Designing together with users

Designing together with users

The first plans for the new operating theatre complex at Maastricht UMC+ were drawn up more than 10 years ago.

The new-build facility was already in use by 2016, and for the past few months the operating theatres in the renovated section have also been fully operational. Users have been closely involved in the design and construction process from the very beginning. What has this meant for the project and the end result? 

Identical operating theatres

“Originally, there were not going to be any operating theatres in the new-build facility,” says Jori Stevens, property manager at MUMC+. “We were only going to renovate the outdated operating theatre complex. However, a combination of a new-build facility on level 3, the same level as the existing building, and renovation of the existing complex proved to be the best solution. In the end, we developed the new-build facility and renovation together as a single Schedule of Requirements, along with the preliminary and detailed designs.” The new complex houses 20 operating theatres, 14 of which are identical, as well as the holding and recovery areas, the central sterile services department (CSSD) and the internal distribution centre (IDC). Hub Ackermans, head of operating theatres at MUMC+, is pleased with the decision to make the operating theatres identical. “We benefit from that every day. There’s no debate about who can use which theatre, and you can find your way around almost anywhere with your eyes closed.”

A pivotal role in the process is crucial

Ackermans has been involved in the project from the outset. But taking on a role in the project team is not something you can just do on top of your day job. “It takes commitment and time. You also have to stay on top of the process and be willing to ask difficult questions. So we freed up unit manager Agnes Derwa completely to represent us as users on the project team, in the role of staff adviser for operating theatre construction and renovation. And she did a perfect job!” Derwa was also the key link between the doctors and the architect, consultants and contractors. Ackermans says: “Because, whichever way you look at it, healthcare professionals and the construction industry speak different languages. Her role was invaluable and was one of the most important factors behind the success of this project.”

(Beeld: John Sondeyker)

Vision and collaboration

According to Ackermans, another important success factor is having a clear vision of what you want and why. “Agnes or I attended every design team meeting. As someone directly involved, I shared my vision of how the operating theatre should function, what it should look like and what was needed. I also stood by that vision, for example to prevent the theatre from becoming too narrow because of an oversized air duct. Bureau Vastgoed & Huisvesting worked with the architect and consultants to find other solutions, and there usually were alternatives. It was a genuinely multidisciplinary collaboration, with understanding of one another’s views and respect for one another’s interests.” Stevens adds: “Problems were seen as challenges, and ‘can’t be done’ was not an option. Expectations were managed well. If something really couldn’t be done, that was fine too. In the end, we always reached the best decision together. That was also down to focus: we all knew what we wanted to achieve, and users’ needs were central. The careful process involving users seemed to take a great deal of time, but it more than pays off in less follow-up work and more satisfied users!”

Mock-up invaluable

Ackermans’s vision did not come out of nowhere. Years of experience at other hospitals and several site visits provided inspiration. A model of the desired operating theatre was eventually built in the basement of MUMC+, using a mock-up. All the walls could be moved, as could the pendants. This made it possible to create the right layout for every procedure. Peter Meertens, who was responsible for the technical aspects and preparation of the medical equipment, accompanied users on their visits to the mock-up. “For quite some time, I helped all the clinical disciplines test and improve their ideal way of working in this operating theatre. We discussed all the procedures they normally follow and adjusted them where necessary. We soon discovered that the laminar flow canopy was too small. Before the detailed design was completed, it was enlarged from 3.25 metres to 3.5 metres. Making that change afterwards would have been much more expensive, or even impossible. Only once everything was right did we translate the mock-up into a detailed design for the operating theatre.” All the materials from the trial operating theatre were then reused to create a model of a recovery area. Pendants, bridges, beds, lighting: everything was simulated. “We even had a ceiling made with ambient lighting,” adds Joëlle Theunissen, head of the holding and recovery areas. “We tested it live in practice in the interim. So before the new holding and recovery areas were handed over, staff already knew what they would be getting.”

Everything in 3D

“Another way of giving people a clear picture of the end result in advance, and another success factor, was to produce fully developed 3D drawings,” says Stevens enthusiastically. “We now use BIM and virtual reality (VR) in all our projects, but the operating theatre complex was the pilot project. Everything was modelled, from walls, doors, windows and pipes to beds and cabinets, and VR enabled users to see things such as sightlines.” Project manager Alex Duijzings says: “As well as knowing what they will get, users can see whether everything fits. You can identify all clashes before construction starts. We call that virtual handover. This means there are no surprises during construction, helping the work to run more smoothly and reducing the cost of rework.” The approach has proved effective in practice. So far, no remedial work has been needed.

Listening to users

“Designing in 3D has also led to a completely new design process for us,” says architect Rafael Calis Sanchez of Architecten aan de Maas. “In the past, we would have a brief conversation with users, make a sketch and then go back to the drawing board. We took a different approach at MUMC+. We designed live in Revit with users present. That gave us very direct feedback and meant we could immediately show why something was not possible, for example because a main shaft ran through that area. This approach builds support among users and speeds up the design process, because there are fewer return visits to discuss changes. After a design session like that, the main outlines of the design were settled.” 

One of the requirements was to use a ‘flush’ design, creating smooth walls throughout. “Monitors, dispensers and even the door frames are integrated flush into the walls. It is a fine example of the craftsmanship of Cleanroom Combination Group, which was responsible for the detailing and finishing of the operating theatres.”

Space and calm

The layout of an operating theatre is not the only important consideration. Logistics are also a key factor in the smooth operation of the entire complex. As well as the mock-up and 3D models, logistics workshops were therefore held, which showed that providing space for staff and specialists was the number one priority. All the operating theatres are at least 52 m². There is nothing on the floor. Everything is suspended from pendants, apart from the operating table. Everything is also built flush into the walls, mainly for hygiene reasons and to maximise space. Equipment and supplies are stored in lean stores, where every item has a designated place marked with a photo. Even the beds. As a result, the corridors are clear and tidy. And that encourages everyone to keep them that way!

Information systems

A ‘state-of-the-art’ operating theatre complex calls for equally advanced information systems. Here too, the starting point was: ‘what does the user want?’. Dennis Haagmans, project manager at MIT at MUMC+, was involved at an early stage and helped explore the options. “The starting point was that the software had to support the process. We introduced a patient tracking system and integrated the systems extensively. It was helpful that users had thought so carefully about their information needs. That greatly helped with the tendering process and led to advanced software packages, enabling us to deliver something that genuinely benefits patients and staff.” Theunissen is pleased with the patient tracking system. “We can now look half an hour ahead, which helps us reduce peak workloads in the holding and recovery areas. That makes the department much calmer. We can also generate management data that allows us to make process improvements.”

Construction as a vehicle for change

Ultimately, the new-build facility and renovation of the operating theatre complex involved much more than replacing a number of outdated operating theatres. The entire process was reviewed. This meant that all operating theatre-related departments moved to level 3. Many procedures changed as a result, as did the way people worked. Efficiency improvements were introduced. In short, far more changed than just the physical environment. By involving users in these changes, they embraced the solution. There is support, pride and engagement. The prevailing feeling is: ‘we made it happen together’. Ackermans says: “We now have a future-proof operating theatre complex, a model for the academic sector, where it is also a very pleasant place to work. Students are keen to study here. I’m proud that our complex is now a source of inspiration for other hospitals, including internationally.”     

Have a business enquiry for CCG Holding? Get in touch

Who worked on it

MUMC+ Maastricht operating theatre complex in Maastricht

  1. architectArchitecten aan de Maas
  2. detaillering en afwerkingCleanroom Combination Group

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectMUMC+ Maastricht operating theatre complex
  • ThemeSafe and reliable healthcare buildings
  • SubjectHospitals
  • CompanyArchitecten aan de Maas
  • CompanyCleanroom Combination Group
  • CompanyCCG Holding
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.