Leonardushof, Wouw: A safe and welcoming home in a building that breathes

It was not meant to look like a traditional care home. What sets the new Leonardushof in Wouw apart is its high ambitions for sustainability, natural light and transparency. Aan de Stegge construction company from Roosendaal has created a striking building that feels like a warm home to residents with psychogeriatric conditions. “Everyone involved has done an outstanding job.”

Sjoerd de Wit, property manager at client Stichting Groenhuysen, says mutual trust was the foundation of the successful partnership. Bas Moens, managing director of Aan de Stegge Roosendaal (ADSR), had already looked at the site some time earlier. “The two parties had been in contact for a while.” Their relationship grew closer when the decision was made to bring the outdated care home in Wouw up to modern standards. A thorough survey of the building’s condition showed that a new build was the best option. De Wit explains why ADSR was chosen. “We were looking for a local company with sufficient scale and extensive experience delivering care projects.” From the outset, the focus was on what could be achieved within the available budget and the ambitions Groenhuysen had in mind. Moens immediately points to one of the challenges in the client’s brief. “The old building had an unusual shape. The new building had to stay within the footprint of the former nursing home, so that the zoning plan would not need to be amended and the project could be delivered quickly.”

Challenge
The design on the table was by Oomen Architecten in Breda. It was a three-storey building with 48 apartments, intended at the time for older people with a nursing home care indication. Moens highlights another point in the brief: the high sustainability ambitions. Numerous options were considered for the building services, with the aim of making the building as green and sustainable as possible. Moens says weighing up all these options during the development phase was a major challenge. “As a construction team, we had to make sure we could deliver on all the ambitions within the set budget. You have to look at building services systems that require a large upfront investment but have relatively low depreciation costs later on, and vice versa. In the end, we chose an ice storage system for seasonal thermal energy storage. It is an innovative solution that is still relatively unfamiliar in the Netherlands, but widely used in countries such as Germany.” For Angelique de Keizer, site manager and internal project lead, the proven track record of the technology was also a key consideration for Groenhuysen. “The last thing you want is for our residents to be left in the cold. We still have electric boilers on standby as a back-up.”

Time pressure
Leonardushof was built at a time when the Covid crisis was at its height and construction costs were soaring. The time pressure increased further when, during construction, Groenhuysen decided to make the site suitable for older people with dementia as well. De Keizer describes it as a change prompted by new insights. “Research showed that we could expect a sharp increase in the number of older people with psychogeriatric conditions, such as dementia, in the coming years. We decided to designate our site for this group. This had a major impact not only on our staff, who had to undertake further training at short notice, but also on the construction work.”
The change in target group meant that the construction team, for example, had to adapt quickly. “The latest home automation technology was installed, along with additional personal safety measures.” Moens is proud that they managed to make it all work. “As a builder, you always have to keep the end user’s needs in mind, from start to finish. But things became challenging when so much new information came in unexpectedly during the process. The whole supply chain had to adapt, at a time when the market and all logistics flows were already under pressure. And that is without even considering the need to move the residents.” The planned completion date was nevertheless met, thanks in part to smart solutions that saved time. De Wit sums it up succinctly: “Everyone involved has done an outstanding job.”


Freedom
The apartments at Leonardushof range from 45 to 50 m2 and have their own sleeping area and bathroom. The ground floor houses a welcoming restaurant, a snoezel room and a hair salon. The home automation system allows residents to move around as freely as possible, De Wit explains. “We want our residents to live freely, with as few restrictions as possible, and we can arrange this for each individual.” The building’s entire layout reflects the ambition to make Leonardushof a safe and welcoming home, with light and sightlines throughout, spacious corridors that breathe, and comfortable furniture in shapes and colours you would not normally expect to find in a care home. Another striking feature is the extensive use of wood, both inside and out. This was a deliberate choice, says De Wit. “We wanted a natural look.” Moens also points to the brickwork details on the outside, with bricks in a range of shades and staggered bonds. “That gives the building a playful, welcoming appearance.” For site manager De Keizer, what stands out most about Leonardushof is how many happy residents there are. “It feels as if they are living in a hotel.”

‘Prioritising user comfort and minimising running costs’
DWT Groep, a specialist in sustainable climate control systems, has been a trusted partner of Aan de Stegge Roosendaal for many years. The two companies have already delivered a number of care buildings together, particularly in West Brabant and Zeeland. Mark-Jan Koldijk, director of DWT Groep, describes Leonardushof in Wouw as a model project. “During the design phase, we really focused on user comfort and minimising running costs.” The solution selected combines thermal panels on the roof with an ice store for energy storage. It is a sustainable and efficient solution that has already been used with great success, particularly in countries such as Germany and Switzerland. “Wouw is in a groundwater protection area, so ground-source energy was not an option. The building is also in the middle of the village, which ruled out air-to-water heat pumps because of possible noise nuisance for local residents. But above all, keeping operating costs under control in the long term has always been a major issue in healthcare. Wouw is no exception.” Koldijk is pleased with the chosen concept, which uses no fewer than five sustainable energy sources: sun, air, earth, water and ice. “The result is that more money is left for care, and that is what we all want.”
Question about this story? Ask your question
Wie aan Leonardushof werkte
- clientStichting GroenhuysenIn this story
- Construction companyAan de Stegge Roosendaal (ADSR)In this story
- sustainable climate control technologiesDWT GroepIn this story
- the entire fit-out
Vervoort MeubelenMentioned in A wide variety of furniture for Leonardushof: ‘We listen carefully and can move quickly’
Keep following this
Get an email when a new story is published. No account needed.
- ProjectLeonardushof
- ThemeSustainable healthcare buildings
- SubjectResidential care & nursing homes
- CompanyStichting Groenhuysen
- CompanyAan de Stegge Roosendaal (ADSR)
- CompanyDWT Groep