Residential care & nursing homes

Accurate budgeting with a housing concept and preferred suppliers

L-vormige woonblokken.
L-vormige woonblokken.

The modernisation of ’s Heeren Loo’s Willem van den Bergh site in Noordwijk has taken another two steps forward.

Following the recent opening of the central building (see the previous issue of Bouwen aan de Zorg), which brought many of the central facilities and offices together in sustainable accommodation, two residential complexes opened last November. KBM Groep built a total of 93 care homes for care provider ’s Heeren Loo at two separate locations on the extensive site, for young people and older people with multiple disabilities. 

Willem van der Plas (KBM) and Iwan Nieuwenhuijzen (’s Heeren Loo).

’s Heeren Loo is a care provider that offers support and accommodation nationwide to more than 12,000 people with learning and/or physical disabilities. Its 16,000 employees provide both community-based and residential care. One of its larger sites is Willem van den Bergh, next to the dunes in Noordwijk. In recent years, new buildings have been constructed across several parts of the site, gradually replacing the outdated accommodation. The latest addition comprises two groups of buildings, each consisting of L-shaped blocks.

93 homes

“’s Heeren Loo has a housing concept that is continually being developed and applied to almost all its homes,” says Iwan Nieuwenhuijzen, Property Project Manager at ’s Heeren Loo. “We build two blocks of eight homes joined together in an L shape. The connecting section contains a room that can be used as an office, crisis accommodation, a sensory room or a day activity room. For this development, which comprises five blocks, we have also added an extra living room there. This enabled us to increase the planned total from 88 to 93 homes. The individual living rooms are about 20 m², while the communal living room with kitchen, centrally located between every eight homes, has a net floor area of 100 m².”

Bathroom with hoist.

From dormitories to individual homes

The new homes replace several pavilions scattered across the site. Nieuwenhuijzen: “They date from the late 1960s and early 1970s, when clients still slept in dormitories. After 20 years, changing views led to an upgrade, with partition walls creating individual sleeping areas. But showers and sanitary facilities were still shared. That was understandable from the point of view of being able to supervise residents, but today it no longer meets privacy standards. All the new living areas therefore have their own shower and sanitary facilities. They are also all fitted out in line with the same housing concept.”

Preferred suppliers

’s Heeren Loo works with preferred suppliers, who contribute to the ongoing development of the concept. For example, clients with profound multiple disabilities and older people often do not need a toilet. Geberit has therefore installed removable toilets in these homes, as removing the toilet creates enough space for a shower stretcher. “Working with preferred suppliers also makes it possible to agree better prices, while standardisation gives us a cost advantage,” Nieuwenhuijzen adds. “That is essential, because budgets are under constant pressure.”

Large communal living room with kitchen and island unit.

EPC

One of the preferred suppliers for the western Netherlands is Katwijk-based builder KBM Groep. On 5 November, one day before the final handover, director Willem van der Plas walks through the new living areas and spacious communal living rooms with a smile. “We managed to complete everything on time and within the agreed terms. Given the exceptionally wet months from September to March, followed by the coronavirus crisis, I’m not unhappy with that. The EPC requirement is still 0.4 this year, but next year it will be BENG. To meet the EPC requirement, we installed PV panels on the roof and used energy-efficient systems.”

A fund for extra sustainability

Nieuwenhuijzen has a little more to say about sustainability: “The requirements for care are somewhat less demanding. The buildings do not have to be quite so energy-efficient, but ’s Heeren Loo is still contributing to the sustainability challenge. We set money aside for this at national level. We have annual budgets for building maintenance and functional adaptations (for care facilities; ed.). We can skim some money from the functional budget for extra sustainability, because all the new buildings from recent years are up to date and little money is needed for functional adaptations. This has worked well over the last two years. And we benefit from SDE subsidies, which enabled us to secure the financing.” Van der Plas: “What I find unfair is that consumers get a discount on their mortgage costs if they invest in sustainability, while the care sector does not. ❯ In addition, ’s Heeren Loo pays 7 or 8 cents per kilowatt-hour as a large energy consumer, so you cannot recoup the cost of investing.”

Red brickwork

The results of all the building work can now be seen on Giraffelaan and Appelhof. There was no budget for architectural flourishes. Van der Plas: “The exterior is more restrained than in IAA’s original design. Built on concrete foundations, the homes have calcium silicate inner leaves and internal walls, with red brick outer leaves, the predominant façade material at the Willem van den Bergh site. Concrete plinths and roof edges are examples of details we removed from the design to save costs. And yet the exterior still does not look like Center Parcs, where everything is uniform.”

Residential unit (20 m²).

Island unit

“In any case, we have to keep a close eye on costs,” Nieuwenhuijzen adds. “Building materials are becoming more expensive, requirements are becoming more stringent and care is getting more costly too. That is why we wanted functional buildings and did not want to spend money on things that add nothing to the floor plan. The quality is mainly on the inside. We now have large communal living rooms, each with a large island unit fitted with induction hobs for safe cooking and a powerful extraction system. An island unit means staff do not have to stand with their backs to clients while preparing meals. Each island has two wheelchair spaces.” The residential blocks have Marmoleum flooring, PVC wall protection for wheelchairs and painted lining paper on the walls. Each communal living room has its own colour scheme. The 1.25-metre-wide doors are suitable for bed transport. Some showers have hoists designed to transfer a client from bed to shower in one movement, without unsafe transitions. These costly facilities, like a number of electric doors, were funded from the additional budget for ZZP VG8 care indications.

Outside, each group home has a purpose-designed storage facility by Vaarkamp. Van der Plas: “Here too, centralised, standardised purchasing means the supplier can offer a competitive price. The storage facilities house waste containers, laundry trolleys, three- or four-wheeled bicycles and wheelchair bikes.”    

More than just an electrical installer

De Wit Totaal E-techniek’s involvement in the construction of the new residential buildings for ’s Heeren Loo in Noordwijk goes beyond supplying, installing and commissioning the electrical systems. “We also place great value on soft skills, taking the pressure off the client, how we work with them and considering the end user.”

Sjaak van der Zwan, director of De Wit Totaal E-techniek, believes it is important for his organisation to be more than a straightforward installer. “Whatever we do, we do well. In this case, that means all the electrical systems not purchased centrally by ’s Heeren Loo. Those centrally purchased systems include the nurse call system, ICT and functional care systems such as hoists. We do, however, provide the cabling and power supply for these, and sometimes also carry out the final connections. There is still plenty left for us to do, including the basic electrical installation, LED lighting, socket outlets, cabling, emergency lighting, escape route signage, the fire alarm system and 330 PV panels on the roof, with all the associated infrastructure.”

Making our own contribution as standard practice“What matters just as much to us,” Van der Zwan continues, “is how we care for and work with the client and the different user groups. We receive a housing concept from the organisation that lists its requirements. We do not adopt it blindly. Because we have a lot of experience in this area, De Wit Totaal E-techniek can play an active role in making its own contribution and tailoring the design more closely to individual needs. Take the lighting. We proposed setting a higher light level in the circulation areas in the older people’s accommodation than in the young people’s accommodation. We also created quiet zones for the young people, with suitable lighting. Another example: in some bathrooms with stretcher hoists, we replaced the ceiling light with a wall light providing grazing light, so clients are not bothered by direct light in their faces. We also made sure the power connections were correctly positioned, so the stretcher hoists do not need to be powered using long extension leads.”

No misgivings
These are examples of a way of working, but also of an attitude. Van der Zwan: “I feel a strong sense of responsibility for what I do and do not want to walk through the rooms after handover feeling uneasy. I want a tidy end result, satisfied users, a quick build and as little disruption as possible for residents moving around their own site. And this is all much easier when the parties you work with, such as KBM, share the same approach.”

Facts and figures

Owner
’s Heeren Loo, Amersfoort

User
Willem van den Bergh, Noordwijk

Architect
IAA Architecten

Structural engineer
Bogaards Constructiebureau

Contractor
KBM Groep BV

Electrical services
De Wit Totaal E-techniek

Mechanical services
Megens Installaties Rotterdam BV

Have a business enquiry for KBM Groep? Get in touch

Who worked on it

Willem van den Bergh in Noordwijk

  1. contractorKBM Groep
  2. Owner’s Heeren Loo
  3. ArchitectIAA Architecten
  4. Structural engineerBogaards Constructiebureau
  5. Electrical installationsDe Wit Totaal E-techniek
  6. Mechanical installationsMegens Installaties Rotterdam BV
  7. demontabele toilettenGeberit
  8. doorontwikkelde bergingVaarkamp

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectWillem van den Bergh
  • SubjectResidential care & nursing homes
  • CompanyKBM Groep
  • Company’s Heeren Loo
  • CompanyIAA Architecten
  • CompanyBogaards Constructiebureau
  • CompanyDe Wit Totaal E-techniek
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.