Refurbished St Jansdal moves in the day after completion
Text Desiree Pennings Beeld St Jansdal

St Jansdal Hospital in Harderwijk is being modernised in phases. The first section of the clinical building was recently completed. Unusually, the wards were already in use by staff and patients the following day. Making this possible required close collaboration, trust and meticulous planning.
The ageing building dating from 1987 was due for renewal in response to new insights and changing healthcare needs. Between 2020 and 2026, a large part of the hospital in Harderwijk is being renovated and extended. This enables it to deliver future-proof care in a building that provides optimum support and facilities.
Following work on areas including the technical facilities, radiology, the laboratory and the South building section, it was the turn of the clinical building. It now houses the neurology and cardiology wards on the ground floor, gastroenterology, urology and gynaecology on the first floor, trauma and vascular surgery on the floor above, and respiratory and internal medicine on the third floor. The new-build layout clusters departments so that healthcare staff can provide better support for one another. Efficient logistical routes for care also contribute to this.

Having the courage
One significant change was the number of beds per room, reduced from four to one or two. This is not only more efficient, but also gives patients and their families greater privacy. To make the new layout possible, the entire building was stripped back to its existing concrete frame. This had to be done carefully, as a large proportion of the materials were reused. Niels Slotman, project manager at building contractor Goossen te Pas, says: “The demolition materials were recycled, as were the doors, counter components and furnishings. But the biggest contribution to reuse is the concrete frame. Nothing is more sustainable than that.”
Anita van der Haar-Ros, Manager of Construction & Accommodation at St Jansdal, adds: “Sustainability is very important to us. We would prefer to invest every penny in healthcare, but sustainability contributes to that too. As well as reusing materials, we carefully selected new ones. We developed a LEAN design and a CO2-reduction construction solution. This renovation contributes to making our hospitals more sustainable. The façade, window frames and HR+++ glazing will last for decades to come. The architect, builders and installer also advised us on this, of course. And sometimes it takes courage. The entire exterior façade was removed. That was quite a major intervention, but fortunately our Board of Directors agreed to it. The hospital wing now looks like a brand-new building.”

A pleasant place to stay
Sustainability is not just about the materials used, but also about creating a pleasant building to spend time in that can adapt to different uses, says Michelle Booltink, architect at IAA Architecten. She designed it to adapt to users’ needs. “If the hospital functions well, there should be no need to adapt it again later. Because all the departments are broadly identical and the accordion principle is used, the building is highly flexible. If the specialisms in a department change, the building does not have to change with them.”
Discussions were held with various user groups to develop the floor plans within the constraints of the existing frame. The entire exterior façade was renewed, with new insulation, new brickwork and new window frames. This creates a pleasing link with the recently completed new building section, which houses clinical departments. “It has become a light, fresh environment where every patient has a window overlooking the garden. Soft colours and wood feature in the finishes, while the corridors have prints of natural scenes designed especially for the hospital. Thanks to AFAS Foundation, these wall prints were made possible. At the end of each corridor there is a view outside and a seating area. This improves orientation and makes efficient use of the space,” says the architect.


Building services for healthcare
Total building services contractor Unica provided both the electrical and mechanical installations. This was a substantial job too, involving the replacement of the air handling unit, chilled and heated water distribution, and hot and cold water supplies. Adiabatic humidifiers were also installed. The electrical work included new distribution boards, the replacement of all lighting with LED, a complete replacement of the fire detection and alarm system, and a new patient call system. “We also replaced the entire data installation, so everyone has internet access and a tablet. Services for patient care, including power and medical gases, have been provided behind every bed and incorporated into a bedhead unit. As an installation company, we do a lot of work for hospitals. We have the right expertise in-house and, together with our construction partners and hospital staff, we put it to the best possible use,” says Astrid Scholtsbergh, project manager at Unica Building Projects.

Planned down to the minute
While the work was still in full swing, the building sections were already being furnished and healthcare staff were training in the wards. This required meticulous planning and rock-solid trust in one another, says Van der Haar-Ros. “Normally, there are months between completion and occupation. In our case, there was just one day. During the final construction phase, we had already started moving in, of course in close consultation with the construction partners. We took care of everything from IT to putting up the hand sanitiser dispensers. Scenario-based exercises and training on the building systems also took place. By the time construction was completed, everyone was ready to move. As well as saving time, we saved a lot of money. This tight schedule also prevented a great deal of disruption.”
Bart Valkema, Care Manager at St Jansdal, continues: “We had already gained a lot of experience when the South building section was brought into use. We set up a working group that specified exactly what needed to happen and when. Everything was coordinated down to the minute. Later, we reaped the benefits of that perfect preparation. We moved over the weekend and nothing came up that we had not anticipated.”


Understanding and trust
During the moving weekend, everyone knew exactly what needed to be done, and the relevant departments, with a total of 110 beds, were moved. No department had to close temporarily, so everything remained operational. Patient care could not be allowed to suffer, however. “I have been involved in hospital construction since 2011, but what we have done here is truly unique,” says Slotman. “Many contractors can lay bricks, but understanding and trusting one another is essential here. The construction site belonged not only to us, but also to the staff specially trained for the move. We had one shared goal: a safe move. Trust in one another was always the foundation.”

Major advances in technology
When the final wing of wards is renovated at the end of next year, 24,000 square metres will have been renovated and built, with more than €100 million invested in capital expenditure. All the parties are enthusiastic about the renovation completed so far, says Scholtsbergh. “There is a sense of calm in the hospital. We are now working on the second wing, and staff cannot wait to start using it.”
Moving from a dated four-bed room to an attractive double room with private sanitary facilities is a major improvement. Nurses are pleased that they can now provide care more efficiently. This would not have been such a great success without the smooth collaboration between St Jansdal, Unica and Goossen te Pas. “We have made major advances in technology. Healthcare staff now have smartphones with patient data, making it easier to record information.
They no longer have to walk back and forth to collect supplies or medication. We now have a central point for storage and stock management, which is monitored using innovative methods. The number of beds per department has been reduced, which requires capacity management, but we are now using that capacity far more effectively. All the construction partners involved can rightly be extremely proud of the result,” says Valkema.
Patient care is at the heart of the refurbished clinical building: calm, privacy and safety underpin every design decision. At the same time, consideration has been given to the people who make this care possible. Staff work in a modern, efficient environment that enhances their job satisfaction.

A business enquiry for Unica? Get in touch
Wie aan Radiologie St Jansdal Harderwijk werkte
- building contractorGoossen te PasIn this story
- architectIAA ArchitectenIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectSt Jansdal Harderwijk radiology department
- SubjectConstruction projects
- CompanyGoossen te Pas
- CompanyIAA Architecten
- CompanyUnica