Highest point reached in new Franciscus Gasthuis building in Rotterdam
Text and images Sabine Bison

Hospital of the future
Since construction began in mid-2023, the replacement building for Franciscus Gasthuis in Rotterdam has been rising at a rapid pace. It has now reached its highest point, providing a reason to celebrate and an opportunity for an update.
While Franciscus Vlietland in Schiedam can expect a number of renovations and sustainability upgrades in the coming years, Franciscus Gasthuis in Rotterdam is undergoing a complete transformation. The current building, opened in 1975, no longer meets the requirements of modern healthcare. A completely new hospital is being built next to the existing one in two phases, after which the old building will be given a new purpose and the site transformed into a campus. “This will bring together all the facilities needed to provide patients with high-quality, safe and innovative care in the future. It will also be a pleasant workplace for future users,” explains Bert Jan Grevink, Director of Site Redevelopment.
From vision to design
The process of getting to this point has been challenging. Grevink explains: “Franciscus wanted to modernise on its current site, with a new Operating and Interventional Centre and a new Women & Children’s Centre. We looked into what was possible and permitted, and added a third wish: a new Emergency Department and GP out-of-hours service. It soon became clear that renovating the existing building was not feasible in terms of space, disruption, technology and cost. The decision was made to build a replacement and give the old building a new purpose. This ensures that care can continue until the new building opens.”
Hospital of the future
To create a hospital of the future, Grevink says, you need to think in terms of life cycles. “A hospital building lasts around 40 years. So you have to ask yourself: what will the world look like then? Working practices and medical technology change significantly over that period. For example, operating theatres from the past no longer meet today’s needs. We will have an Operating and Interventional Centre with 12 rooms, four of which will be high-tech operating theatres with image-guided technology that, unlike before, can be used by multiple disciplines.” Patient and staff experience, changes in the healthcare landscape and the potential of information technology also informed the decisions. “Patients will still come to the hospital for procedures, but more and more follow-up appointments can take place remotely,” says Grevink. Project leader Anna Hekman describes the careful process that preceded the new building: “Joint design sessions with the future users of the medical and support departments helped us map out and assess all their wishes and requirements. Designing a hospital is a people-centred process.”


The new Franciscus
The new building will house three essential hospital services: Spoedplein Rotterdam Noord, where Emergency Department and GP out-of-hours service professionals work efficiently together in one setting; the Operating and Interventional Centre, with the latest surgical and X-ray technology for complex treatments; and a Women & Children’s Centre with a Ronald McDonald Huiskamer, where midwives and maternity care organisations work together to provide family-centred care. Hekman says: “Light, views and nature were important starting points for the design of the new building. Plenty of natural light, natural colours and materials will help everyone feel at ease here.”
Building with ambition
The contract was awarded to a consortium comprising Berghege Heerkens bouwgroep, ULC Installatietechniek and Unica Building Projects. Peter Kamermans, Chairman of the Executive Board of Berghege Heerkens bouwgroep, says: “This new building is a perfect fit for our ambitions and expertise. When building a hospital, it’s not about concrete, but about creating spaces that, for example, need to accommodate a CT or MRI scanner. That requires careful thought.”

Complex construction
“The construction site is in a complex location,” says Grevink. “It is surrounded by every type of infrastructure imaginable, and it is a former landfill site.” Kamermans adds: “You’re also building 15 metres from a hospital that is fully operational, next to an Emergency Department and Intensive Care Unit. This requires thorough preparation and technical choices to manage noise, vibration and other disruption. For this project, for example, we chose to drill the 354 piles 35 metres deep without vibration. As we didn’t know exactly what was in the ground, we had to stop more than once and drill somewhere else.”
Sustainable and innovative
Grevink says: “The new building meets the standards for the latest technological innovations and surgical techniques, as well as the latest sustainability requirements (BENG).” Hekman adds: “Solar panels will be installed on the roof. The building is entirely gas-free, and we will use heat pumps, energy storage and recovery, and thermal energy storage.” Sustainable choices were also made during construction. Kamermans says: “We looked at reusing materials and applying circular principles. For example, we used the outdoor paving bricks to cover crawl spaces. By placing piles closer together, you can opt for a lighter type of concrete and use a lot of prefabricated components. We use electric equipment wherever possible and separate and reduce waste wherever we can. All of this helps to minimise the project’s CO2 footprint.”
Highest point
Reaching the highest point was recently celebrated in style. “Achievements you accomplish together deserve a celebration. It’s a long and challenging journey, so it’s important to pause and recognise the milestones along the way,” says Kamermans with a smile. “The new building will be ready in 2026, after which Franciscus will continue developing the site into a campus, with 2036 as the target date for completion. In the meantime, we’ll be looking ahead to the next life cycle. Every 10-20 years, we define new steps. That’s how Franciscus will remain the hospital of the future,” Grevink concludes.
Een zakelijke vraag aan Berghege Heerkens bouwgroep? Get in touch
Wie aan Ziekenhuisgebouw Franciscus Gasthuis & Vlietland werkte
- architecta/d Amstel architectenMentioned in Franciscus launches sustainable new-build project with European financing
Keep following this
Get an email when a new story is published. No account needed.
- ProjectFranciscus Gasthuis & Vlietland hospital building
- SubjectHospitals
- CompanyBerghege Heerkens bouwgroep
- CompanyULC Installatietechniek
- CompanyUnica