Masterplan for UZ Gent campus. Setting a new standard in care and sustainability

UZ Gent wil met haar Masterplan een voortrekkersrol nemen en tonen dat welzijn en duurzaamheid hand in hand kunnen gaan.
UZ Gent wil met haar Masterplan een voortrekkersrol nemen en tonen dat welzijn en duurzaamheid hand in hand kunnen gaan.

UZ Gent is currently implementing its Masterplan for the campus on Heymanslaan. The existing multi-storey car park is to make way for a flexible hospital building that puts patients and visitors first. With this project, UZ Gent aims to take a leading role and show that wellbeing and sustainability can go hand in hand. VK architects+engineers developed the concept.

UZ Gent’s campus is located on Heymanslaan, a landmark for healthcare on the edge of the city centre for many years. “But our infrastructure is ageing,” says Petra Demoor, project manager at UZ Gent. “With our Masterplan, we want to catch up and create hospital infrastructure that is fit for the future.” Work on the plan began in 2019. The preliminary design is now complete, and the permit and subsidy applications have been submitted for approval. The aim is to build a new facility on the site of the existing multi-storey car park, housing the hospital’s main medical and care activities. Visitors and patients will be able to park beneath the new building. A logistics building will also be constructed at the rear of the site, where deliveries will be received before being transported underground to their final destination. “The aim is to create a green belt around the hospital,” says Demoor.

Healing environment

This idea has a solid basis. “Numerous studies have shown a positive link between the presence of greenery and patient wellbeing. ‘Green for everyone’ is therefore our motto. Around, in and on the building, with terraces, patios and roof gardens. Bringing nature right into the building. Daylight is another important factor in creating a healing environment. Thanks to the saw-tooth design, we can create as many façades as possible that admit daylight. This will allow daylight into every space, from the rooms to the operating department and offices.” The design was created by VK architects+engineers. “A great deal goes into building a hospital: design, permits, building services, structural studies, and more. It is a complex puzzle to solve. VK architects+engineers brings all these different disciplines together under one roof, making it ideally placed to support us throughout the entire process,” says Demoor. “Its expertise in this field is beyond question. It also aims to set a high bar for sustainability.”

Fully electric heating and cooling

For UZ Gent, sustainability was another key pillar of the Masterplan. As early as 2019, the hospital stated its ambition to make its new building as independent of fossil fuels as possible. “Almost prophetic, given the current energy climate,” recalls Simon Ossieur, project manager at VK architects+engineers. The decision was made to use fully electric heating and cooling. “UZ Gent has firmly opted for a low-temperature system, which will provide a comfortable temperature through radiant ceiling panels. We also want to tackle Legionella control in this way. We are keen to phase out steam production. This is the last major stumbling block. In other countries, this is already a viable option, but here the legislation is still holding things back. The same applies to adiabatic humidification. The aim is to demonstrate in black and white that these are 100% safe technologies, thereby underpinning our ambition to be 100% electric. We have another three to four years to do that.”  

Energy-efficient operation

Energy independence, however, starts with energy efficiency. Ossieur says: “Hospitals are very energy-intensive buildings, because the building itself accounts for only a fraction of the energy bill. There are ventilation airflows, medical infrastructure, data management, and more. Even with extensive use of solar panels, we would only be able to generate 13 to 17% of the electricity we need on site.” To make its hospital operations as energy-efficient as possible, UZ Gent also aims to recover as much energy as it can. “A hospital is a unique environment where cooling and heating are needed simultaneously at all times. By bringing the cooling and heating systems as close together as possible in terms of temperature, we can exchange energy between them. Energy that cannot be exchanged immediately will be stored. The water in the sprinkler tanks offers an economical solution for this. It will enable us to cool and heat efficiently.”

Simon Ossieur (VK architects+engineers)
Tine van Besien (VK architects+engineers)
etra Demoor (UZ Gent)

Circular construction

Sustainability, however, goes beyond energy efficiency alone. UZ Gent had already requested in its tender specifications that the principles of circular construction be applied. “It actually starts with the design,” says Tine van Besien, sustainable design engineer at VK architects+engineers. “The aim is to create a basic structure that can last for hundreds of years, even as needs change. The fit-out must then be flexible and circular. That is why we have used the so-called ‘layers’ approach in the design. Only what is needed to ensure the building’s stability is fixed; flexibility takes precedence in every other respect. For example, we are using a beamless structure so that spaces can easily be adapted if their use needs to change. For the flexible fit-out, we have specifically chosen prefabrication and circular use of materials. The façade, made of timber frame construction with brick slips, is also a model of circularity, with its high degree of modularity and choice of materials that can be easily removed and recycled.”

Reusing materials and rainwater

A second priority was reusing materials already present on the site. “This is no easy task, because not only does the structure have to remain stable, it also has to fit within the proposed timetable for the various phases,” says Van Besien. The steel structure of the existing car park ultimately proved perfectly suited to the requirements. It will be reused for the structure of the technical floor. Water management was also high on the agenda. UZ Gent asked VK architects+engineers to reuse as much as possible of every drop of rainwater falling on the 4.6 ha site. This will be achieved by building two retention basins and installing a high-performance system to treat the collected rainwater. Most of it will be used to flush toilets. “This is not straightforward in a hospital environment, so we will use ultrafiltration,” adds Demoor. Other potential uses for the water include the cooling towers, the IVAGO district heating network, to which UZ Gent is still connected, and the roof gardens.

Keeping a close eye on progress

If all goes according to plan, work will start next year, after which the Masterplan will take shape step by step. UZ Gent hopes to open the new hospital in 2029. VK architects+engineers has been appointed as delegated client to ensure the project is delivered successfully in the next phases of the process
as well.    

Een zakelijke vraag aan VK architects+engineers ®? Get in touch

Wie aan Masterplan voor campus UZ Gent werkte

  1. architectVK architects+engineersMentioned in Masterplan for the UZ Gent campus

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectMaster plan for UZ Gent campus
  • ThemeSustainable healthcare buildings
  • SubjectGeneral
  • CompanyVK architects+engineers ®
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.