Failure costs kept to a minimum at Noordwest Ziekenhuisgroep in Alkmaar thanks to commissioning
Text Desiree Pennings Beeld Facto Image Productions

Phase 1 of the new-build project at Noordwest Ziekenhuisgroep’s Alkmaar site covers no less than 35,000 square metres. Everything was built in just two and a half years, including the most complex installations. To achieve the best possible result and keep failure costs to a minimum, a strong emphasis was placed on commissioning, both by the hospital itself and by building contractor MedicomZes and installer ULC Installatietechniek.
Noordwest Ziekenhuisgroep is redeveloping its sites in Alkmaar and Den Helder. Phase 1 in Alkmaar has just been completed. It comprises the Emergency Centre and ICU, operating theatres for complex care and inpatient wards for complex care. During this phase, the underground car park was also built by construction company K_Dekker. The hospital can now move in and train its care staff to work in the new environment.
Checking everything in advance
Commissioning was already emphasised during the tender process. Systems and installations were thoroughly checked throughout the project, and the results were measured. This was carried out by Dion Holvast, commissioning manager at Noordwest Ziekenhuisgroep, and Teije van den Heuvel, commissioning manager at ULC Installatietechniek. Holvast says this was a good reason to choose ULC and MedicomZes. “They really know how to manage these processes. As a result, we have significantly fewer problems after handover. That is especially important when it comes to patient safety. It is great that they delivered on what they promised.”

A joint process
ULC Installatietechniek delivered all the building services, including water and sanitary systems, fire safety systems, medical gases, ventilation and air-conditioning systems, power and emergency power installations, lighting, operating theatre signalling, control systems and access control. The team checked that all the building and technical elements fitted together perfectly. Gabe Westra, project leader for mechanical installations at ULC Installatietechniek: “It is not just about the equipment, but about working together to create a well-integrated whole. During the verification phase after the contract was awarded, we put ourselves in the client’s shoes to clarify their expectations. During installation, Van den Heuvel walked around the new hospital checking everything. That makes handover a process we work towards together.”
Spot checks
What is on paper and what happens in practice are not always the same, says Ed Lenting, project manager at MedicomZes. “We overlaid and compared the building and building services drawings. Good preparation means fewer disputes later on. The integrated design review was very important. It is better to raise any concerns in advance than a week before handover.”
This approach was followed from start to finish, with Van den Heuvel walking around to carry out spot checks and make sure everything was proceeding as it should. He believes it is in everyone’s interest to keep failure costs to a minimum and ensure the client gets what they ask for. “Installation instructions, diameters and dimensions, commissioning the systems and an integrated final test: everything is checked systematically. We then check whether everything works together as a whole.”
Mock-up and air test
The design was also tested in practice. A mock-up of the single-patient room was built, and all its components were assessed by the people who would use them: healthcare professionals. The patient rooms were then built on that basis. Another example: once the operating theatre walls had been completed to shell stage, an air test was carried out. Work did not move on to the next phase until it had passed. The air test was repeated at the end to make sure all conditions were as required. Holvast: “This is an example of checking the construction in good time, so that later you do not have to demolish walls because something turns out not to be working properly.”



A streamlined build
This approach may seem only logical, but in practice commissioning often takes a back seat. This increases the likelihood of errors creeping in and needing to be rectified later. Van den Heuvel says commissioning is often assigned to the contractors, who then have to carry it out alongside their existing day-to-day work. “I work independently of the project team and do not have to take the budget or schedule into account. I only check whether the correct procedure is being followed and whether things are going well.” Holvast says this makes a difference: “This build went so much more smoothly than projects where commissioning is not embedded in the organisation. We met with Teije and MedicomZes every two weeks. That structure was extremely important.”
Working atmosphere on site
It is of course important that all parties listen to one another and communicate well. MedicomZes and ULC Installatietechniek are long-standing partners and know what to expect from each other. No induction period was needed, and the schedule was followed closely. Even so, disagreements inevitably arise. They did not lead to any insurmountable problems, says Holvast: “We always resolved the problems. By the end of the process, we were still on speaking terms. Alongside cost, quality and schedule, it is important to have a good atmosphere on site and maintain good working relationships. That was certainly the case here. Delivering on a construction project is a top-level sport, with all the complex challenges and legislation involved. Building a top clinical hospital is the Champions League.”
Both sides
As construction phase 1 comes to a close, design work on phase 2 has already begun. The experience gained will inform the next phase, and the hope is that phase 2 will run even more smoothly. “We now know in advance which areas need extra attention. We will incorporate them directly into the procedures for future projects. Clients should really make commissioning a clear requirement from the outset when buildings of this kind go out to tender. There needs to be someone in-house who understands it. I visit other hospitals where nobody is responsible for checks. When checks are carried out, it works best, especially when both sides take responsibility, as they did on the Noordwest new-build project,” says Van den Heuvel.
Een zakelijke vraag aan ULC Installatietechniek? Get in touch
Wie aan Noordwest ziekenhuis werkte
- specialist contractor
MedicomZesMentioned in Noordwest Ziekenhuisgroep appoints contractors for phase 1 of new build in Alkmaar - building services
ULC InstallatietechniekMentioned in Noordwest Ziekenhuisgroep appoints contractors for phase 1 of new build in Alkmaar - construction companyK. DekkerMentioned in Noordwest Ziekenhuisgroep appoints contractors for phase 1 of new build in Alkmaar
- liftsKONEMentioned in Noordwest Ziekenhuisgroep appoints contractors for phase 1 of new build in Alkmaar
- architectural practice
GortemakerMentioned in New acute care hub for Noordwest Ziekenhuisgroep Alkmaar - clientNoordwest ZiekenhuisgroepMentioned in New acute care hub for Noordwest Ziekenhuisgroep Alkmaar
- installatietechniek, constructies, bouwfysicaRoyal HaskoningDHVMentioned in New acute care hub for Noordwest Ziekenhuisgroep Alkmaar
- Constructief en technisch adviseurHaskoningMentioned in Healthcare, architecture and landscape come together in Noordwest Ziekenhuisgroep’s redevelopment
Keep following this
Get an email when a new story is published. No account needed.
- ProjectNoordwest ziekenhuis
- SubjectHospitals
- CompanyULC Installatietechniek
- CompanyMedicomzes