New arteries for a working hospital

Text Tamara Brouwers Beeld ULC Installatietechniek

360°-opnames brengen de werkruimte en toegankelijkheid voor nieuwe installaties vooraf haarscherp in beeld.
360°-opnames brengen de werkruimte en toegankelijkheid voor nieuwe installaties vooraf haarscherp in beeld.

Haaglanden Medisch Centrum (HMC) is upgrading the technical infrastructure at its Westeinde site, which supplies large parts of the hospital with electricity, heating, cooling and water, among other services. ULC Installatietechniek is carrying out the work as part of a mechanical and electrical services consortium. Much of the new infrastructure is being installed alongside the existing systems, which will remain operational until the time comes to switch over. In a hospital that runs 24 hours a day, precision is essential.

Some of the existing infrastructure at HMC Westeinde is around 50 years old. Upgrading it was therefore essential. The new infrastructure will provide a solid foundation for the years ahead and make room for future construction projects.

Work on the central mechanical services infrastructure begins with heating, cooling and domestic hot water pipes running through the first service risers and the foundation-pile basement. Further sections will follow. Jacco Kok, project manager for mechanical services, is responsible at ULC Installatietechniek for the central heating, cooling and domestic hot water infrastructure, among other things. “We’re building a completely new infrastructure alongside the existing one,” he says. “Once the new section is ready, we can connect the new systems to it and switch over from the old systems in phases.”

The point cloud is used to survey existing obstructions, while Dalux is used to check whether the design can be built.

Fitting everything into an existing hospital

The work is preceded by an extensive engineering phase. New pipe routes must be fitted in among existing services and structures. New service risers have been planned wherever possible. For routes through the basement, the existing conditions have even been fully scanned and modelled to establish the available space and routes.

The electrical power supply is also getting new infrastructure. Wim Eerland, project manager for central electrical installations, is working on new medium-voltage equipment, transformers and distribution boards, among other things. These systems will also be built alongside the existing ones before being switched over in stages. “You have to find routes for the cables and take the existing structure into account. You can’t just cut a hole in a concrete wall. It takes around nine months of engineering just to get everything right on paper.” Around eight people at ULC are working on this, alongside teams from suppliers and other parties involved. “Everyone has their own expertise,” says Eerland. “We have to make sure it all comes together and is worked out properly.”

The Dalux model connects designers, installers, the contractor and the client for coordination and project documentation.

High-pressure water mist system

Another key element is the installation of high-pressure water mist for fire protection. According to Eric Brugman, head of fire protection, the pipe diameters required are considerably smaller, and water mist uses far less water than a traditional sprinkler system. This means that any water damage in the event of activation is many times lower, which is essential for continuity in a hospital. ULC is now working on the required infrastructure, including the plant room for the system and pipe routes through the foundation-pile basement and service risers, among other areas. Ultimately, high-pressure water mist protection will be installed throughout the hospital.

The medical centre’s complex boiler room is modelled in detail in Revit to resolve building services clashes in advance.

Infrastructure first, then build on

The work is part of a wider programme. The upgraded infrastructure must also enable future projects at HMC. One specific example is the new intensive care unit, which will be built partly on top of the existing building. Around two-thirds will be housed in the new-build section and one-third in the existing hospital. Completion is scheduled for the end of 2027. The new central services must be available in time.

With several projects running in parallel, coordination with HMC and other construction partners is important. At the same time, the Technical Management department remains responsible for the services in the existing hospital and will later also be responsible for maintaining the new systems. Kok sees this as one of ULC’s specialisms. “A hospital has far more services and disciplines working together than, for example, an office building. We know how to manage them during construction while keeping the hospital running.” The project is therefore laying a new foundation for the future of HMC Westeinde and demonstrating the value of phased construction in a healthcare environment that never sleeps.  

Een zakelijke vraag aan ULC Installatietechniek? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
  • CompanyULC Installatietechniek
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.