Woodland setting creates a literal healing environment for new IrisZorg addiction clinic
Text Desiree Pennings Beeld Arcom BV en Dunavast

Dunavast is building a new clinic for IrisZorg in the woodland setting of Panovenlaan in Nijmegen. From May 2027, it will provide care for people with an addiction. There will be space for 52 clients. What makes the project special is the extensive use of biobased materials. This is not only better for the environment, but also actively supports the healing process. A literal healing environment.
IrisZorg currently has clinics at three locations: Tiel, Wolfheze and Zevenaar. The latter two are being brought together in the new building, as the existing sites are outdated. Construction began in January 2026 and is now well under way. When complete, the building will cover 2,936 m2 across two floors and include a range of facilities, such as 52 studios, communal spaces, low-stimulus rooms, a family room, a sports hall and a creative space. Rick van de Kerkhof, clinical psychologist and psychotherapist at IrisZorg, explains: “We offer a range of addiction treatments and also look at underlying causes that need to be addressed. Admissions range from compulsory to voluntary, and from short to long. There will therefore be one closed and four secure groups. Residents will cook and eat in the communal living rooms, and there will be space for both individual and group therapy.”

Low-stimulus environment
Arcom was commissioned to design the building, starting with research into how the clinic would be used. The firm held workshops to clarify the Schedule of Requirements and looked at other sites. Staff and clients were consulted so that their perspectives could inform the design. Arcom ultimately identified three central pillars of addiction care: community, individuality and daily routine. “These are exactly the things you also find in a monastery,” says architect Jan Thijs Groenendijk. “We have incorporated them throughout the design, with a cloister garden, the groups within the building and the circulation routes. These are all parallels with a monastery that we used to shape the building.”
The low-stimulus environment is ideal for peace and recovery. Since the surrounding area already offered a healing environment, this was carried through into the building. The extensive use of wood and calm colours are a perfect fit. Aart Jan Verdoold, CEO of developer and owner Dunavast, says: “Using timber-frame construction is unusual for this client group. We had set ourselves the ambition of building a healthcare facility in timber. It was an exciting adventure, because we were thinking in a completely new direction. The site was previously occupied by an old, outdated sauna complex. However, it was very suitable for this healthcare development. I hope the new building will support the recovery of its users, as they will be in a green setting, in a building made from natural materials.”

Greater design freedom
The exterior features a robust façade clad in mineral brick slips. They look like brickwork but have a lower carbon footprint. As they were bonded in place, they allowed greater design freedom, making it easy to create angled surfaces. Subtle variations indicate the different functions within the building.
The courtyard is enclosed by timber façades. The original plan was to create one large courtyard, but it was ultimately decided to split it in two. One section will be used by the closed group, giving clients a quiet outdoor space. Rooms requiring privacy face onto this garden, while those with a more open function are located on the outside of the building. This means the communal spaces are more connected to the outside world.

Nature-inclusive design
A landscape architect developed a nature-inclusive design, with space for wildlife and native plants. The gardens blend seamlessly with the green surroundings. Jubbe van den Wildenberg, manager of the Wolfheze clinic, says: “Each section of the courtyard will have its own tree. It will be a meeting place where clients can relax and talk with their care teams.” Inside, the natural design continues, with plenty of wood, calm colours and cloister-like corridors to guide people around. The furniture will echo the warm tones of the wood. It is not only attractive, but functional too. “We are asking staff for input on the wall colours, and we have given thought to creating a green entrance. When clients come in, they will immediately feel they have arrived somewhere peaceful,” says Van den Wildenberg.


Short construction period
Using timber and timber-frame construction calls for a different way of working. Preparation is particularly important, as most of the building is made in a factory. The positions of all pipes, sockets and systems must be agreed in advance. “You have to think earlier and faster about where everything will go. There is little you can change once work on site is under way,” says Dennis Mentink, project manager at Burgland Bouw. Technical director Hubert van Velden adds: “The construction period is shorter, but the pre-engineering for the entire structure takes more work. Key considerations include fire safety and acoustics. Timber has a different mass from concrete, so these issues need to be approached differently. The choice helps reduce the environmental impact, and using timber results in a lighter structure, right down to the foundations. It is an efficient construction method that delivers a great result.”
Building services in the walls are completely concealed. In the corridors, the services have deliberately been left exposed. The building is, of course, entirely gas-free, with 250 PV panels on the roof. Heat pumps provide heating and cooling, while ventilation systems recover heat. Each room has an 80-litre electric boiler that charges when it gets dark. Van Velden says: “Because Thermen Nijmegen used to be here, we were able to secure a relatively large electricity connection. Even so, it was a puzzle to position the intelligent systems so that they are fully tailored to the clients.”

Subsidy adviser
Subvention
A sustainable building, backed by the best subsidy advice
Dunavast wanted to make the building on Panovenlaan in Nijmegen as sustainable and circular as possible. Subvention was brought in to make the most of the available subsidies. The consultancy specialises in securing grants for making new and existing property more sustainable.
“We were involved from the design stage,” says subsidy adviser Thijs Vaneker. “We opted for a design eligible for subsidies under GPR. This is a digital tool for assessing the sustainability of a building. The tool proved a good fit with the construction team’s aims. In this way, we secured total tax relief of approximately € 142,500.”
Not all the construction partners had experience of sustainable building using the GPR methodology. Subvention and GPR expert Linneman helped them get to grips with it. The choice of environmentally friendly building materials with a low environmental impact, and the building services, were particularly important. “On our advice, the contractor obtained certification from Stichting Keurhout. This enabled us to secure the tax relief that allows them to supply and process both FSC- and PEFC-certified timber. GPR assesses a building’s sustainability in five areas: energy, environment, health, future value and usability. The project achieved a minimum eligible score of 8 in all these areas,” says Vaneker.
Relocation brings opportunities
Practical completion is scheduled for February 2027, after which IrisZorg can begin fitting out the clinic ahead of its opening in May. Van de Kerkhof says staff and clients will notice a significant difference. “Group interventions and hybrid treatment will become easier. We will be located close to Pro Persona, a major mental health organisation in the region. The university is also relatively nearby. The move gives us an opportunity to take a critical look at what we do and how we can do it better.”


Facts & figures
- Client: Dunavast
- Tenant: IrisZorg
- Architect: Arcom
- Main contractor: Burgland Bouw
Question about this story? Ask your question
Who worked on it
IrisZorg Nijmegen addiction clinic in Nijmegen
- ClientDunavast
- ArchitectArcom BV
- Main contractorBurgland Bouw
- subsidieadviseurSubvention
Keep following this
Get an email when a new story is published. No account needed.
- ProjectIrisZorg Nijmegen addiction clinic
- ThemeHealing environments
- SubjectConstruction projects
- CompanyDunavast
- CompanyArcom BV
- CompanyBurgland Bouw
- CompanySubvention