Endoscopy at Gasthuisberg: smart solutions for a complex renovation

Text Stefan Aerts (M-gineers) Beeld © M-gineers

Visualisatie van de nieuwe afdeling Endoscopie op Campus Gasthuisberg.
Visualisatie van de nieuwe afdeling Endoscopie op Campus Gasthuisberg.

We have been involved in the expansion and renovation of UZ Leuven’s Gasthuisberg campus for more than 30 years. As an engineering consultancy, we are proud to have guided countless construction phases at this healthcare site and contributed ideas for the sustainable and technical solutions that will shape the healthcare of tomorrow. We are currently in the construction phase of the renovation project for the Endoscopy department, designed by GAF and archipelago, for which we are responsible for the building services, structural engineering and sustainability studies.

Endoscopy is a medical technique used to diagnose and treat conditions without the need for major surgery. The new facilities have been specifically designed to provide optimal conditions for these high-tech examinations, with the latest medical equipment and the highest standards of patient comfort and hygiene.

In this article, we take a closer look at the details of the project.

A new phase for the Endoscopy department

The project involves the renovation of more than 3,500 m², focusing on endoscopic examinations. It includes examination rooms, interventional rooms and specialised spaces, specifically:

  • Existing area: the construction of 3 interventional rooms with turbulent airflow, 12 examination rooms for specialisms such as isolation, gastroenterology, pulmonology and proctology, a recovery area with preparation bays, and an area for outpatient motility studies.
  • Shell space: adjoining the current Endoscopy department and above a recent extension to the Surgical Day Care Centre, a shell space was provided. It is now being partially used for a newly centralised sterilisation department and additional recovery capacity.
  • Link corridor: a new link corridor will connect the Kritieke Diensten II building to the rest of the hospital.
Stefan Aerts, Building Services Project Leader at M-gineers

Project phasing and schedule

Work began in March 2025 and is being carried out in two main phases. The full project is expected to take 3.5 years. This timescale is necessary to address the complexity of the renovation and integrate advanced building services.

Challenges and innovative solutions

The project presents a number of specific challenges. For example, it has been divided into two phases so that both the Endoscopy department and the surrounding departments can remain operational during the works.

Another challenge is integrating air-handling systems into the limited space available. The solution was to add an additional level to a plant room on the second level, above the Intensive Care department. Seven air-handling units will be installed there, which is essential to ensure air quality across the different departments.

The limited ceiling void also presented obstacles, due to the presence of ribs and structural beams. To address this, we decided to install filter fan units with HEPA filters in the suspended ceilings. Recirculated air is filtered through a combination of compact fine-dust and carbon filters in the walls, providing an efficient solution that meets both spatial and hygiene requirements. This is a fine example of the designers’ and client’s creativity in making all the elements fit together!

Visualisation of the new Endoscopy department at Campus Gasthuisberg.

Energy efficiency and sustainability

Energy efficiency is a priority in this project. The air-handling units and ducts are fitted with heating water and chilled water coils that are ready for future connection to Kritieke Diensten II (new-build phase VIII). The coils have already been sized for low hot-water temperatures and high chilled-water temperatures, making it easy to switch over as soon as Kritieke Diensten II is operational.

Various measures have also been taken to save energy, including the use of motion detection in sanitary facilities, circulation areas and other unoccupied spaces. Occupancy detection is used in spaces that are occupied intermittently.

The importance of Revit in the design

The project was designed in Revit, an essential tool for coordinating the many new systems with the existing ones. Using this 3D modelling software, we can identify and resolve clashes between the different systems in the suspended ceilings at an early stage of the design. This not only saves time, but also means contractors can start work with a well-coordinated plan in place.

This renovation project for UZ Leuven is a complex undertaking, involving both technical challenges and opportunities to deliver the healthcare facilities of the future. To find out more about our approach or services, please get in touch. 

Revit model of the new Endoscopy department at Campus Gasthuisberg.

Facts & figures

  • Client: KU Leuven
  • Architects: archipelago
  • and Gortemaker Algra Feenstra
  • Engineer: M-gineers

Een zakelijke vraag aan Gortemaker Algra Feenstra architects? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeSustainable healthcare buildings
  • SubjectGeneral
  • CompanyGortemaker Algra Feenstra architects