New construction in an existing hospital environment requires all parties involved to be flexible.

Everyone involved had to go the extra mile during the construction of ‘the new Radiology department’ at Ziekenhuis St Jansdal in Harderwijk. Looking back, they are satisfied with the result. So much so that a letter of intent has already been signed with contractor Goossen te Pas Bouw for further renovations.

The new-build and renovation project links two existing wings of the hospital. The Radiology department is on the ground floor and includes two MRI scanners, a CT scanner and a PET scanner. The Cardiology outpatient clinic has been built on the first floor. On one side, construction is taking place next to the operational ENT department. The operating theatre complex is on the other side. The site cabins were installed in January 2020, and the new-build section is due for completion in December.

The reception desk in the Cardiology department on the first floor.

A good fit

Niels Slotman, project manager at Goossen Te Pas Bouw, and Anita van der Haar, manager of Construction & Property at St Jansdal, both look back on an intensive period. “Initially, the plan was to build a single-storey Radiology building, but during the tender process we concluded that we wanted to add a first floor. When the plans for the floor above Radiology took shape in September 2019, it was clear this could not be postponed. The project had to cover the whole scheme, which meant revising the plans within four months. Splitting a construction process like this into two projects would be more expensive, but perhaps worse still, it would cause a great deal of additional disruption.”

Construction team

Following the contractor selection, Goossen Te Pas Bouw was brought on board as construction partner. “They actively helped us work through the changes to the plans,” explains Van der Haar. “When selecting the right contractor, we looked not only at price, but also at experience and flexibility. Goossen Te Pas Bouw has extensive experience of working in a hospital environment. As part of VolkerWessels, it has plenty of expertise at its disposal. But a good rapport is important too: how does a builder handle unexpected situations? And are they willing to contribute ideas throughout the construction process? We hit it off from the day of the selection.” The construction team was formed in mid-2019, with Halmos installatieadviseurs, Wiegerinck architecten, ABT constructeurs and Unica Building Projects joining Goossen Te Pas Bouw.   

Niels Slotman, project manager at Goossen Te Pas Bouw, and Anita van der Haar, manager of Construction & Property at Ziekenhuis St Jansdal, both look back on an intensive period. (NB: This photo was taken before the COVID-19 pandemic, when the 1.5-metre rule was not yet in force. Photo: Elles Boot)

Disruption

Flexibility and minimising disruption are essential in a hospital environment. Most of the disruption occurred at the interfaces where connections had to be made to existing departments. Slotman: “We are used to working in a hospital environment, but it must never become something we take for granted. It is clear that patient care comes first. That is why certain tasks are carried out early in the morning, at weekends or in the evening. Fortunately, the hospital also understood that construction work had to take place. We hold weekly meetings with the hospital’s construction team. The flat organisational structures and short lines of communication help us work efficiently and quickly.”

Construction team

Transparency is one of the strengths of a construction team, and the hospital also worked hard to ensure transparency. Van der Haar: “We issued a weekly construction bulletin for staff and our neighbours to keep everyone informed. We also allowed for minor changes during construction, but tried to keep these to a minimum. We took plenty of time at the outset to review the whole process carefully, in order to limit the number of changes along the way.” Slotman: “On projects of this scale, we work with a decision schedule, dividing the process into phases. There is an opportunity to make changes at the start of each phase.”

The handover is not set for a specific date, but is taking place in phases. This means the hospital is already installing equipment (as of November 2020, ed.), while the construction teams are still at work. “We are doing this to save time. Working at the same time on a construction site requires mutual trust, but it also reflects the trust and cooperation between us.”

The Radiology department is on the ground floor.

Next steps

Now that the new-build work is complete, Goossen Te Pas Bouw is preparing for the next job: the renovation, which will create space in the old
Radiology department for, among other things, the Angio room and 2 CT scanners. This section is scheduled for completion in May 2021. “We are satisfied, so much so that a letter of intent has now been signed for Goossen te Pas to also build the new ‘South’ hospital wing. We have got to know each other and know what to expect from one another,” says Van der Haar, who knows what she will do differently on future construction projects. “The construction teams bring a great deal of drive and ideas. We should have made better use of that earlier in the Radiology project. We will definitely do things differently next time.”    

Building services design and energy study

As part of the extension and renovation of the existing Radiology department at Ziekenhuis St Jansdal, Halmos Adviseurs is responsible for the building services design and preparation of the contract documents. The consultancy has also carried out an energy study to enable all the new-build and renovation plans to be delivered.

The study bridges the gap between current operations and maintenance and the available capacity of the central building services systems required for the new extensions. Halmos mapped all existing energy flows and capacities, then recommended the final solution based on the existing situation.

All the designs have been developed so that, in time, the entire hospital can operate without gas. The energy study led to an expansion of the energy sources for the thermal energy storage system, the integration of new heat pumps and a doubling of emergency power capacity. All proposals were assessed and put forward using the TCO methodology. The studies were ultimately incorporated into the tender documents, together with the associated drawings.

Following a tender process that came in on budget, the project is now in full swing. The expectation is that the project will be fully operational in March 2021.

A business enquiry for Unica? Get in touch

Wie aan Radiologie St Jansdal Harderwijk werkte

  1. construction teamUnicaIn this story
  2. contractorGoossen Te Pas BouwIn this story
  3. building services consultantsHalmos installatieadviseursIn this story
  4. architectsWiegerinck architectenIn this story
  5. structural engineersABT structural engineersIn this story
  6. building contractorGoossen te PasMentioned in Refurbished St Jansdal moves in the day after completion
  7. architectIAA ArchitectenMentioned in Refurbished St Jansdal moves in the day after completion

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectSt Jansdal Harderwijk radiology department
  • SubjectHospitals
  • CompanyUnica
  • CompanyGoossen Te Pas Bouw
  • CompanyHalmos installatieadviseurs
  • CompanyWiegerinck architecten
  • CompanyABT structural engineers
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.