General

Masterplan for the UZ Gent campus

UZ Gent wil met haar Masterplan een voortrekkersrol nemen en tonen dat welzijn en duurzaamheid hand in hand kunnen gaan.
UZ Gent wil met haar Masterplan een voortrekkersrol nemen en tonen dat welzijn en duurzaamheid hand in hand kunnen gaan.

UZ Gent is currently working on implementing its Masterplan for the campus on Heymanslaan. The existing car park tower will make way for a flexible hospital building that puts patients and visitors first. With this project, UZ Gent aims to take a leading role and show that wellbeing and sustainability can go hand in hand. VK architects+engineers developed the concept.

Setting a new standard in care and sustainability

The UZ Gent campus is located on Heymanslaan, a long-standing landmark for healthcare on the edge of the city centre. “But our infrastructure is outdated,” says Petra Demoor, project manager at UZ Gent. “With our Masterplan, we want to catch up and create hospital infrastructure that is fit for the future.” Work on the plan began in 2019. The preliminary design is now complete, and the permit and funding applications have been submitted for approval. The aim is to build a new facility on the site of the existing car park tower, housing the hospital’s main medical and care activities. Visitors and patients will be able to park beneath the new building. A logistics building will also be constructed at the rear of the site, where deliveries will be received before being transported underground to their destinations. “The aim is to create a green belt around the hospital,” says Demoor.

Simon Ossieur (VK architects+engineers)
Tine van Besien (VK architects+engineers)
Petra Demoor (UZ Gent project manager)

Healing environment

This is not an idea that has come out of nowhere. “Numerous studies have shown a positive link between access to green spaces and patient wellbeing. ‘Green for everyone’ is therefore our motto. Greenery will surround, fill and cover the building, with terraces, patios and roof gardens. Nature will extend into the building. Daylight is another important factor in creating a healing environment. The building’s sawtooth design will allow us to create as many daylight-facing façades as possible, bringing natural light into every area: patient rooms, the operating department, offices, and more.” The design is by VK architects+engineers. “Building a hospital involves a great deal: design, permits, building services, structural studies, and more. It is a complex puzzle to solve. VK architects+engineers brings all these disciplines together under one roof, making it exceptionally well placed to support us throughout the entire process,” says Demoor. “Its expertise in this field is beyond question. It is also aiming high when it comes to sustainability.”

All-electric heating and cooling

For UZ Gent, sustainability was another key pillar of the Masterplan. As early as 2019, the hospital set out its ambition to make its new building as independent from fossil fuels as possible. “That was almost prophetic, given the current energy climate,” recalls Simon Ossieur, project manager at VK architects+engineers. The decision was made to provide heating and cooling entirely through electricity. “UZ Gent is firmly committed to a low-temperature system, with climate ceilings maintaining a comfortable temperature. We also want to tackle legionella control in this way. We are determined to phase out steam generation. This is still the last major obstacle. It is already a viable option in other countries, but here legislation is holding things back for now. The same applies to adiabatic humidification. We want to demonstrate in black and white that these technologies are 100% safe, and thereby make good on our ambition to be 100% electric. We have another three to four years to do that.”  

Energy-efficient operation

Energy independence, however, starts with energy efficiency. Ossieur explains: “Hospitals are highly energy-intensive buildings, because the building itself accounts for only a fraction of the energy bill. There are ventilation airflows, medical equipment, data management, and more to consider. Even with extensive use of solar panels, we would be able to generate only around 13 to 17% of the electricity we need on site.” To make its hospital as energy-efficient as possible, UZ Gent also wants to recover as much energy as it can. “A hospital is a unique environment where there is simultaneous demand for cooling and heating at all times. By bringing the cooling and heating systems as close together as possible in terms of temperature, we can exchange energy between them. Any energy that cannot be exchanged immediately will be stored. The water in the sprinkler tanks offers an economical solution for this. It will enable us to cool and heat efficiently.”

Circular construction

Sustainability, however, goes beyond energy efficiency. UZ Gent had already requested the application of circular construction principles in its tender documents. “It really starts with the design,” says Tine van Besien, sustainable design engineer at VK architects+engineers. “The aim is to create a basic structure that can last for hundreds of years, even as needs change. The fit-out must be flexible and circular. We have therefore applied the so-called layers approach in the design. Only what is needed for the building’s stability is fixed; flexibility is the priority in every other respect. For example, we are using a beamless structure so that spaces can easily be adapted if their use changes. We are explicitly opting for prefabrication and circular use of materials for the flexible fit-out. The façade, comprising timber frame construction with brick slips, is also an example of circular design, with its high degree of modularity and the choice of materials that can be easily removed and recycled.”

Reusing materials and rainwater

Another priority was reusing materials already on site. “This is no easy task, as structural integrity must be maintained and the work must also fit within the planned timetable for each phase,” says Van ­Besien. The steel structure of the existing car park building ultimately proved to be perfectly suited to the requirements. It will be reused for the structure of the plant floor. Water management was also high on the agenda. UZ Gent asked VK architects+engineers to make the best possible use of every drop of rainwater falling on the 4.6 ha site. This will be achieved by installing two storage basins and a high-performance system for treating the collected rainwater. Most of it will be used to flush toilets. “That is not straightforward in a hospital environment, so we will use ultrafiltration,” adds Demoor. Other potential uses for reclaimed water include the cooling towers, the IVAGO district heating network, to which UZ Gent is still connected, and the roof gardens.

Ongoing monitoring

If all goes according to plan, work will begin next year, after which the Masterplan will take shape step by step. UZ Gent hopes to put the new hospital into use in 2029. VK architects+engineers has been appointed as delegated client to ensure successful delivery in the next phases of the project
as well.    

Een zakelijke vraag aan VK architects+engineers ®? Get in touch

Wie aan Masterplan voor campus UZ Gent werkte

  1. architectVK architects+engineersIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectMaster plan for UZ Gent campus
  • ThemeHospital construction and refurbishment
  • SubjectGeneral
  • CompanyVK architects+engineers ®
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow