New main entrance for the AMC site in Zuidoost is a ‘major logistical challenge’

(Beeld: Johan Carlier)
(Beeld: Johan Carlier)

The entrance area at Amsterdam UMC, AMC site has undergone a complete transformation. Patients, visitors, staff and students no longer enter the university medical centre in Zuidoost via a bleak, dilapidated car park, but through a light, spacious reception hall in a glass pavilion set in parkland.

Walking through the recently completed pavilion, project manager Johan­ Carlier looks back with satisfaction on this ‘major logistical challenge’. “Demolition and construction work weren’t even my biggest concern. Far more complex was ensuring that patient care, which continued throughout, was not put at risk,” he says. Throughout the construction process, the hospital had to remain fully accessible. This was particularly important for the GP out-of-hours service, the Emergency Department, the ambulance station and Ronald McDonald Huis Emma, which is also located on the site. Keeping the emergency services open at all times required the construction team not only to plan and phase the work meticulously, but also to communicate intensively with all stakeholders. “After all, we had to build right in front of and above the emergency services’ entrances,” Carlier explains. “The 24/7 opening of the emergency services came under even greater pressure as patient numbers rose sharply during the first and second waves of coronavirus. That had an enormous impact on the entire process.” 

Having to close the main entrance for more than a year during the COVID-19 pandemic and use temporary entrances placed significant demands on the organisation, says the project manager, particularly for one of the largest academic hospitals in the Netherlands. “It was a major challenge, but thanks to the cooperation of the hospital’s various directorates, we managed it. Patient care was never put at risk.”

The oval roof, rounded forms and fully transparent curved-glass façade give the pavilion a contemporary, welcoming appearance. (Image: Gerritjan Huinink Fotografie)

A distinctive design

Carlier describes the new main entrance, which has two floors, as ‘a distinctive design with beautiful architecture’. The oval roof, covered with moss, succulents and solar panels, the rounded forms and the fully transparent curved-glass façade give the pavilion a contemporary, welcoming appearance. Visitors can park their cars in one of 300 new spaces, and new parking facilities have also been provided for motorbikes, scooters and bicycles. There is also a Kiss & Ride zone outside the entrance.

The spacious central reception hall on the first floor can be reached by stairs, escalator or lift. Wood takes centre stage in this light-filled hall. The large, wood-clad reception and control-room desk immediately catches the eye. The wooden service desk is equipped with digital information screens, while elegant seating areas are arranged around the hall, offering visitors a wonderful view of the park.    

The high wooden ceiling creates a sense of space. The wood finish on the round service islands in the reception hall and the tiled floor, which becomes lighter towards the centre, create a pleasant atmosphere. The colour scheme of the tiled floor blends seamlessly with the existing tiles in the corridors leading to the hospital and outpatient clinics. 

Rain gardens

Although most of the planting in the park will only start to grow next spring, the first signs of the herb gardens and 57 newly planted trees are already visible. Rain gardens have been created to capture excess rainwater. The wood from trees felled during the demolition work has been reused. Stadshout Amsterdam made it into benches, which are dotted around the park and give visitors, patients, staff and local residents somewhere to take a break and enjoy the green oasis around them. The seating on the tiered steps will also be clad in this reclaimed wood. 

The architects, Tom Bergevoet and Joost van Noort, are very pleased with the result. “This used to be an area dominated by cars. Now it’s a ‘Health Park’, greener and healthier. It forms a natural connection between the hospital and its wider surroundings. The bridge over the water to Meibergdreef invites local residents to enjoy the park.”

Switching over

The demolition and construction work took place in six phases, each preceded by meticulous preparation. Carlier: “On 8 June 2020, we ‘switched over’. From that day, the two main entrances to the hospital and outpatient clinic were closed, and the ring road around the monolith was shut. Alternative temporary entrances and parking facilities were put in place.”

Because of the demolition work in the forecourt, the access routes for ambulances and visitors to the Emergency Department, including the associated barrier system, were relocated several times. “There was even a phase when visitors to the Emergency Department had to park in the middle of the construction site. Fortunately, contractor MedicomZes was able to guarantee safe access to the hospital during every phase of construction, and there were no incidents.” 

Meanwhile, as the municipality of Amsterdam was building a new station square at Holendrecht station, right next to the AMC site, the so-called dry route was demolished. This popular walkway connected Holendrecht station, the adjacent bus station and the hospital. The hospital provided shuttle buses for people with limited mobility who travelled by public transport. Alternative driving and walking routes were introduced, and during the coronavirus pandemic separate entrances were provided for visitors and patients on the one hand, and AMC staff on the other. The number of entrances was increased from two to four to minimise the risk of infection. 

Hurdles

“We had to overcome quite a few hurdles before we could start building,” says Carlier. “The project’s success was due in part to the excellent cooperation between the construction team and the various directorates and divisions at the AMC site. This meant we could demolish and build with minimal disruption, while care continued uninterrupted.”

He considers the new entrance area ‘a huge improvement’ on what was there before. “Previously, patients barely knew where they had entered or where they needed to go, the car park was falling apart and the facilities were poor. Now it’s a healthy, green environment where everyone is welcome, with a beautifully designed, spacious and welcoming reception hall at its heart. A real calling card.”    

‘As a construction consortium, we have all the expertise we need’

Complex project at Amsterdam UMC’s AMC site successfully completed through intensive collaboration

In less than two years, the construction consortium of MedicomZes, HOMIJ Technische Installaties and Van Kessel Sport & Cultuurtechniek, all VolkerWessels companies, transformed the completely outdated concrete forecourt at the AMC site into a green space, soon to be complete, with a welcoming glass pavilion as the new main entrance. The project managers believe that close collaboration between the construction consortium, Amsterdam UMC, its Housing & Engineering Directorate and its advisers was a key factor in the project’s success. 

The three companies were deliberately selected for the consortium because of their experience with projects at the AMC site and their long-standing cooperation. Ed Lenting (MedicomZes), Ulco Hendriks (HOMIJ Technische Installaties) and Johnny Blommers (Van Kessel Sport & Cultuurtechniek) describe the redevelopment of the entrance area at the AMC site as ‘a great but complex project’ that presented plenty of challenges. “This project had everything, from demolition, dismantling and foundation work to cabling and construction,” says Lenting. “With so many stakeholders, something was happening every two months, from direct deliveries to coronavirus.” The project’s success was down to close cooperation with Amsterdam UMC and the expertise within our construction consortium. We look back on it with pleasure.”

Rainwater

That expertise proved useful, among other things, when addressing the question of how to drain rainwater. Hendriks: “The architect had planned for it to be drained through the columns in both the central reception hall and beneath the ramp. It looks beautiful on a drawing, but turned out to be a little more challenging in practice. We still managed it. The rainwater now flows through a special drainage system into the rain gardens in the park.”

Clear communication with the client proved essential throughout the process, says Lenting. “For example, the fresh-air supply to the operating theatres, intensive care units and Emergency Department runs through the external wall, right next to the construction site. While the pavilion roof was being laid, we stayed in direct contact with hospital staff. If they said they could smell the bitumen being torched inside, we stopped work immediately. The same applied to sawing the asphalt. Whenever there was disruption, we stopped straight away.”

The pavilion features escalators, draught lobbies, a round curtain wall and beautiful wooden ceilings.

A logistical feat

After the dilapidated access roads and parking decks were demolished on 8 June 2020, work moved quickly. The first pile was driven on 11 September that year, with sister company ­Volker Staal en Funderingen using bored piles to minimise vibration. The new pavilion and adjoining forecourt were completed last November. It was a logistical feat, as coronavirus put pressure on delivery times worldwide. Nevertheless, the construction consortium was able to start fitting out the pavilion in August last year. “A tremendous amount of work was done in the week before handover,” says Lenting. “Not a cross word was spoken. Everyone worked incredibly hard to get it done, and successfully.”

Recycling

The round, transparent entrance pavilion, with approximately 2,000 m2 GFA, connects the hospital’s main entrance with the entrance to its outpatient clinics. In addition to its distinctive design, it is a sustainable building, with solar panels and sedum on the roof. The construction consortium processed demolition waste from the existing entrance into the site paving. All excavated soil was also reused within the project. “The entire parking deck is buried beneath us here,” says Hendriks, describing it as a huge cost saving.

The pavilion was effectively built in reverse, starting with the roof, a steel structure placed on the foundations. First, four large columns were installed, to which the steel structure was attached. All the pipes and cables were also incorporated into the columns. The first-floor slab was then poured. “A milestone,” according to the project managers, who completed the work in a single day. “Seventy lorries came and went from early morning until late afternoon. By five o’clock, a thousand cubic metres of concrete had been poured and everyone could head off for the Christmas break.” The slab then proved to have cured sufficiently, allowing the finishing touches to be made to the roof and external façade. 

A transitional function

In addition to the building, the construction consortium is responsible for redeveloping the forecourt of the AMC site. It will include almost 400 parking spaces for cars, motorbikes and bicycles, a Kiss & Ride zone, and new entrances to the ambulance service, Accident and Emergency department and GP out-of-hours service. The forecourt, adjoining the car park, will be landscaped as a park. As well as providing a place to spend time, it will serve as a route linking the recently renovated Holendrecht station square with Meibergdreef. The Ronald McDonald Huis Emma will also be easily accessible via the new forecourt.    

Have a business enquiry for Medicomzes? Get in touch

Who worked on it

  1. ClientAmsterdam UMC, Directoraat Huisvesting & Techniek
  2. DesignersTemp.architecture & Studio Nuy van Noort in samenwerking met Studio BLAD. Kernteam: Tom Bergevoet, Maartje Nuy, Maarten van Tuijl, Joost van Noort, Fiona Kydd en Frank van Zuilekom. Medewerkers: Justyna Breczko, Sebastian Nitu, Andoni Urreizti Álvarez, Deniz Atakan en Zsófia Török
  3. Building services and building physics consultantsNelissen Ingenieursburo BV
  4. Structural engineerPieters Bouwtechniek Amsterdam
  5. Construction cost consultantBremen Bouwadviseurs
  6. Construction management consultantBBC Bouwmanagement
  7. Civil engineering consultantGryllus Advies
  8. ContractorMedicomZes, HOMIJ Technische Installaties en Van Kessel Sport en Cultuurtechniek
  9. ProgrammeProgramma binnen: entreepaviljoen met balie, meldpunt, toiletten, zit- en verblijfsruimte voor bezoekers en patiënten Programma buiten: brug- en voetgangersdek van station Holendrecht naar entree, kiss- en ridezone, 300 parkeerplaatsen, 70 fietsparkeerplaatsen, toerit ambulancegarages en park
  10. Project size2.000 m2 BVO entreepaviljoen 2.500 m2 brug- en voetgangersdek 3 ha buitenterrein waarvan ca. 1,5 ha park en ca. 1,5 ha parkeren en infrastructuur

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeHospital construction and refurbishment
  • SubjectHospitals
  • CompanyMedicomzes
Share this article

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.