Treant Zorggroep, Hoogeveen | just one dust wall between construction and surgery

Treant Zorggroep, Hoogeveen | just one dust wall between construction and surgery

The operating theatres at Bethesda hospital, part of Treant Zorggroep in Hoogeveen, have undergone major refurbishment over the past two years. This demolition and refurbishment project took place while the hospital remained open as usual. How do you keep construction workers and medical staff from getting in each other’s way while ensuring patient safety?

The answer has three parts: thorough preparation, good communication and close collaboration. “The end result is fantastic,” says Tamara Kusters-Frins, head of anaesthesia, recovery and the pain management/anaesthesia outpatient clinic.

The operating theatres were custom-designed and are mainly used for planned surgery.

The extensive refurbishment was long overdue. The technical systems, including the ventilation system, were outdated, and users were short of space. “This construction project gave us the opportunity to implement the latest technologies expected in a state-of-the-art operating theatre centre,” explains project manager Theo Spoelstra. He refers to the so-called image routing system, which allows specialists at Treant’s other sites to watch operations live.

AZ Sint-Maarten in volle glorie. Het ontwerp van het ziekenhuis is tot in de puntjes geoptimaliseerd.

Efficiency

The new operating theatre centre, built on the existing site, has four operating theatres. Each theatre has its own preparation room, where instruments and other equipment for operations are laid out. Previously, this was done in the operating theatre itself and took an average of 15 minutes per operation. “The preparation rooms save us around an hour and a half per theatre per day, boosting efficiency by 20 per cent. With four theatres, we can now carry out the same number of operations as we used to with five,” says Tamara.

BIM-visualisatie van AZ Sint-Maarten.

Custom-designed

Treant involved the users of the operating theatre centre closely in the design phase. “OKCN guided us through the design process, and we were a regular part of discussions with the architect and engineering firm,” says department head Tamara. Mock-up sessions enabled operating theatre staff to try out their future workplace in advance. “They could assess whether the room dimensions and the positioning of the ceiling pendants met their requirements. Based on their input, we tailored and equipped the operating theatres and recovery room to their needs, so they were truly custom-designed.” Throughout the refurbishment, the builders and users also stayed in close contact. “If the noise became too disruptive, one phone call was enough to stop the demolition and construction work. That hotline helped bridge the tension between construction and patient care,” says Theo. 

Jan Claesen: “De keuze voor BIM heeft binnen het projectteam voor eensgezindheid, engagement en een vlotte samenwerking gezorgd.”

During demolition next to the recovery area and the Acute Care Department (AZA), a strict regime was put in place: half an hour of demolition was followed by half an hour of silence. “If you want to maintain support for the project, you also need to build in periods of quiet. That applies to our patients and direct users, as well as our neighbours above and below us, such as the lab, outpatient clinics and radiology department.” 

Goodie bag

Patients undergoing surgery at Treant Bethesda were also closely involved in the refurbishment. At their pre-operative appointment, everyone received a goodie bag containing information materials and an invitation to a tour. Hundreds of patients and their families took up the offer and saw the new operating theatre complex take shape.

The biggest challenge in this complex construction project was physically separating the construction work from care delivery. Dust-proof walls and tunnels were erected for this purpose, “because dust can pose a major risk during operations,” Tamara explains. To further minimise the risks, detailed work plans set out close arrangements with the contractor, negative pressure was created, and airborne dust levels were monitored. “These control measures proved sufficient throughout the nine construction phases, and the work proceeded steadily. There were no incidents,” Theo concludes with satisfaction.

Going the extra mile

The intensive refurbishment demanded a great deal from everyone involved. “We relied heavily on the flexibility of our staff and the contractor,” Tamara emphasises. By keeping everyone informed through a construction app and newsletter, and by continually reviewing and adjusting the work, everyone went the extra mile. The same was true of Treant’s support services, including the technical services department, cleaning staff, ICT department, Hygiene & Infection Prevention and facilities services. “Without their efforts, the project would never have progressed so smoothly,” says the project manager. He and Tamara are very pleased with the result of two years of demolition and construction.

Peter Noordhuis (left) and Theo Spoelstra. Both are project managers in Treant’s Housing and Construction department.

“After hospital site Refaja in Stadskanaal received a new operating theatre centre last year, Bethesda is now ready for the future too.” The operating theatres in Hoogeveen are mainly used for planned surgery, including knee and hip operations and breast surgery. “With this new operating theatre centre, we meet the latest medical guidelines, can work more efficiently and provide patients with the best possible care,” Tamara says.

Looking back, what was the secret to this successful construction project? “Thorough preparation and having the right person in the right place,” replies the department head. For her, the project has been more than successful. “The result is better than I ever dared to dream.”  

A business enquiry for OKCN? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeSafe and reliable healthcare buildings
  • SubjectGeneral
  • CompanyOKCN
Share this article

Advertisement

Follow on Bouwen aan de Zorg

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.