Hospitals

New state-of-the-art operating theatre complex for VieCuri created through intensive collaboration

Text José Mulder Beeld Pascale Clephas

In het nieuwe OK-complex kunnen meer patiënten per dag worden behandeld.
In het nieuwe OK-complex kunnen meer patiënten per dag worden behandeld.

Work has been under way since 2022 on a state-of-the-art operating theatre complex at VieCuri hospital in Venlo. The entire new-build and refurbishment project is due to be completed by the end of 2026. The hospital will then have ten high-quality operating theatres, including one hybrid theatre and one prepared for robotic surgery. A large and complex project like this requires not only technical and construction expertise, but also clear communication and close collaboration

The spaces are truly tailored to day-to-day work.

Construction work in a live healthcare environment

Eric Boots, Project Coordinator for Construction and Engineering, has been closely involved in the project from the outset. He explains the complexity: “We are building in a hospital that operates 24 hours a day. While an operation is taking place on one side of a dust partition, we are carrying out demolition work on the other. This calls for the utmost coordination and flexibility, with patient and staff safety the top priority. We regularly have to drill at six o’clock in the morning or work at weekends to minimise disruption to patients and staff.”

Marcel Willems, Building Services Supervisor, also confirms the complexity: “We are working on both existing and new-build sections. This means that sometimes you have to shut down parts of the building services, while other parts must continue running as normal. The hospital’s operational reliability must never be put at risk.”

Staff can see their input reflected in the end result.
Healthcare and technology come together seamlessly.

Close collaboration as a key to success

The project’s strength lies in its collaboration. Rather than a succession of separate contractors or temporary project managers, there is a permanent construction team in which everyone knows one another. Bernd Kooi, Building Supervisor at VieCuri, stresses the importance of involvement: “We know each other’s strengths and weaknesses. This openness fosters mutual trust and a strong sense of responsibility.” Healthcare professionals are also closely involved. From doctors to nurses and other care staff, everyone was able to contribute and was expected to do so. “That has ensured the spaces are truly tailored to day-to-day work,” says Boots. “For example, at their request, we paid a great deal of attention to natural light in the operating theatres and patient areas. It may seem like a minor detail, but it makes a world of difference to staff and patients alike.”

Reliable healthcare, ready for the future

Six of the ten operating theatres are now in use. Work is also well under way in the Medical Imaging department. The first reactions have been very positive. “The staff are enthusiastic. They feel listened to and can see their input reflected in the end result,” says Boots. “We have replaced all the building services, from medical gases to air handling, with an exceptionally high level of redundancy. That means maximum reliability, even in the event of a fault. To give an idea of the scale of the imaging facilities: for 4,500 m2 of Medical Imaging space and 4,400 m2 of operating theatre floor space, an impressive 2,000 m2 is devoted to building services.” The operating theatre complex is fully equipped for the future. Work processes have also been optimised. The new infrastructure enables more efficient working and allows more patients to be treated each day.

Completion of the entire project is scheduled for the third quarter of 2026. Around 70% of the overall complex has now been renovated. The result? A safe, modern and efficient working environment where healthcare and technology come together seamlessly. Willems concludes: “It’s a huge job, but when it works out, and it will, it’s incredibly rewarding. We really are doing this together.” 

The operating theatre complex is fully equipped for the future.
Work processes have also been optimised.

Question about this story? Ask your question

Wie aan OK-centrum VieCuri Venlo werkte

  1. construction workCornelissen Aannemingsbedrijf B.V.Mentioned in New operating theatre demonstrates VieCuri’s ambitious development
  2. electrical installationsSpie Worksphere B.V.Mentioned in New operating theatre demonstrates VieCuri’s ambitious development
  3. mechanical installationsCroonwolter&dros B.V.Mentioned in New operating theatre demonstrates VieCuri’s ambitious development
  4. architectural designAan de Amstel ArchitectenMentioned in New operating theatre demonstrates VieCuri’s ambitious development
  5. building services designSweegers en de BruijnMentioned in New operating theatre demonstrates VieCuri’s ambitious development
  6. structural designSchreuderMentioned in New operating theatre demonstrates VieCuri’s ambitious development

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectVieCuri Venlo operating theatre complex
  • ThemeSafe and reliable healthcare buildings
  • SubjectHospitals