New Noorderhart strengthens healthcare infrastructure in North Limburg (B)
Text Roel van GilsImage Noorderhart

Two crucial construction projects are currently under way on the Noorderhart Mariaziekenhuis site. Work is under way on a new rehabilitation and MS centre, while the hospital is also being expanded with a new surgical day centre. At the same time, care at the existing Mariaziekenhuis must not be disrupted. In short, this is a project full of challenges. We speak to Dirk Van Gorp, director of facilities at Noorderhart.

The new Noorderhart was formed by the merger of the existing Mariaziekenhuis and the rehabilitation and MS centre in Pelt. “The two sites are 5 kilometres apart and are now being brought together at the Mariaziekenhuis site,” says Van Gorp. “The initial impetus was the ageing infrastructure at the rehabilitation and MS centre. Built in the 1970s, it no longer met contemporary requirements. Building a replacement facility on the same site was not really an option. It made much more sense to bring it together with Mariaziekenhuis, so that we can provide patients with comprehensive care at a single location. Hospital admissions and rehabilitation will be better integrated.” Mariaziekenhuis, in turn, needed additional space to accommodate the growing number of day treatments. Plans were therefore drawn up at the same time for a surgical day centre.
Structural work under way
Although these are two separate construction projects, they were tendered in parallel as a single contract. It was a deliberate choice, says Van Gorp. “The two buildings adjoin the rear of Mariaziekenhuis and each other. From a site-management perspective, it would not be practical to separate the projects. We will also tender the building services and finishing work as a single package. Structural work on both projects has been under way since November 2023, with the aim of making them wind- and watertight by mid-2025. The building services will then be installed and finishing work will begin, so that the entire project can be brought into use by late 2026 or early 2027. Construction is progressing well. Several concrete walls have already been erected at the rehabilitation and MS centre, while the contractor has started excavating for the foundations of the surgical day centre. As the new buildings directly adjoin the existing hospital, a number of utility services were relocated during the preparatory phase. This phase also included expanding the car park by 295 spaces. These have been in use since early April.”

Sustainability
According to Van Gorp, the project is full of challenges. “It starts with bringing two organisations together. This also presents technical challenges when connecting the new buildings to the existing ones. A wide range of sustainability features are also being incorporated into the buildings, making the technical side quite complex. For example, the new buildings will be carbon-neutral in operation. This means a ground-source heating and cooling system, PV panels on the roof and rainwater harvesting for flushing toilets.” Van Gorp says that a wind turbine on the site was even considered, but ultimately proved unfeasible because of its proximity to a residential area and height restrictions. These factors would have reduced its efficiency.
Wayfinding
The surgical day centre is being built directly behind the existing hospital. It will contain four operating theatres and a locomotor and cardiac rehabilitation room. The building will also house a psychiatric day hospital, a pain centre and an oral, maxillofacial and facial surgery centre. The rehabilitation and MS centre is located a little further across the site, but will be accessible via the hospital through a connecting corridor, alongside which a new bistro will be situated. “The main design challenge was linking the buildings without creating a maze,” says Van Gorp. “We believe we have succeeded. Visitors and patients will find it easy to navigate between the different parts of the building. A great deal of attention has been paid to wayfinding. From the entrance hall, you can head straight to either the rehabilitation and MS centre or the surgical day centre, arriving at the centre of each building. Internal logistics are also kept separate from patient traffic on level minus 1.”
Smart features
A distinctive feature of the rehabilitation and MS centre is its two large courtyards. “This allows patients to enjoy the fresh air in a safe environment,” explains Van Gorp. “It also gives staff at the nursing station an optimal view of the corridors. That is useful during night shifts, as the lighting is controlled by presence sensors. The building is also easy for people undergoing rehabilitation to access, with few obstacles. For example, they do not need to use lifts. Outpatients arriving from outside can access the large rehabilitation room directly through a separate entrance. The room also has north-facing sawtooth roofs. These let in plenty of daylight while limiting heat gain.” The design is well considered on every front, while the structural work is being carried out using fairly traditional methods. “We believe a concrete structure with a brick façade is a future-proof choice. It offers a very long service life. We are also opting for large spans, which will give us reasonable flexibility in the layout and use of the building over the long term.”
The new rehabilitation and MS centre and surgical day centre will add 23,000 m2 to Noorderhart, bringing its total area to 57,000 m2. “We believe this expansion and merger will significantly strengthen healthcare infrastructure in North Limburg.”
Facts and figures
Client and healthcare provider:
Noorderhart VZW
Architect:
M4 architecten en ingenieurs from Wetteren
Structural engineer:
Studiebureau De Klerck engineering from Brugge
Contractor:
TM Vanderstraeten-Houben
Building services consultant:
Studiebureau De Klerck engineering from Brugge
Total floor area:
23,000 m²
Construction timeline:
· Architect selection: 2020
· Construction start: November 2023
· Watertight shell completed: July 2025
· Expected opening: January 2027
Capacity:
· total: 120 beds for rehabilitation and MS
· 4 operating theatres with day-surgery beds
· various day-treatment services