Modular Moeder- en Kindcentrum HMC equipped with all the amenities

Healthcare is a key market for Dutch Cabin Group.
The specialist in modular building units has already delivered numerous temporary and semi-permanent accommodation solutions for organisations including Erasmus MC, Haga Ziekenhuis and Antes Groep. For Haaglanden Medisch Centrum’s Westeinde site, it is building the new Moeder-en Kindcentrum on a 7.5-metre-high steel structure.
With more than 30 years’ experience building temporary healthcare accommodation, he has ‘seen it all’, but this project is something special, says senior project manager Wim van der Ven of Wagenbouw, the Dutch Cabin Group subsidiary delivering the Moeder- en Kindcentrum. “Building such a large modular complex on a steel structure 7.5 metres above ground is not an everyday job for us. Installing the units requires millimetre-precision, which makes it a great challenge!”

Skybridge
The Moeder- en Kindcentrum will have a total floor area of 4,800 m2 across two storeys. A skybridge will connect it to the second and third floors of the existing HMC Westeinde, ensuring that no time is lost when acute care is needed. The complex will include fourteen birthing rooms, six of them with birthing pools, 38 maternity and neonatal rooms, rooms for twins, and sixteen brightly coloured children’s rooms. Particular attention is being paid to the interior and finishes. “It’s going to look fantastic,” says Van der Ven.
Building at height
The construction team spent more than a year and a half working through the details of the plan. Van der Ven says: “The site presents a complex construction challenge: part of the building will be above the car park of an adjacent building, where foundations are not permitted, above the car park entrance and above the ambulance bay. It also has to connect to the existing hospital at the correct height. After fine-tuning the preliminary designs, a final design was produced.”
DS units
A total of 270 units make up the building. Each unit measures 6 by 3 metres and has a custom height of 3.9 metres. These DS units (Direct Systeem) are manufactured at the company’s own factories in Coevorden and Klundert. The system offers several advantages: the exterior can be tailored entirely to the client’s wishes; units can be connected and configured without limit; they can be stacked up to three storeys high; and they come as standard with a concrete floor. Construction is quick: for this Moeder- en Kindcentrum, it will take around eleven months from the start of foundation work to completion.

Phasing
Work is currently under way to complete the foundations and groundworks. The steel structure is due to start going up around the turn of the year. Because of the complex site, it cannot be erected in one go. “We would block ourselves in, because there are buildings on three sides,” explains senior project manager Berry van Leeuwen. “So we’ll install the first half of the steel structure, then put two storeys of units on top. Next comes the rest of the steel structure, followed by the units on that section. At the same time, we’ll start fitting out the first section. The fit-out, including the installation of services, fixed furniture and various other medical equipment, will continue until the expected handover in summer 2021.
Urban project
The project is not only challenging from a construction perspective, it also presents logistical difficulties. Van Leeuwen says: “We’re building in an urban area, which makes it harder to deliver the units and materials. To reduce the number of transport movements, we’re having as many materials as possible delivered to our factory in Coevorden. They’re loaded into the units there, which are then taken straight up to the site.” He, too, considers it a special project. “We’ve already delivered many impressive healthcare, school and office buildings. With the expertise we have in-house, we know how to handle this one too!”
(We’ll be back with you around mid-2021 with, among other things, photos of this special project.)