design,” says a satisfied director. The hospital’s frame structure makes it easy to relocate departments. The arms of the U-shape can also be extended. “Sustainability is not limited to building services,” explains Elie Vanderbauwede, technical director. “In addition to a borehole thermal energy storage system (BEO) with 140 boreholes, each 150 metres deep, a combined heat and power plant, green roofs, solar shading, a rainwater recovery system and a high level of insulation (K-22), the hospital can also boast a floor area of just 100 m² per bed.”
“And that does not come at the expense of patients,” Professor Verdonck emphasises. “The hospital now has fewer meeting rooms and storage areas. We have also not invested in functions that are not useful in a hospital building, such as an auditorium. It is true that this compactness requires a change in staff attitudes, but it also reflects developments in the hospital sector, such as the use of multidisciplinary spaces and collaboration across departmental boundaries. This in turn leads to lower operating costs and greater returns from the hospital building, bringing us to the ‘financially sound’ aspect. You cannot continue to deliver quality if you are not operating profitably,” Verdonck concludes.
Text: Bram Souffreau Photography: EGM/foto-atelier De Rammelaere
FACTS AND FIGURES
Healthcare provider AZ Maria Middelares, Ghent
Architect EGM Architecten, Dordrecht
LLOX Architecten, Wilrijk
Building services consultant Studieburo De Klerck Engineering, Brugge
Air handling Beltherm, Zedelgem
Consultancy Bopro
Nurse call systems Televic, Izegem
Loose furniture Gispen, Ghent and Art-Nivo, Ghent
Privacy screens Silentia-Elandir-Care, Zwevezele
Air Creative
Flooring Tarkett Belux, RotselaarConstruction period January 2011, January 2015
Architect selection 2003 (2003-2012: design period)
Start of construction January 2011
Completion January 2015
Total building area 64,800 m² (floor area)
Total capacity 631 places: 99 day hospital places, 532 beds, 22 intensive care places and 17 operating theatres
Total construction costs 136 million euros (excluding VAT)
Number of beds 631
A wonderfully fresh fragrance for the new AZ Maria Middelares
AZ Maria Middelares left nothing to chance when building its new hospital. A total of 22 air purification units from Swiss company Air Creative create a harmonious, fresh and pleasant environment. In most healthcare facilities, including hospitals and residential care centres, residents, patients and visitors encounter various forms of unpleasant odour, including those associated with incontinence, stoma care, toileting, wound care and mortuaries. There are therefore many odour-control systems designed for the healthcare sector.
The results are usually disappointing, because entire departments often end up smelling of ‘toilets’, with the air saturated with chemical lemon compounds that make breathing difficult and quickly cause discomfort and physical complaints. When ‘clouds of chemical fragrance’ repeatedly try to mask unpleasant odours rather than eliminate them, people cannot feel a sense of wellbeing.
The Swiss Air Creative process, by contrast, filters the air and then neutralises odours by eliminating all intrusive ambient smells. It also provides a subtle fragrance at the level of unconscious perception, using natural, discreet antiseptic essential oil blends that are unobtrusive and do not cause discomfort.
Flexible InterAxio care platform ready for the future
Televic Healthcare has almost seventy years’ experience in call systems and care communications in hospitals and residential care centres. The Televic interAxio care platform focuses on patient comfort and safety. The new IP patient handset integrates all the features needed to make a hospital stay more pleasant: TV controls, radio and music selection, telephone functions, lighting controls and more.
The large, easy-to-read touchscreen can be adapted to the patient’s needs and provides feedback on the functions being activated. For added peace of mind, the call button also provides direct feedback on the display. In addition, two-way voice communication through the handset reassures patients directly, with a response from the nursing staff. The handset’s new patented magnetic connection provides a reliable and durable link. In short, interAxio is a flexible platform, ready for the future.
AZ Maria Middelares opts for innovative Eleganza 2 hospital bed
AZ Maria Middelares in Ghent is the first reference site for wissner-bosserhoff’s brand-new, innovative Eleganza 2 hospital bed. The Eleganza 2 sets new standards in side-rail systems, build quality and modern design. The hospital bed features numerous innovative functions to support both nurses and patients in day-to-day care. Mobi-lift® is an innovative system that helps patients get out of bed, maximising their mobility and freedom of movement.
Added safety
Although a bed should be a safe place for patients, falls are a major problem for hospitals. The Eleganza 2 therefore offers added safety. Its side rails provide a high level of protection against falls from bed. As a further visible indicator, the green light integrated into the side rails signals that the bed is in a safe sleeping position. The integrated intelligent lying surface in the Eleganza 2 can also measure patients’ vital signs wirelessly.
Intelligent bed sensors
As well as vital signs, the condition of the bed and its safety features can be monitored online using intelligent bed sensors, with alarms sent via the nurse call system. Safety, ergonomics and ease of use were therefore our key strengths, meeting the future needs of AZ Maria Middelares, says sales director Ward Uytterhoeven. Wissner-bosserhoff would like to thank the management and all staff for their trust and excellent cooperation.
Bopro optimises the development and construction process
Bopro, active in the property and construction sectors, has grown over the past thirty years into a reputable, well-established company specialising in advice, management and consultancy. Bopro works for end users, public authorities, healthcare institutions, investors, promoters and developers.
Bopro’s ultimate aim is to create added value in the broadest possible sense. It seeks to achieve the best possible economic, social and environmental balance. By optimally managing construction and property processes, it facilitates responsible and sustainable project development.
AZ Maria Middelares engaged Bopro for project management, cost management and health and safety coordination.
Beltherm supplies air handling systems for the new Maria Middelares hospital
Beltherm NV carried out the air-side work for the HVAC package for the new Maria Middelares hospital in Ghent as part of the temporary joint venture Declercq, Beltherm. Beltherm specialises in air handling systems and currently has three branches: Zedelgem, Nazareth and Eksel. Beltherm provides a complete service, from design, production and installation to commissioning and aftercare.
At its Zedelgem branch, Beltherm has its own production department, where air ducts are made to measure. In-house production gives our installation teams flexibility and ensures the quality of the ducts. All ducts meet air leakage class C requirements.
Beltherm has around forty well-equipped, experienced installation teams. Thanks to its high production and installation capacity and constant monitoring of the quality of the work delivered, Beltherm can also handle larger projects, such as the new Maria Middelares hospital. In addition to this hospital, Beltherm has references in other hospitals, nursing and care homes, public buildings, offices
and industrial applications.
Een zakelijke vraag aan wissner-bosserhoff? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectInteriors
- Companywissner-bosserhoff