Council of State: Noordwest Ziekenhuisgroep can redevelop its site in Alkmaar

The Council of State has upheld the zoning plan that enables the redevelopment of Noordwest Ziekenhuisgroep’s hospital in Alkmaar. The ruling was announced today. Three objections had been lodged against the zoning plan. The Council of State dismissed the objections from Red de Hout and residents’ association Metiusgracht. Stichting Animo and Stichting Milieubelang Alkmaar’s objection concerning the number of parking spaces was initially upheld by the Council, but was ultimately unsuccessful following an additional calculation of the number of parking spaces by the municipal authorities.
The ruling means that the zoning plan is now final and Noordwest Ziekenhuisgroep can apply for an environmental permit for the first phase of the redevelopment. In response to the ruling, Jurgen Sernee, member of the Noordwest Ziekenhuisgroep executive board, said: “We are absolutely delighted that this ruling has brought the hospital redevelopment and further greening of the hospital grounds a major step closer.”
Role of the zoning plan
Noordwest Ziekenhuisgroep faces the complex task of redeveloping its hospital at its current site in Alkmaar, in order to ensure that high-quality healthcare remains available to residents of the north-western Netherlands in the future. The zoning plan enabling this redevelopment places the provision of continuous, high-quality care at its heart. A limited intervention in Westerhout is necessary to provide future-proof healthcare. This intervention will be fully offset on the hospital grounds. The zoning plan provides the basis for developing detailed construction plans, with due regard for the green surroundings of Westerhout, traffic and parking, and limiting disruption during construction work.
Construction period
Construction will take place in three phases, allowing Noordwest Ziekenhuisgroep to respond to the constantly changing healthcare landscape. The construction period for all three phases will span 17 years. An environmental permit is now being sought for the first phase. Construction is then expected to start in early 2020. Phase 1 is scheduled for completion by the end of 2021.
First phase
The first construction phase mainly involves building the so-called ‘acute axis’. This will house the operating theatres (complex care), the emergency centre, including the emergency department, the intensive care unit and inpatient wards (complex care). The underground car park will also be built during this phase, and Huize Westerlicht will be renovated. The former residential care home will accommodate educational and office facilities.
Ruling
Read the full ruling here.
Question about this story? Ask your question
Who worked on Noordwest ziekenhuis
- specialist contractor
MedicomZesMentioned in Noordwest Ziekenhuisgroep appoints contractors for phase 1 of new build in Alkmaar - building services
ULC InstallatietechniekMentioned in Noordwest Ziekenhuisgroep appoints contractors for phase 1 of new build in Alkmaar - construction companyK. DekkerMentioned in Noordwest Ziekenhuisgroep appoints contractors for phase 1 of new build in Alkmaar
- liftsKONEMentioned in Noordwest Ziekenhuisgroep appoints contractors for phase 1 of new build in Alkmaar
- architectural practice
GortemakerMentioned in New acute care hub for Noordwest Ziekenhuisgroep Alkmaar - clientNoordwest ZiekenhuisgroepMentioned in New acute care hub for Noordwest Ziekenhuisgroep Alkmaar
- installatietechniek, constructies, bouwfysicaRoyal HaskoningDHVMentioned in New acute care hub for Noordwest Ziekenhuisgroep Alkmaar
- Structural and technical consultantHaskoningMentioned in Healthcare, architecture and landscape come together in Noordwest Ziekenhuisgroep’s redevelopment