By 2021, BIM was well established in the construction industry, but ten to fifteen years ago it was still a distant, unrealistic dream.

The project that paved the way in Belgium was AZ Sint-Maarten in Mechelen, which opened its doors on 15 October 2018. Almost two and a half years later, technical director Jan Claesen looks back on the pioneering years and explains how BIM is proving its worth in the operation of the new hospital too: “It is already clear that we will more than recoup the cost of learning the ropes.”

Jan Claesen: “Choosing BIM fostered unity, commitment and smooth collaboration within the project team.”

When did you first come into contact with BIM? How did the idea of using it for the design, construction and operation of AZ Sint-Maarten come about?

“AZ Sint-Maarten was a €350 million project. We were all too aware that delivering such a
huge complex within the planned timescale and budget would be a major challenge. No one was familiar with a commission on this scale, so I went looking for a project management tool that could help us keep track of everything and make it ‘manageable’. We hoped this would enable us to identify and resolve potential problems with scheduling, budget management, communication and coordination at an early stage, during the preparation phase, so that everything would be in order once construction began. We also wanted to avoid losing crucial information ‘en cours de route’. Lost documents, people changing roles, and so on are seemingly minor issues that can have a major impact, so we wanted to anticipate them. This was important for the operational phase too. After searching online, following a tip from our software supplier Autodesk and asking around in academic and architectural circles, BIM emerged as a ‘deus ex machina’, having already delivered promising results in the Netherlands and France. And that is how the ball started rolling.”

At the time, BIM was still a futuristic concept in Belgium. Did you have to deal with any teething problems?

“Of course, that was inevitable. There were no precedents in our country fifteen years ago, so initially neither we nor the architect and engineering consultancies fully understood what it would involve. On the one hand, we ran into technological limitations, such as unsuitable software and computers with too little capacity and processing speed. On the other, we were starting from scratch in terms of structure and working methods. Around 2008, we travelled to the Netherlands with VK Architects & Engineers to study two excellent case studies and gather ‘good practices’. That gave us a boost, as it showed that it was indeed feasible to build a 100,000 m² hospital using BIM. We decided to commit to it wholeheartedly and implement the BIM methodology from the design phase onwards, using the BouwData working method developed by Peggy Bovens (PB calc & consult) to keep the budget under control.”

In your view, what was BIM’s greatest added value in delivering the new hospital?

“It was not just the usual clash detection and the associated practical and financial benefits, but also the openness and transparency we were able to ensure through the shared BIM model. Traditional specifications, bills of quantities and schedules of quantities were not yet linked to BIM, as that would have been a step too far at the time, but interested contractors could see the (provisional) building structure, how the cost estimates had been prepared, and so on. This was a major benefit for them, particularly when assessing risk. Of course, they still had to add information or make changes to bring the BIM model to a level of maturity suitable for construction. This inevitably involved an intensive learning process, but once they had completed it, the BIM methodology really paid off for them too, for example in preparing schedules, deriving quantities and resolving clashes with building services. All the major decisions were made during the preparation phase, so during construction we did not have to contend with daily discussions and consultation meetings. This made a huge difference to the project duration, efficiency, and the reduction of errors and waste (easily 10 to 15%). Finally, choosing BIM also fostered unity, commitment and smooth collaboration. It was a leap into the unknown for all the construction partners, and that clearly brought them together. However difficult things sometimes became, there was always a positive dynamic around the project. There were no formal complaints or disputes. Given how complex and pioneering the delivery of AZ Sint-Maarten was, it is fair to call it a remarkable achievement.”

BIM visualisation of AZ Sint-Maarten.

Looking back, are there things you would do differently? Have you learned any particular lessons?

“Absolutely. With what we know now, we would focus much more on the 50-year operational life of the hospital and make more effective use of the information in the BIM model. Given our lack of experience at the time, we did not impose a fixed structure on the architect and engineering consultancies, so everyone added data to the model to the best of their ability. But what was useful to certain construction partners at the time is not always what we need for operations now. As the client, we would therefore set out clearer ‘ground rules’ and impose very specific minimum requirements: how should painting works be indicated in the model? Should different types of doors be distinguished? Can we easily produce quantity lists of taps and ‘shut-off valves’? And so on. The aim is to make future maintenance and technical interventions much easier. When we build the new youth and child psychiatry unit on our site, where we will once again use BIM, we do not want to miss this opportunity a second time!”

You have now been operating the hospital for two years. How useful is BIM in the day-to-day running of the new hospital?

“Extremely useful! Less than a year after opening, we had an operational, up-to-date schedule for facilities and technical maintenance, as well as a multi-year financial plan based on the BIM model, which we have worked with every day ever since. Rather than gathering all kinds of information for maintenance, documentation and so on, we can derive everything from the BIM model in just a few clicks. And if technical or structural changes or renovations are needed, we can refer to and build on convenient as-built models. In terms of time saved and efficiency, it makes a world of difference. It is already clear that we will more than recoup the cost of learning the ropes, partly because the hospital is much easier to ‘manage’. Thanks to BIM, we can keep everything running smoothly with a small technical team, whereas otherwise I would need at least two extra employees to manage projects.”

The delivery of AZ Sint-Maarten was a resounding success. Do you feel it is considered a model project for BIM?

“Absolutely, partly because we applied it to every discipline from the outset (architecture, building services, finishing, and so on). We are regularly approached by people and organisations from Belgium and abroad who want to know exactly how we did it, what the pros and cons are, and what they should definitely take into account. I am convinced that our project helped make BIM commonplace, and even almost a standard. I am very pleased to see that, because I also felt it was our responsibility to ‘give something back’ to society in return for the government support we received to deliver our project. I think we certainly achieved that!”    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeHospital construction and refurbishment