The new hot floor at Rode Kruis Ziekenhuis (RKZ) in Beverwijk opened in November 2024. It is the result of close collaboration between the hospital and the construction partners. Integrating the existing infrastructure with the new building was crucial. “Both for the continuous operation of the existing hospital and for future-proof care processes”, say care manager Judith Ferwerda, construction director Willem-Jan Hanegraaf and Jos Lans, director of main contractor Medexs.
The RKZ’s new building is located at the front of the existing building, which dates from the 1970s, with a new full-height glazed entrance façade on Vondellaan. The new building houses a hot floor and forms the heart of the hospital’s phased renewal. It includes the Emergency Department, an Emergency Care Centre with an ambulance entrance, a GP out-of-hours service, an operating theatre suite with recovery area, and full radiology and acute admissions departments. The new hospital entrance connects the new departments to the existing entrance hall. Great care has been taken to create a healing environment through natural daylight and a bright, calming interior, with separate waiting areas and a courtyard garden. The new hot floor opened between November and Christmas 2024 and is fully connected to the existing hospital.

New concepts
Ferwerda is the care manager responsible for the new departments and was one of the RKZ representatives on the project team. “A great deal of attention was paid to logistics and ensuring good connections,” she says proudly during a tour. First and foremost, this was about care processes. “The hospital expansion is not just about technical requirements, such as upgrading the installations and providing larger operating theatres. The building has also been adapted to support future-proof care, with a major change being genuine collaboration with other parties within the hospital. We have introduced a new concept in collaboration with the existing GP out-of-hours service and our Emergency Department, called SEMD: Spoedeisende Medische Dienst. The Emergency Department now has space for the cardiac monitoring unit and CCU (Critical Care Unit).”

Internal ambulance bay
The new building has a floor area of approximately 5,000 square metres, spread over several storeys. The ground floor houses the Emergency Department, SEMD and an internal ambulance bay with space for three ambulances. The entire Radiology department is located above, with MRI and CT scanners, as well as an Acute Admissions Unit.
The top floor of the new building houses the Operating Centre, with six operating theatres, instrument preparation rooms and a recovery area. One of the operating theatres can also be converted into a hybrid operating theatre in the future. All operating theatres are equipped for the use of imaging techniques.

Communication
Communication with users and local residents was essential during the construction process, which began in February 2023. “We built on the car park by the old entrance, which was no longer accessible during the works. The surrounding area is also densely built up,” says Lans. Hanegraaf played an important role in management and coordination, aligning hospital operations with construction, overseeing the relocation of departments and communicating with the local community. “Willem-Jan, our link with the hospital, handled that very well,” says Lans. “Every Wednesday, we took people around the site to show them how work was progressing. It worked extremely well.”
Sustainable, effective and efficient
Hanegraaf says: “The aim was to make the new building as sustainable as possible. There was a major difference between the gas-fired energy generation in the existing building, supported by chillers, and the ATES system, supported by heat pumps, for the period after opening.” First, the technical infrastructure of the existing building had to be adapted to serve the new development. “The hospital remained fully operational throughout the process. Medexs submitted a budget, logistics plan and schedule for the works, and delivered in line with the contract. The new building was also connected to the existing hospital while care continued uninterrupted. That was quite an achievement.” Ferwerda adds: “Of course, adjustments were needed along the way. These were dealt with through the three-way coordination between Willem-Jan, the contractor and us. We also visited other hospitals, and the close lines of communication helped ensure an effective and efficient process.”

Close collaboration
Lans says: “To complete the works within 1.5 to 2 years, you need close collaboration, including with suppliers and subcontractors. Advanced technologies have been used, and everyone is needed throughout the process. We can scientifically substantiate our energy-reduction decisions, for example in the operating theatres.” Hanegraaf adds: “The success of a project like this is certainly not guaranteed. Together, you have to answer the question: ‘How can you guarantee the hospital’s continuity, bring the new departments into use and prepare for future developments, combining new and existing infrastructure while the entire existing hospital remains operational?’ This requires good management and communication. During construction, we tried to minimise disruption.”
Renovation of the existing building
Ferwerda cannot yet say much about the exact scope of the renovation of the existing building, which includes the Burns Centre, inpatient wards and outpatient clinics. To enable the plans, which have yet to be finalised, various hospital functions will have to be temporarily relocated. “We want to improve every department, but the renovation programme will of course need to be organised differently from the new-build programme.” Decisions are still to be made. “Staff are already very satisfied with the new building, with much more daylight and better visibility, improved logistics and, as a result, better care processes. The objectives for the new building have been met.”
Have a business enquiry for Medexs? Get in touch
Wie aan Hotfloor werkte
- Technology development partner
SiemensMentioned in Hotfloor to become the new heart of Rode Kruis Ziekenhuis - Construction managementAdviesbureau VriesemaMentioned in Hotfloor to become the new heart of Rode Kruis Ziekenhuis
- DesignBureau Berndsen voor architectuurMentioned in Hotfloor to become the new heart of Rode Kruis Ziekenhuis
- Adviseur technische installaties en energieSweegers en de BruijnMentioned in Hotfloor to become the new heart of Rode Kruis Ziekenhuis
- mechanical installationsVan Dorp projectenMentioned in Diverse mechanical services package for new Rode Kruis Ziekenhuis building in Beverwijk