Hospitals

New acute care hub for Noordwest Ziekenhuisgroep Alkmaar

Text Tjerk van DuinenImage MedicomZes, ULC Installatietechniek en Gortemaker Algra Feenstra

Impressie van de acute as. (Beeld: Gortemaker Algra Feenstra)
Impressie van de acute as. (Beeld: Gortemaker Algra Feenstra)

Compact, efficient and phased

In Alkmaar, Noordwest Ziekenhuisgroep is building a completely new teaching hospital. The organisation has divided this major undertaking into three phases. Phase 1 involves construction of the so-called acute care hub, with an operating theatre centre for complex care, an emergency care centre with an emergency department, four wings with a total of 105 single rooms and an underground car park for 200 cars. The complex is being built by a consortium comprising building contractor MedicomZes and building services contractor ULC Installatietechniek, to a design by architecture practice Gortemaker Algra Feenstra. The first phase is scheduled to open in spring 2026.

The new acute care hub lies between Huize Westerlicht, the existing buildings and Alkmaarderhout. (Image: MedicomZes/ULC)

The new development is intended to be around 30% more compact than the existing site, which comprises several listed buildings and buildings dating from the 1960s to the late 1990s. “Phased construction means we can keep the entire building programme financially manageable and take future changes in healthcare into account as the project progresses,” says Peter Geerlings, Project Director for New Build at Noordwest Ziekenhuisgroep. “We are proceeding step by step, creating space, moving departments, demolishing buildings, putting up new ones, moving again, and so on. The process began several years ago with the renovation of the listed Huize Westerlicht, which now houses office and education functions. This created the first opportunity to move departments and then demolish buildings, starting with the oldest.”

Treatment building

Phase 1 is the first step towards the compact hospital Noordwest Ziekenhuisgroep is aiming for, and is intended for unscheduled, complex care. The complex comprises a front building, referred to by staff as the treatment building, which will be recognisable by its champagne-coloured aluminium façades. The emergency care centre and emergency department are on the ground floor. Cardiac catheterisation and intervention, diagnostics and the 24-hour laboratory occupy the first floor. The second floor will house the operating theatre complex, with five small theatres (52 m2), one large theatre (72 m2) and one hybrid theatre (85 m2). A plant floor sits above. “From the treatment centre, patients move on to the four wings with inpatient wards, identifiable by their white aluminium façades,” Geerlings explains. “The layouts are designed to make this as efficient as possible, with short walking distances for our care staff. We are building the outpatient clinics last, because this is where developments are moving fastest. Outpatient consultations and diagnostics are increasingly taking place digitally, close to patients’ homes. That could free up space within a year. If you build everything at once, you can’t easily make adjustments later.” 

The four wings with inpatient wards are identifiable by their white aluminium façades.

Standardising operating theatres

Alongside building more compactly, standardisation is a recurring theme for the hospital. “Phase 2 will have an operating theatre complex for planned care. For efficiency, it will be an extension of the theatres in phase 1,” Geerlings continues. “The eight theatres in phase 2 will have the same shape, dimensions and basic layout, and we will incorporate feedback from users of the first phase.” Operating theatres are usually redesigned from scratch each time, but we are aiming for a degree of standardisation. One unusual feature is that the operating table is no longer in the centre. This takes account of a common procedure: a caesarean section, where an incubator may be needed. The theatre therefore needs a little more space on that side. We recognise that the anaesthetist needs a fixed workstation, while the surgeon requires more room to move around. After extensive consultation and mock-up trials, we decided to move the table, pendants and other facilities by a few decimetres.”

From left to right: Ed Lenting (MedicomZes), Peter Geerlings (Noordwest Ziekenhuisgroep) and Gabe Westra (ULC Installatietechniek).

Involvement

Changes of this kind have implications for the entire chain. Ed Lenting, Project Director for MedicomZes, says: “Coming up with an idea is one thing, but all the parties involved need to be around the table early on to ensure it is implemented correctly. If the operating table is moved, all the connections have to be moved, as do the service penetrations to the plant floor above.” He stresses the importance of collaboration between doctors, designers, contractors and building services engineers to deliver a project correctly. Changes to the design of operating theatres and medical equipment have a direct impact on the building and services designs. Early consultation and detailed planning are crucial. Once designs are finalised, changes are no longer possible. That is why it is essential to involve all users closely in the process. “I am impressed by the commitment shown by everyone involved.” 

BIM on site

The hospital has, of course, been fully developed in a BIM model. Lenting says: “We are working at a very high level of detail, and we benefit from that every day. At an early stage, all the structures, building services and openings were modelled in detail, and we ensure that all components are coordinated digitally. Because everything has been developed to such a high level of detail, our site teams hardly need drawings any more. We do almost everything digitally using Dalux’s BIM Viewer. You can see everything in it. For example, it shows a door frame with a reinforced jamb, so an electrician won’t accidentally drill through it when running a cable. The floor plans from the BIM model have also been printed directly onto the floors. This lets you mark everything, from openings, drill holes, soil stacks and the positions of internal walls and door frames through to product types. I didn’t know about this two years ago; now I wouldn’t want to be without it, because it provides accurate information and prevents errors.”

The operating theatres are currently being fitted out.

Artificial clay layer

Construction of this 35,000 m2 first phase began in 2022 with the demolition of the old buildings and excavation of the construction pit. “The hospital site is mainly sandy soil, with no underlying clay layers,” Geerlings explains. “To create a dry construction pit, an artificial clay layer was formed using gel injection after a sheet-pile wall had been installed. Contractor K_Dekker then excavated the pit, installed a pile foundation and poured the basement floor. MedicomZes and ULC joined the project after that.”

Façades facing the woodland

“The building’s shell was then erected using precast concrete walls, columns and cores, and wide slab floors,” Lenting continues. “Steel structures were used for the rooftop plant enclosures. Most of the façades have now been installed. Noordwest Ziekenhuis gave us the scope to develop this package in detail with façade supplier Sorba. It is always a balance between aesthetics and buildability. Sorba supplied the aluminium cladding for the main volumes, while Schüco provided the curtain walls around the lounges and entrances. The result will be a beautiful building with patient rooms, waiting areas and plenty of lounge spaces, all looking out onto the greenery of Alkmaarderhout.”

Nearly energy-neutral

ULC is responsible for the building services. Like MedicomZes, it has a strong focus on the healthcare sector. “We took on this project together, as we have worked together for many years,” says Gabe Westra, Project Manager at ULC. “You could say we know each other inside out. For complex projects such as building a hospital, it is essential to understand each other down to the last detail. The client was looking for a compact, sustainable and efficient hospital. As a construction team, we can add real value here. The hospital is not aiming for BREAAM certification; that is almost impossible given the large amount of medical technology, and it would also involve a substantial administrative burden. However, we are building an almost energy-neutral facility, with district heating, sufficient solar panels on the roofs of the inpatient wings and a highly insulated building envelope.” 

Patient rooms 

Like the operating theatres, the single-bed patient rooms are the result of construction team discussions, consultation with users, mock-up testing, decisions being made and construction getting under way. Geerlings says: “For a year, we tested the layout of a patient room in a mock-up. Among other things, we looked for a new balance between space for nursing staff and room for a rooming-in bed for family members and loved ones who want to stay overnight with the patient. In the end, the space available means reaching a compromise that gives a little more room to nursing staff, who are in the room every day. The four wings are also deliberately oriented towards Alkmaarderhout. This makes the city park part of the ‘healing environment’.” The beds have been considered too. “In a standard layout, beds with all their facilities and connections are grouped back to back, meaning one patient faces east and another west. In our hospital, they will all face the same way, towards the attractive green space.”

Construction Day

There is no shortage of enthusiasm for the new hospital. Westra says: “Last summer, during Construction Day, members of the public and hospital staff were able to visit the construction site. The turnout was very high.” He says engagement with future users has been particularly positive. “We are working together as a team to create something special, and we enjoy involving future users closely in the process. You can feel how much they appreciate it. We are holding another Construction Day this year, on Saturday 21 June 2025.” Geerlings adds: “We have involved the people who will work in the hospital from an early stage. Not only to get that compact, efficient hospital built, but also to build and sustain everyone’s enthusiasm. We are learning from this first phase and will apply those lessons in the next construction phase. The first phase is scheduled for completion in October 2025, with the hospital opening six months later. After that, we will move departments again and prepare for the next demolition project. We intend to build the next phase with MedicomZes and ULC as well.”  

Een zakelijke vraag aan ULC Installatietechniek? Get in touch

Who worked on Noordwest ziekenhuis

  1. specialist contractorMedicomZesMentioned in Noordwest Ziekenhuisgroep appoints contractors for phase 1 of new build in Alkmaar
  2. building servicesULC InstallatietechniekMentioned in Noordwest Ziekenhuisgroep appoints contractors for phase 1 of new build in Alkmaar
  3. construction companyK. DekkerMentioned in Noordwest Ziekenhuisgroep appoints contractors for phase 1 of new build in Alkmaar
  4. architectural practiceGortemakerIn this story
  5. clientNoordwest ZiekenhuisgroepIn this story
  6. installatietechniek, constructies, bouwfysicaRoyal HaskoningDHVIn this story
  7. fire safetyDGMRIn this story
  8. Project managementAT OsborneIn this story
  9. façade supplierSorbaIn this story
  10. curtain wallsSchücoIn this story
  11. Wall coveringsM-WallMentioned in Wall panelling as part of a healing environment
  12. architectGortemaker Algra Feenstra architectsMentioned in Noordwest Ziekenhuisgroep receives keys to new building in Alkmaar
  13. Structural and technical consultantHaskoningMentioned in Healthcare, architecture and landscape come together in Noordwest Ziekenhuisgroep’s redevelopment

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectNoordwest ziekenhuis
  • SubjectHospitals
  • CompanyGortemaker Algra Feenstra architects
  • CompanyNoordwest Ziekenhuisgroep
  • CompanyRoyal HaskoningDHV
  • CompanyDGMR
  • CompanyAT Osborne
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.