IJsselland Ziekenhuis builds new operating theatre complex using modular construction

IJsselland Ziekenhuis builds new operating theatre complex using modular construction

The new operating theatre complex at IJsselland Ziekenhuis, made up of 36 modules, was transported by boat and lorry from the factory in Germany to Capelle aan den IJssel in mid-January. The entire complex was installed there in four days. Finishing work and commissioning will take place over the coming months. Specialists at the hospital in Capelle will be able to start work in their brand-new operating centre in June.

Modular, but made to measure

There was barely any room to build the new operating theatre complex, as is clear when entering the grounds of IJsselland Ziekenhuis. The various new-build and renovation projects carried out in recent years have left very little open space. The compact new building also borders almost directly on the back gardens of neighbouring
homes. “The final building footprint, measuring thirty by forty metres, was the only plot within the zoning plan that we could still use. Close cooperation with the local authority and consultation with residents were needed to make it happen,” says Marlous Boender, Accommodation Project Manager at IJsselland Ziekenhuis.

Vervoort leverde maatwerk voor de kinderen in Villa Pardoes.

Impression of the new holding and recovery area.

Best option

Initially, a new building was not on the cards at all. The original plan was for a thorough internal renovation of the existing operating theatre complex. “Changes were urgently needed,” Boender explains. “There had been few changes since it was built in 1991. Regulations have become stricter over the years, and the growing use of technology meant more space was needed. However, renovation alone proved unfeasible. Contractors considered the complex phasing too risky and factored this into their prices. The cost became prohibitive. We then looked into the possibility of a new building after all. As we had already lost a lot of time, modular construction was the best option. It speeds up the building process and causes much less disruption than a construction site where work goes on for months. The existing operating theatres could also remain in use throughout.”

Sabine Berndsen (left) and Marlous Boender (right).

Pre-installed

German manufacturer Cadolto supplied the modular construction, comprising 36 modules measuring up to 4.5 by 14 metres. “It is modular construction, but made to measure, with a lifespan and appearance comparable to traditional construction,” says Boender. “We already had a design, and they then worked out how to turn it into units. Transport determined the dimensions: each module had to fit on a lorry. Our new operating theatres measure seven by seven metres, so they could not be made from a single module. There is therefore a joint in the floor and walls, which will of course be finished neatly so that you will not see it at all.”      

Cadolto engineered almost all the technical installations in 3D, from pendants to power sockets, and partially assembled them at the factory. The window and door façades were also installed in advance. Only the aluminium cladding on the exterior façade will be fitted later.

Concrete structure

Before the modules could be installed, a concrete slab on V-shaped columns was built in the autumn. This was necessary to connect the new operating theatres to the first-floor level of the existing building. Car parking spaces and a bicycle storage area will be located beneath the complex. The plant room has been installed as an additional recessed storey on top of the operating theatre centre. The building’s foundations are formed by 78 piles. By screwing them into the ground rather than using conventional piling methods, the work could be carried out with minimal vibration and noise. Two walkways connect the existing and new sections.

Work is progressing at pace on the finishing of the new operating theatre centre.

Shared set-up room

The new complex comprises six general-purpose operating theatres, a large combined set-up room and a spacious holding/recovery area. A corridor runs around these spaces along the façade. This allows the movement of people and logistics flows to be kept as separate as possible. “A shared set-up room does present some challenges,” says Sabine Berndsen, the architect responsible for the project at Architecten aan de Maas. “You want to rule out as much as possible anything that might disrupt the set-up process. Here, the aim was to centralise, particularly because of the lack of space. That means making smart choices about the layout and organising the logistics flows. Together with the users, we tested trial layouts and mock-ups throughout the design process.”

Villa Pardoes was voor Vervoort een eerste stap in de ‘kinderwereld’.

A module being hoisted into position. (Image: Rogier Bos)

Clean lines, yet welcoming

The operating theatres have virtually identical layouts to allow maximum flexibility. One is slightly larger and can be configured as a hybrid operating theatre. Multimedia and compliance systems contribute to better working conditions. Holding and recovery are not separate, but form one large space. This offers greater flexibility in how beds are allocated. A large visual of Rotterdam adds atmosphere to the otherwise stimulus-free environment. “The appearance of the operating theatre centre fits the overall concept we have developed for the entire IJsselland Ziekenhuis. Calm, clean-lined and formal, yet welcoming, are the key words,” Berndsen explains. So-called ‘hotspots’, such as the coffee room, feature accents in colour and form.

The planned handover of the new-build section in May will not mark the end of work on the operating theatre centre. Work will then begin on the section to be renovated. The main elements are the creation of two short-stay operating theatres with their own holding/recovery areas, a central storage area for sterile and non-sterile supplies, and a new central sterilisation department (CSA). The entire project is expected to be completed in 2021.   

Question about this story? Ask your question

Who worked on the operating theatre complex at IJsselland Ziekenhuis

  1. system buildingCadoltoIn this story
  2. architectArchitecten aan de MaasIn this story
  3. builderDijkxhoorn bouwMentioned in The contractor also plays its part in a surgical operation at IJsselland

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectIJsselland Ziekenhuis operating theatre complex
  • ThemeHospital construction and refurbishment
  • SubjectHospitals
  • CompanyCadolto
  • CompanyArchitecten aan de Maas
Share this article

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.