Bergman Clinics’ largest independent treatment centre
Text Tjerk van DuinenImage Bouwcombinatie Goossen Te Pas & Wessels Zeist & Tjerk van Duinen

On 1 April 2025, Bergman Clinics will open its largest location to date in Capelle aan den IJssel. Following the partial demolition, conversion and extension of an old machine factory and office building, the healthcare provider now has a state-of-the-art independent treatment centre covering 8,400 m2. With four operating theatres, a theatre preparation corridor, a recovery unit, X-ray and MRI facilities, 25 patient rooms and a fully equipped Central Sterile Services Department (CSSD), it is almost a small hospital. The focus is on orthopaedic procedures involving the knee, hip and shoulder, among other areas. The CSSD will also sterilise instruments for several other Bergman clinics.
Following demolition and groundworks in the first half of 2023, construction got under way immediately after the summer building break that year. “With the building work due to be completed by the end of December 2024, the schedule was tight,” says project manager Bart van der Most of Goossen Te Pas. “The first ten weeks of 2025 were spent commissioning the systems and resolving all outstanding issues. Bergman then began fitting out the clinic and moving in, ready to receive its first patients on 1 April.”

Construction team
The highly successful delivery was made possible by close collaboration between the parties responsible for planning, design and construction, some of which had already worked together on earlier Bergman projects. Activ Vastgoed, responsible for all Bergman Clinics’ accommodation requirements for 12 years, began preparing the plans in 2021. This resulted in a Schedule of Requirements, the choice of site, a preliminary design (together with in-house architect Hasselaar) and the selection of the construction team. In addition to Activ, which also acted as the client’s representative, the team comprised the Goossen Te Pas & Wessels Zeist construction consortium (conversion of the existing building and shell construction of the new building), Interflow (operating theatre centre and CSSD) and De Groot Installatietechniek (building services). The guiding principle for the team was to use the benefits of repetition to further improve the quality of the various processes.
Location
First, however, the choice of location. “We were looking for a replacement for Bergman’s current ‘movement’ clinic near Rotterdam The Hague Airport, which had become outdated and, above all, too small,” says Aart Knop, project manager at Activ. “For the new location, we wanted a building with a spacious site that met the Schedule of Requirements. This meant, among other things, that it had to be structurally and functionally suitable, with sufficient ceiling heights for the operating theatre complex and CSSD, enough parking and good accessibility. The vacant machine factory proved suitable, and we were able to accommodate the required ceiling heights in the newly built extension. The CSSD is also located there.”

Process with milestone reviews
The entire construction team worked through the stages from the Schedule of Requirements and preliminary design to the developed, technical and construction designs, and developed these into a BIM model. “This makes the best possible use of the team’s expertise and produces an integrated, optimised design that has been tested for feasibility on all fronts,” says Van der Most. “We used interim milestone reviews to check that we were on track in terms of budget and schedule. During this phase, structural surveys were carried out after the parts of the building to be retained had been completely stripped, to establish the condition of the shells, rule out risks and address any that arose. For example, Aveco de Bondt surveyed the existing shell using 3D laser scanning and converted it into a mesh format. DigiBase incorporated this format into the model. The deviations and dimensional tolerances were then determined before further design work continued. One advantage of working with VolkerWessels companies is that these specialist skills sit within the same group and use the same working methods. Other milestone reviews included the pre-engineering agreement and the construction contract. This provides transparency and a clear overview for all parties, including the people at Bergman.”
Yellow, green, blue
The project drawings divide the building into three sections, each identified by a different colour. Section 1 (yellow) is the new operating theatre complex, with the CSSD, theatre preparation corridor and recovery room on the ground floor, and a staff canteen, changing rooms and operating theatre technical services on the upper floor. Section 2, the conversion of the high-rise building (blue), is the former five-storey office building, which will house outpatient departments, patient rooms, physiotherapy and offices, among other facilities. Section 3, the conversion of the low-rise building (green), will have X-ray rooms and an MRI scanner on the ground floor and patient rooms on the upper floor. A new staircase with two bed lifts connects the sections, acting as the central piece of the puzzle.


Existing building shells
The existing building shells required considerable attention from the construction consortium. Van der Most explains: “The design consists of clean, rectilinear volumes with straight façades. However, the old office building’s shell had structural setbacks on the ground floor, first floor and top floor. The floor plates also needed to be extended.
“This was resolved by cantilevering the existing floor plates by approximately 1.3 m using connecting reinforcement bars, reinforcement cages and concrete, then adding steel strips and a sand-cement screed. Recesses in the floors were also infilled in this way. All the façades were then built using 5.40 m-wide prefabricated timber-frame elements, onto which a smart, sound-attenuating aluminium façade cassette system was installed, with lightweight façade modules that are easy to replace.” The existing cement screeds were retained in the shells of sections 2 and 3. Only for the MRI scanner was the floor sawn out and replaced with a reinforced steel structure and concrete beams to support the loads. High-quality metal stud wall systems were used to fit out the new room layouts. The suspended ceilings in these rooms are taupe, a subtle colour that carries through into the wall finishes. Therdex PVC flooring in a herringbone pattern has been laid throughout.

Clean air
The new-build section (section 1) has a steel structure, with a prefabricated concrete ground-floor slab and prestressed hollow-core slabs on the first floor, to support the pendants and accommodate the many service penetrations. Here too, prefabricated timber-frame elements and the aluminium façade cassette system were chosen. Once the shell was structurally complete and met all the requirements, the construction consortium handed it over to Interflow. This is its sixth Bergman clinic. “We have 50 years’ experience in everything related to clean air, and are the only company in the Netherlands to design and build fully integrated cleanrooms,” says Interflow project manager Pieter Geradts. “The high-performance areas in hospitals and clinics must meet demanding standards, which we guarantee in advance. Here, these include the operating theatres, theatre preparation corridor, recovery room, CSSD, canteen and changing rooms, storage rooms and all technical installations. The 45 m2 operating theatres are Class 1+ and intended for major orthopaedic procedures. These require an extra-sterile working environment because implants are particularly susceptible to infection. The operating theatre complex is therefore also suitable for other procedures, making it future-proof should Bergman wish to treat a different patient group there.”
Flexible wall system
The Goossen Te Pas & Wessels Zeist construction consortium prepared the shell of the new building with floors meeting high flatness standards and façades with enhanced airtightness. After handover, Interflow fitted out the rooms with metal stud partition walls. The cleanrooms have smooth HPL walls and suspended ceilings. The operating theatres follow Interflow’s Flex-OK concept, comprising a plenum, air handling and flexible walls with skirting-level extraction. Geradts explains: “Clean, conditioned air enters the operating theatre from a 3 x 3 metre plenum and flows down past the table to the floor, where it is ultimately extracted through slots at the bottom of the hollow walls. This has been tested with countless layouts and room sizes and produces the least turbulence. That is one reason why all the dispensers, control panels, PC workstations and screens have been integrated into the flex drawers, prefabricated modular wall elements that can be quickly and easily replaced if changes are needed in the future. This keeps the floors as clear as possible. The ceilings are made with sound-absorbing material sealed in foil, because orthopaedic surgery generates extra decibels. With eight to ten operations a day, you want to be able to work comfortably.”
Pressure differentials
The operating theatre complex and CSSD operate according to a stepped pressure hierarchy. The theatre preparation corridor is at a positive pressure of 40 Pa; the operating theatres, clean side of the CSSD and sterile storage for implants and surgical instruments are at 30 Pa; the corridor is at 20 Pa; and the holding area, recovery room, washrooms, changing rooms and dirty side of the CSSD are at 10 Pa. “The large staff canteen and changing rooms are also covered by the cleanroom regime,” adds Geradts. “This means staff do not have to keep changing clothes as they move around within the operating theatre complex.” The CSSD has a dirty-to-clean workflow. Knop explains: “These rooms are also ISO 7 classified. The route runs from pre-rinsing and ultrasonic pre-cleaning to the washer-disinfectors, drying, packing instrument sets into baskets and sterilisation, before they are moved into sterile storage.”
All disciplines
The building services for the new Bergman clinic were designed and installed by De Groot Installatietechniek. “It’s a wonderful project that involved almost every electrical engineering discipline: low voltage, medium voltage, lightning protection, data, intruder alarms, cameras, fire detection, medical earthing, music, access control, intercom, evacuation, silent alarm, nurse call, lighting with a lighting control system, emergency and escape route lighting, solar shading, an uninterruptible power supply, 203 solar panels on the roofs and EV charging points on the site,” says electrical engineering project manager Angelo Stoové. “The building is supplied with electricity via a new, dedicated 2,000 kVA transformer station on the site. The operating theatre centre and the rest of the clinic each have their own 1,600 A circuit breaker.” De Groot Installatiegroep agreed a demarcation with Interflow for the new operating theatre complex. “Fire detection, evacuation, security and communications systems cannot be split between contractors. Interflow therefore provided the pipes, trunking, back boxes and power supplies for De Groot Installatiegroep.”
Proven, energy-efficient systems were chosen for the climate control installations. “Sections 2 and 3 are equipped with large air handling units with rotary heat exchangers and CO2-controlled VAV boxes. A VRF unit has been installed in each room for heating and cooling. Thirteen heat pumps have been installed on the roof to serve these sections,” says W-services project manager Klaas Noorlander. “You could easily call this almost a fully fledged hospital. With patient rooms and a CSSD, it really is a 24/7 operation. Having considerable freedom to design the installations for this type of facility is a huge advantage. That comes down to trust, which we have built up through previous collaborations.”
Trust
The other members of the project team are equally positive about the collaboration. Knop: “As project manager, we said: we work with parties we trust, who share in the risks and can therefore be given the freedom to act. That has paid off here.” Van der Most: “Goossen Te Pas joined forces with Wessels Zeist under the VolkerWessels banner. On this project, we were able to draw on our experience from previous collaborations for Bergman and Activ to make the construction process even more efficient. Naturally, there were some tensions along the way, but I’m very proud of how we achieved the best result here through honest and transparent collaboration. I’d be happy to take this team on to the next project.” Geradts is also very pleased with how things went. “Activ knows the end user very well and is confident in making decisions. With decisive action, you can keep things moving from design right through to final handover.” Noorlander concludes: “This is not a project with an unlimited budget, and yet it has delivered a beautiful, high-quality clinic. A wonderful team achievement.”
Question about this story? Ask your question
Who worked on it
Zelfstandig behandelcentrum Bergman Clinics Capelle aan den IJssel in Capelle aan den IJssel, transformation
- contract administratorActiv Vastgoed
- In-house architectHasselaar
- Construction consortiumBouwcombinatie Goossen Te Pas & Wessels Zeist
- Operating theatre and sterile services departmentInterflow
- building servicesDe Groot Installatietechniek
Keep following this
Get an email when a new story is published. No account needed.
- ProjectZelfstandig behandelcentrum Bergman Clinics Capelle aan den IJssel
- ThemeFaster, more flexible healthcare construction
- SubjectConstruction projects
- CompanyActiv Vastgoed
- CompanyHasselaar
- CompanyBouwcombinatie Goossen Te Pas & Wessels Zeist
- CompanyInterflow
- CompanyDe Groot Installatietechniek