Working together on a new Radboudumc. More compact, smarter, more sustainable

In three years, FourCare, a partnership between two construction companies and two building services companies, built the new Building A and handed it over to client Radboudumc last April. The academic hospital has once again taken a (major) step towards becoming a modern, highly sustainable and future-proof healthcare institution. The new main building has nine floors and two basement levels (45,000 m2 in total). It includes four floors of outpatient clinics, three floors of inpatient wards, two floors of staff facilities, two floors (mostly below ground) for building services, and spaces for reception, the main entrance to Radboudumc, retail and logistics. The hospital has 150 single-patient rooms and 24 day-treatment beds. The construction consortium’s watchwords: collaboration, sustainability and… coronavirus.

It may seem strange to use new construction to reduce the size of a site, but that is precisely the aim of Radboudumc’s property strategy. By the end of the campus-wide redevelopment, the floor area is to have been reduced by 100,000 m2 to 380,000 m2. “And yet we intend to maintain, or even improve, the quality of care,” says René Bleeker, construction director at Radboudumc. “We will do this through smart technologies,
more efficient, demand-led use of space, and a healing environment that helps patients recover through light, quiet, calm and nature. At the same time, academic hospitals are increasingly focusing on highly complex care.”

Sharing capacity
The task of delivering EGM’s design, and with it the hospital of the future, fell to the FourCare consortium. “FourCare is a partnership between contractors Trebbe and Van Wijnen and building services providers Unica and EQUANS,” says Geert Klein Lebbink of Trebbe. “We also built the new Amphia Hospital in Breda together, and are currently renovating the existing buildings. The collaboration worked so well that we decided to take on more projects of this kind in highly complex healthcare.” Other reasons for working together include sharing risk and capacity, says Jasper van der Meer, director of Van Wijnen Rosmalen. “Building a hospital puts an enormous strain on your resources and people. With the current shortages, particularly of staff, that is not sensible.”

Sharing responsibility
The consortium won the UAV contract through a public tender. Klein Lebbink: “We had already agreed on an equal division of responsibilities, assembled the teams and involved the people who would also have a role during construction. After all, the capacity has to be available in case you win.” And FourCare did. “In effect, you set up a separate construction company for the project,” Van der Meer continues. “Henk Mulder of EQUANS, Arjan van Haperen of Unica, Geert and I formed the four-person management team and represented the consortium to the client. Within that, there were two general partnerships, one for the building work and the other for the building services, with project directors Ed Tuinder and Gerard Niemeijer responsible for day-to-day management. We did not divide the work by discipline; we shared responsibility.”
Logistics
The construction work presented the builders with a number of challenges, particularly in terms of logistics. Van der Meer: “Working in an environment that has to remain operational is complex, especially in a hospital. Access for the supply chain was limited, and logistics had to accommodate visitor flows and ambulance traffic, both of which continued as usual. Deliveries followed the ambulance route, with a waiting area for lorries and a booking system to call drivers forward. The tower crane operators were in constant contact with the trauma department because of the adjacent helipad.” The structural work was no simple undertaking either. Klein Lebbink: “EGM and structural engineer Aronsohn designed a building that connects to the Central Axis and brings together a variety of construction methods. To achieve BREEAM ‘Excellent’ certification, they also designed a slim concrete frame and used a great deal of fair-faced concrete. All these aspects had to be addressed during the tender process and translated into buildable solutions. I think we did that successfully.”

But the biggest challenge was unplanned: the coronavirus pandemic. Van der Meer: “We spent three years building this particularly ambitious and challenging project, two of them under all the restrictions imposed by the virus. Huge efforts were made to deliver the building on time and within budget despite those restrictions. Looking back, I still consider that a remarkable achievement.”

Grids
The building services in Building A play an essential role, both in making it the most sustainable academic hospital in Western Europe and in bringing the Smart Hospital concept to life. Arjan van Haperen, director of Unica Projecten Zuid: “To meet Radboudumc’s high sustainability ambitions for a major energy consumer such as a hospital, Deerns designed an excellent mix of building services. The existing ATES system has been converted into an ATES ring serving the entire campus. Together with a series of air-to-water heat pumps, it provides heating and cooling for gas-free Building A. The 700 m2 of solar panels on the roof and the 3,000 m2 elsewhere on campus also form a grid shared by several buildings. Sustainability measures inside the building include LED lighting and climate ceilings that provide low-temperature heating and high-temperature cooling in all occupied spaces.”

Large basement
Apart from the large air handling units, the main building services installations are housed on the lower basement level, which has a surprising amount of space. Robert Vlek, project leader for EQUANS, describes what is installed there: “This level houses the heat pumps, the control system, 6,400 kVA of transformers, 54 metres of main distribution boards, the indispensable emergency generators with a capacity of 5,000 kVA, a 3,000-litre diesel tank and an extensive pneumatic tube system serving the whole campus. The scale of the installations shows how much stricter the requirements for climate control and operational reliability are becoming. Space has also been set aside in this basement for developments that cannot be predicted over the next 30 to 50 years. Extra electrical connections have already been installed to allow more transformers and distribution boards to be added if further electrification is required.”
Testing
Then there is the building automation system, the Smart Hospital (see also the previous article). “One of the key elements of the new building,” says Van Haperen. “Climate control, power supply, electrical systems, fire detection and security installations, data systems, patient monitoring: everything is interconnected. On top of that, there is the system of patient tablets and smartphones for nursing staff. This required extensive preparation and detailed engineering, followed by factory tests for the individual systems and an ISAT, or Integrated Site Acceptance Test, to check that all the systems worked together. The most nerve-racking test came when the grid operator switched off the power and the emergency power supply had to take over. It was also nerve-racking because several buildings are connected to it. This full-system ‘lights-out test’ took place in June. The diesel generators start up and a plume of smoke comes out of the chimney. The result: no error messages.”
Now that the job is complete, FourCare is looking forward to what comes next. “We have been asked to contribute ideas for a new project on the campus,” Van der Meer concludes. “We will need to put together another strong proposal and follow the tender procedure. In any case, we are proud of this work and pleased to have a satisfied client.”
A business enquiry for Unica? Get in touch
Who worked on Gebouw A
- buildersTrebbeIn this story
- Technical service providersEQUANSIn this story
- clientRadboudumcIn this story
- design by EGMEGMIn this story
- structural engineerAronsohnIn this story
- systems designedDeernsIn this story
- construction companyALHO SysteembouwMentioned in Permanent modular 3D extension for A.S.Z. campus Aalst
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBuilding A
- ThemeSustainable healthcare buildings
- SubjectHospitals
- CompanyUnica
- CompanyVan Wijnen
- CompanyTrebbe
- CompanyEQUANS
- CompanyRadboudumc