A successful interior fit-out for Het Wooldhuis
Text Gerrit TenkinkImage De Bruin Architecten

The challenge for a furniture supplier is to meet the client’s requirements. KVS/Vervoort Meubelen more
than rose to that challenge when fitting out Het Wooldhuis.
Joost Graat, Care Manager Netherlands at Vervoort, explains how the partnership came about. “The project was initially assigned to KVS Project- & Kantoorinrichting in Zwolle. They were looking for a specialist in care and approached us. Based on the interior design by Inggé Syaranamual (ontwerpstudio Syara), we put together a furniture proposal. We have extensive experience in care, so we were well placed to answer questions about the right upholstery, sustainability (choice of materials, construction, lifespan and waste processing) and the durability of the furniture.”
As well as fitting out the lounges, hair salon, staff room, restaurant and day activity facilities, Vervoort’s architects, working with KVS and Syara, designed several themed alcoves along the corridors. A new reception desk was also installed, with a mail pigeonhole and work cabinet behind it.
Het Wooldhuis chose Vervoort for the KVS/Vervoort Meubelen partnership not only because of an extensive presentation in Heino, but also thanks to the companies’ employees, who shared their vision and contributed ideas in collaboration with Syara, and to Vervoort’s large showroom in Goirle. “We have a showroom of more than 4,000 square metres, where our six account managers specialising in care and four studio employees specialising in care could give a very tangible demonstration of what Vervoort has to offer. We find that clients appreciate this. Ultimately, it was also what led Het Wooldhuis to work with KVS/Vervoort Meubelen.”
FACTS AND FIGURES
Client: Stichting Zorgspectrum ’t Zand, Zwolle
Architect: De Bruin Architecten, Zwolle
Accommodation consultant: Penta Rho, Apeldoorn
Building contractor: Dons & Troost, Staphorst
Interior fit-out: KVS/Vervoort Meubelen, Goirle
Ventilation units: ClimaRad, Oldenzaal
Construction phase 1: Vijvergebouw
Construction phase 2: Parkgebouw (almost simultaneously with phase 1)
Construction phase 3: Connecting corridor, central kitchen and communal facilities
· Architect selection: 2018
· Start of demolition phase A (Nijenhuys): 2020
· Completion of new-build phases 1 and 2: January/February 2023
· Move-in: March/April 2023
· Start of demolition phase B (main building): May 2023
· Start of new-build phase 3: September 2023
· Completion of new-build phase 3: March 2024
Total site area: approx. 30,860 m2
Total building area: approx. 7,900 m2
Capacity: 90 client studios with en-suite bathrooms, 9 lounges with their own kitchens, day activity facilities, activity support, restaurant and central kitchen, sensory garden and a large park
Een zakelijke vraag aan Vervoort Meubelen? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectResidential care & nursing homes
- CompanyVervoort Meubelen