New arteries for a working hospital
Text Tamara Brouwers Beeld ULC Installatietechniek

Haaglanden Medisch Centrum (HMC) is upgrading the technical infrastructure at its Westeinde site, which supplies large parts of the hospital with electricity, heating, cooling and water, among other services. ULC Installatietechniek is carrying out the work as part of a mechanical and electrical services consortium. Much of the new infrastructure is being installed alongside the existing systems, which will remain operational until the time comes to switch over. In a hospital that runs 24 hours a day, precision is essential.
Some of the existing infrastructure at HMC Westeinde is around 50 years old. Upgrading it was therefore essential. The new infrastructure will provide a solid foundation for the years ahead and make room for future construction projects.
Work on the central mechanical services infrastructure begins with heating, cooling and domestic hot water pipes running through the first service risers and the foundation-pile basement. Further sections will follow. Jacco Kok, project manager for mechanical services, is responsible at ULC Installatietechniek for the central heating, cooling and domestic hot water infrastructure, among other things. “We’re building a completely new infrastructure alongside the existing one,” he says. “Once the new section is ready, we can connect the new systems to it and switch over from the old systems in phases.”

Fitting everything into an existing hospital
The work is preceded by an extensive engineering phase. New pipe routes must be fitted in among existing services and structures. New service risers have been planned wherever possible. For routes through the basement, the existing conditions have even been fully scanned and modelled to establish the available space and routes.
The electrical power supply is also getting new infrastructure. Wim Eerland, project manager for central electrical installations, is working on new medium-voltage equipment, transformers and distribution boards, among other things. These systems will also be built alongside the existing ones before being switched over in stages. “You have to find routes for the cables and take the existing structure into account. You can’t just cut a hole in a concrete wall. It takes around nine months of engineering just to get everything right on paper.” Around eight people at ULC are working on this, alongside teams from suppliers and other parties involved. “Everyone has their own expertise,” says Eerland. “We have to make sure it all comes together and is worked out properly.”

High-pressure water mist system
Another key element is the installation of high-pressure water mist for fire protection. According to Eric Brugman, head of fire protection, the pipe diameters required are considerably smaller, and water mist uses far less water than a traditional sprinkler system. This means that any water damage in the event of activation is many times lower, which is essential for continuity in a hospital. ULC is now working on the required infrastructure, including the plant room for the system and pipe routes through the foundation-pile basement and service risers, among other areas. Ultimately, high-pressure water mist protection will be installed throughout the hospital.

Infrastructure first, then build on
The work is part of a wider programme. The upgraded infrastructure must also enable future projects at HMC. One specific example is the new intensive care unit, which will be built partly on top of the existing building. Around two-thirds will be housed in the new-build section and one-third in the existing hospital. Completion is scheduled for the end of 2027. The new central services must be available in time.
With several projects running in parallel, coordination with HMC and other construction partners is important. At the same time, the Technical Management department remains responsible for the services in the existing hospital and will later also be responsible for maintaining the new systems. Kok sees this as one of ULC’s specialisms. “A hospital has far more services and disciplines working together than, for example, an office building. We know how to manage them during construction while keeping the hospital running.” The project is therefore laying a new foundation for the future of HMC Westeinde and demonstrating the value of phased construction in a healthcare environment that never sleeps.
Een zakelijke vraag aan ULC Installatietechniek? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectGeneral
- CompanyULC Installatietechniek



















