A new centre providing integrated care for mothers and children has been built in a short time on the Lijnbaan side of HMC Westeinde hospital in The Hague. The HMC Sara de Bronovo Mother and Child Centre (MKC) was completed on 24 September by Wagenbouw, part of Dutch Cabin Group. What makes the extension unusual is that it starts on the second floor and is built entirely from 270 modules. 

“Semi-permanent,” says Berry van Leeuwen, Director of Projects at Directbouw. “The brief was for eight years. That will probably be longer, but 30 years is also feasible.” In time, Haags Medisch Centrum (HMC) will provide care from two locations, Westeinde and Antoniushoeve (Leidschendam). Renovation and refurbishment work has begun at HMC Westeinde as part of this plan. One of the first major projects is the construction of a new mother and child centre. Van Leeuwen says: “This has given HMC a substantial amount of extra floor space. Once the move is complete, the old mother and child centre will be vacated and can be refurbished, making room for another department. A hospital is essentially an organism that is constantly being renovated. This more or less temporary facility, which could be built very quickly, was an excellent fit.”

Raised up

Family-centred care for (expectant) mothers, babies and children will soon begin in the new building. The two-storey building stands on eight-metre-high stilts above the entrance area on the Lijnbaan side. The main entrance has therefore been temporarily moved from the Warmoezenierstraat side. “By placing the building on a steel structure, the MKC can use facilities on the same level in the main building, such as the operating theatres,” explains Van Leeuwen. “If complications arise during a birth, a bed can be wheeled to an operating theatre very quickly.”

Not quite standard

The MKC is built entirely from prefabricated units, prepared and pre-assembled at the factory in Klundert. All the units measure 3 by 6 metres. “So far, they’re standard,” Van Leeuwen continues. “Because we were supplying the second and third floors, we had to match the heights of the existing hospital building to which the extension connects. We all know that ceilings are full of ducts, pipes and services, so the units are considerably higher than usual. All the service penetrations were also prepared at the factory, and some of the units were adapted to operate at positive or negative pressure. We always try to prefabricate as much as possible, but with a hospital, a relatively large amount of work is done on site.”

One of the final units is hoisted into position.

Collaboration

Preparations began in 2019. Van Leeuwen says:­ “We sat down with the client to explore options for semi-permanent accommodation that would meet the Programme of Requirements. After a short break, the following year we received an advance order to start producing the basic units, so that construction could get under way quickly at a later date. After signing the final agreement, we erected the steel supporting structure in the summer of 2020, and in February this year we hoisted the last of the 270 modules into place. All the modules are connected across the two floors. Some have a façade panel, while others have only a roof and floor, with small columns to maintain the structural connection. To the untrained eye, however, it is not apparent that they are prefabricated units.”

Integrating building services

Prefabrication means a short construction period but a lot of preparation, and that takes collaboration. Van Leeuwen says:­ “During the on-site construction work, we worked particularly closely with Unica, HMC’s building services contractor. But of course, the process starts much earlier. You are forced to think everything through at an early stage. Using the technical design by Ingenieursbureau Prent Landman, we worked through the whole building with Unica to identify all the interfaces. This enabled us to make as many of the necessary openings as possible in advance and to integrate the services neatly into the modules on site. The partition walls and suspended ceilings were also installed on site, as was the flooring, all in accordance with the strict guidelines for hospital construction.” 

Façade

The outer cavity wall currently features grey insulated sandwich panels. “A screen façade made from corrugated sheet will be added in front,” says Van Leeuwen. “The 3 by 6 metre grid will then be completely concealed from the outside. We’re using special sandwich panels that can take screws. Several building services plant items are located on the roof, mainly along the stronger edges. The extension does not have a lift. Everyone uses the nearby vertical circulation cores in the existing main building.”

And so HMC has created an extension intended to be temporary, using a fast, flexible solution. The building is highly functional, has a fresh appearance inside and will get an attractive outer skin. It would come as no surprise if it were still in use in 30 years’ time.    

A business enquiry for Unica? Get in touch

Who worked on it

HMC Sara de Bronovo Moeder- en Kindcentrum in Den Haag

  1. huisinstallateurUnica
  2. prefab unitsWagenbouw
  3. technical designIngenieursbureau Prent Landman

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectHMC Sara de Bronovo Moeder- en Kindcentrum
  • ThemeFaster, more flexible healthcare construction
  • SubjectHospitals
  • CompanyUnica
  • CompanyWagenbouw
  • CompanyIngenieursbureau Prent Landman
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.