Operating theatres, intensive care and cleanrooms
Twelve new operating theatres for AZ Monica
Text and images Koen Mortelmans

AZ Monica has thoroughly upgraded and expanded both its campuses. Work is still under way in Deurne, but in early 2024 the Antwerp hospital officially opened the additional space at its Harmonie campus in the city centre.
The TM comprising Antwerpse Bouwwerken-Eiffage and Cordeel was responsible for the works at the Harmonie campus in central Antwerp, to a design by ABV+ Architecten. AZ Monica plans to focus more on low-risk procedures in orthopaedics, oral and maxillofacial surgery, and pain management. The hospital aims to be among the best in Europe in these fields. “We believe that focused clinics will improve the experience for staff and patients, increase efficiency and raise the quality of care,” says managing director Geert Smits. Harmonie, formerly the Eeuwfeestkliniek, will also continue to serve as an outpatient hospital, where patients are welcome for consultations and follow-up appointments across a range of medical specialities. There will also continue to be space for both inpatient and outpatient rehabilitation. The Deurne campus, by contrast, is being strategically redeveloped as a general referral hospital for eastern Antwerp and several eastern suburbs.





No centenary for the Eeuwfeest buildings
Space is limited in the largely residential neighbourhood near Harmoniepark. To build a new wing, an existing monastery building and chapel in the centre of the site had to be demolished. The former nuclear medicine department was also removed. The old buildings date back to 1930, when the Augustinian Sisters founded what was then the Eeuwfeestkliniek. The name refers to the centenary of the Belgian state. The two remaining elderly nuns were willing to move to make way for the hospital expansion. In their place, the contractor consortium built a new volume containing the reception area, an operating suite with twelve operating theatres, an auditorium and various doctors’ consulting rooms. The reception area also includes a spacious cafeteria with eighty seats, as well as a separate glass pavilion for people who really cannot give up smoking. The old buildings were also demolished at the fire brigade’s request, to ensure that emergency services can access the entire site.

Focused clinic
“By focused clinic, we mean organising specific care pathways in separate units, either inside or outside the hospital. To work efficiently, these pathways need to be concentrated in high volumes. They have low variability, allowing processes to be made efficient and predictable. For a condition to be considered low-risk, the risk of complications must be limited,” explains Geert Smits. “Focused clinics have already been introduced successfully in neighbouring countries. In most cases, this has led to lower costs and improved quality of care. The concept is still new in Belgium.”
Glass and timber
ABV+ designed the new building with a double-height transparent glass plinth and two cantilevered upper floors, clad externally in timber slats. “The choice of timber softens the scale of the volume and connects it to the greenery in the centre of the site,” explains project leader Luc Jacobs of ABV+ Architecten. There was only limited space available for a green roof, which is mandatory in Antwerp. Most of the roof was needed for 200 solar panels, with a combined peak output of 80 kW. The aim of making the centre of the site as green as possible could not be fully realised either. The cafeteria’s outdoor terrace, which has sixty seats and is sheltered by the overhang, is too shaded and too heavily trafficked for real grass to grow, so artificial turf was installed instead.

There is a connection to the existing hospital on both levels. This is important for the smooth transfer of patients to and from the operating theatres, without having to use the lifts extensively. The new building has a total above-ground floor area of 5,746 m². It also has an underground car park of 1,247 m². This is no unnecessary luxury, as parking is in very short supply in this part of Antwerp. “Unfortunately, we could not build a second underground parking level, as we would have had to excavate far too close to existing buildings,” says technical and facilities director Wout Struyfs. “We added an extra access ramp to improve safety and traffic flow.”
At the top
The new operating suite, with twelve operating theatres, is on the third above-ground level, between two semicircular corridors: a ‘clean’ corridor on the inside and a ‘dirty’ corridor on the outside for removing medical waste. This level also contains support rooms, including preparation rooms and a recovery room. A fibre-optic network supports imaging. Medical staff and patients can watch procedures in detail and live on large screens. The new facilities are intended to ensure that AZ Monica retains its leading position. “AZ Monica is responsible for about 1% of all hospital procedures in Belgium,” says head of orthopaedics Dr Olivier Verborgt. “But in orthopaedics, that share is 33%, and in knee surgery it is more than 6%.
The fourth floor is entirely dedicated to technical services. This is where the air-handling units are located. “They deliver a flow rate of 10,000 m³ per hour,” says Struyfs. “Three chilled-water units provide cooling. The existing boilers are sufficient for heating, although we have added heat exchangers.”
Versatile engineering consultancy
Engineering consultancy Botec (Wommelgem) was responsible for the design, studies and supervision of the climate control systems, electrical services, medical gases, pendants, smoke and heat extraction in the underground car park, and the sprinkler system in the operating theatres. Botec has also previously worked at the ‘Eeuwfeestkliniek’ on projects including the conversion of the pharmacy into an intensive care and recovery area, the refurbishment of the central sterilisation department, the pain clinic and the construction of earlier operating theatres.
For the current expansion of OLV-Middelares, AZ Monica’s other hospital in the Deurne district, Botec is responsible for the design, study and supervision of the sanitary services and fire-fighting equipment, climate control, electrical services, including lightning protection and the emergency generator, medical gases, the pneumatic tube system, smoke and heat extraction, and the sprinkler system in the underground car park. Botec has also previously worked on numerous renovations, expansions and technical innovations at this site.
Question about this story? Ask your question
Wie aan Ziekenhuisvleugel campus Antwerpen AZ Monica werkte
- ClientAZ Monica, AntwerpenIn this story
- DesignABV+ Architecten, AntwerpenIn this story
- main contractorTM Antwerpse Bouwwerken-Eiffage, Antwerpen: Cordeel, TemseIn this story
- Technical studies and follow-upBotec, WommelgemIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectZiekenhuisvleugel campus Antwerpen AZ Monica
- SubjectOperating theatres, intensive care and cleanrooms
- CompanyAZ Monica, Antwerpen
- CompanyABV+ Architecten, Antwerpen
- CompanyTM Antwerpse Bouwwerken-Eiffage, Antwerpen – Cordeel, Temse
- CompanyBotec, Wommelgem