ZNA Cadix, Antwerp | A multidisciplinary approach delivers an optimised installation at ZNA Cadix

A major project such as ZNA Cadix calls for an impressive technical installation. Cegelec, a VINCI Energies brand, was awarded the contracts for both HVAC and electrical services. At the request of the client, Ziekenhuisnetwerk Antwerpen (ZNA), Hysopt’s dynamic simulation software was used to optimise the hydraulic systems.
Cegelec took part in the tender for the project as part of the THV Ziekenhuis Noord (Interbuild-MBG) consortium, and secured the contract. From the tender stage, Cegelec’s experts worked with the VK Engineering consultancy team on the preliminary technical design. “The first discussions date back to 2011,” recalls Walter Wens, project manager for the electrical services at Cegelec.
BEO field
Heating is provided by 3 condensing gas boilers rated at 1.75 MW, a 390 kWh CHP unit and a 277 kW heat pump connected to the BEO field. Yves Hendrickx, project manager for HVAC at Cegelec, says: “We carried out 40 boreholes, each 140 metres deep. A heat exchanger connected to the BEO field also provides free cooling. Cooling is provided by 3 water-cooled chillers rated at 1.28 MW. The heat from the chillers is rejected by 6 dry coolers on the roof. The ventilation system comprises 53 air handling units, with a total airflow of 370,000 m³/h, including 17 hygiene air handling units. Humidification is provided by electric resistance steam humidifiers with a total capacity of 1,500 kg/h.”

‘Everyone shares the same goal: to deliver a strong end result.’ (© VK Studio Architects & Engineers in collaboration with Robbrecht & Daem Architecten)
A hospital also needs an extensive electrical installation. Wens outlines the various systems: “A 4,500 kVA medium-voltage installation has been installed. This is the normal power supply, which uses mains electricity. In addition, there is an emergency power network with generators providing 2,000 kVA, and a 600 kVA UPS supply with batteries. The electrical installation also includes fire detection, with around 6,000 detectors, a sound system with 1,200 loudspeakers and a data network with approximately 11,000 end connectors. Finally, there are access control systems, configured for 900 badges, CCTV with 150 cameras, a nurse call system and an intercom system, allowing nurses to communicate with one another.”
HVAC, electrical services and maintenance
One of Cegelec’s strengths is that, as a multidisciplinary company, it can take on both HVAC and electrical installations. Hendrickx says: “After handover, our colleagues at VINCI Facilities continue to support us and take responsibility for maintaining and managing the technical installations we have installed. This includes preventive maintenance, corrective maintenance, the full warranty and the necessary reinvestment over the term of the contract, to ensure the installations continue to operate optimally for 20 years. Many more projects are planned for the future, in which Cegelec will not only take care of HVAC and electrical services, but will also carry out other technical work, such as plumbing and sprinkler installations.”
As well as delivering a technical installation to be proud of, Wens is proud of the project for another reason. “The different companies responsible for the building services work together extremely well. That is not a given on every construction site. Communication between them is clear and constructive, and everyone shares the same goal: to deliver a strong end result. That makes working together enjoyable.”
Dynamic simulations
As well as heating, cooling and air treatment, the technical infrastructure includes systems for distributing various fluids and medical gases. It was crucial to the client, ZNA, that the entire installation should work properly. Tom Havermans, Environmental Coordinator at ZNA, explains: “We attach great importance to being responsible stewards. We demonstrated this earlier by going beyond the government’s requirements when submitting the planning application. We also pay close attention to correct commissioning and hydraulic balancing. The way an installation is sized and balanced has a major impact on both comfort levels and energy performance. That is why we were among the first in the hospital sector to start using dynamic simulations.”

As a simulation tool, Hysopt makes it possible to estimate system performance during the design phase. (© Hysopt)
In consultation with VK Engineering and Cegelec, Hysopt software was used as a design and simulation tool. “Dynamic simulation using Hysopt software has become standard practice on all our renovation and new-build projects,” says Havermans. “Two people from Cegelec attended a Hysopt training course to get to grips with the software,” adds Hendrickx. “That enabled our own people to enter the installation into Hysopt.”
Havid El Khaoui, Support Engineer at Hysopt, provided the necessary support and expertise. “As a design tool, it links all the individual components into a complete hydraulic and control engineering calculation model. This makes the design process much faster, and allows more intelligence to be built into the model,” says El Khaoui.
As a simulation tool, Hysopt makes it possible to estimate system performance during the design phase, taking account of the installation’s part-load behaviour. El Khaoui says: “We simulated several design options to achieve the highest possible level of comfort for patients and staff at ZNA Cadix, alongside the lowest possible energy consumption and CO2 emissions. The optimised designs delivered savings of between 10% and 28% on annual energy costs, and between 9% and 11% on CO2 emissions. An optimal result, thanks to Hysopt software.”
Finally, the existing model is used to create a digital twin of the installation. The dynamic as-built dossier will add significant value as the installation is developed further.