Dijklander Ziekenhuis’s operating theatre complex is fit for the future once again

Since early September, Dijklander Ziekenhuis in Purmerend has had six fully renovated operating theatres, or, more accurately, a brand-new operating theatre complex. The project was completed at remarkable speed, partly due to the coronavirus pandemic, and the results speak for themselves.

The operating theatre complex in Purmerend was in need of a major upgrade, says Maarten Sijpestein, Dijklander Ziekenhuis’s manager of Property, Engineering and Procurement. “The floors had been worn through, the rooms no longer met all the hygiene requirements, and the power supply was outdated. Users sometimes genuinely felt as though they were walking around in the last century. In a sense, they were: the operating theatres were more than twenty years old and had reached the end of their service life. We had actually wanted to renovate them eight years ago, but at the time there was not enough funding. The plans were revived after the merger of the hospitals in Purmerend and Hoorn in 2017.”
Higher turnover
As part of the merger, the two sites were given different roles: complex and highly complex care is now concentrated in Hoorn, while routine care, such as routine surgery, is provided in Purmerend. The renovation of the operating theatre complex is part of hospital-wide construction and refurbishment plans, which also include the IVF centre, the day treatment centre, the psychiatric department and the outpatient clinics.
The operating theatres in Purmerend needed more than a routine update, says Sijpestein. “We wanted to redesign the department completely to increase turnover and operate on more patients each day. An important part of this was making the patient journey as efficient as possible. Previously, a patient occupied a bed in the holding area before surgery and a bed in the recovery area afterwards. As a result, we had empty beds in recovery in the morning and empty beds in the holding area in the afternoon.”

Combined holding and recovery area
The decision was ultimately made to combine the holding and recovery areas in a single room, explains Theo Spoelstra, who as project manager was responsible for translating user requirements and the initial design into a detailed construction design. “Under the new arrangement, patients arrive for treatment on foot wherever possible, then get ready for surgery in a patient preparation room. This is more comfortable for patients, who spend less time in bed before surgery. Combining the holding and recovery areas means fewer beds are needed and gives staff a clearer overview of the department.”
Separate instrument preparation rooms and differentiated performance levels
Another important element of the refurbishment was the creation of a separate instrument preparation room, Spoelstra continues. “Previously, the instruments for an operation were prepared in the operating theatre. Only afterwards could the patient enter the room and be prepared for surgery. By creating a separate preparation room for each theatre, these processes can now take place in parallel. The time saved allowed us to reduce the number of operating theatres in the design from seven to six. The space freed up was used to provide the storage needed for equipment.”
The decision was also made to differentiate the operating theatres by performance level. Spoelstra explains: “Two operating theatres are designed to level 1, for infection-sensitive operations, and four to level 2, for less high-risk procedures. This differentiation meant that most of the existing air-handling systems could be retained, avoiding unnecessary investment in the hospital’s air-handling plant.”

Working with Heddes
The refurbishment was carried out by West Frisian construction company Heddes Bouw & Ontwikkeling. “We had already been providing daily maintenance at the hospital in Hoorn for several years,” says Tijmen Schrauwers, Head of Project Development at Heddes. “So we knew each other fairly well. The entire refurbishment plan fitted neatly into the further development of our partnership, particularly because we could carry out the projects in phases.”
“It was also important to us to work with a company from the local area,” adds Sijpestein. “We also wanted to stop hiring a different contractor for every project. We opted for a small team, with Heddes handling the building work and BAM the building services.”
Schedule changed due to coronavirus
After nine months of preparation, the construction work was completed in thirteen weeks. The coronavirus pandemic disrupted the original schedule to some extent, says Schrauwers. “At first, there was talk of setting up a temporary operating theatre complex in the car park. However, as care was scaled back due to coronavirus, it was decided to close the operating theatres in Purmerend and move operations to Hoorn. This meant we could bring the refurbishment forward by a few weeks, so we would be finished in early September rather than October. For us, that meant bringing in extra capacity and working through the summer holidays. Fortunately, we are flexible and used to carrying out construction work outside the main season.”

A remarkable achievement
Despite having to step up the pace, the construction team managed to complete the operating theatre complex in early September. It was a remarkable achievement, says Spoelstra. “The entire complex went from concept to completion in just over a year. That is truly unique. In the final stages, finishing the construction work and moving into the operating theatres took place side by side. This required a great deal of flexibility from everyone involved. During those weeks, we held daily start-of-day meetings to coordinate everyone’s priorities as effectively as possible.” Schrauwers adds: “It was certainly not always a straightforward process. Working with a permanent team helped enormously. We could quickly get in touch with one another and respond immediately. Close communication is crucial, especially when time is short.”
Satisfied users
The first operations took place in Purmerend again on 4 September. Sijpestein has already heard plenty of positive feedback from users of the operating theatre complex. “It is wonderful for operating theatre staff to work in a modern environment. It looks beautifully clean and bright. The computers are now safely built into the wall behind glass, making everything even more hygienic. Because the turnaround was so quick, staff can see the results of their input into the design process straight away. That has generated a great deal of support and enthusiasm. All in all, we look back on an intensive process, a good working relationship and, above all, a fantastic end result.”
Question about this story? Ask your question
Who worked on it
Dijklander Ziekenhuis operating theatre complex in Purmerend, renovatie
- installatiedeelBAM
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDijklander Ziekenhuis operating theatre complex
- ThemeSafe and reliable healthcare buildings
- SubjectHospitals
- CompanyBAM