Everyone pulling in the same direction

Fitting all the equipment from Dialysecentrum Tergooi into its temporary premises, which are half the size of the former department, was a real puzzle. But they made it work, and patients are now enjoying the high-quality modular building. Tergooi Hospital will open the doors of its new site in Hilversum in 2023 and close its Blaricum site. Anticipating possible capacity constraints during both construction and the move, the Medical Specialist Company Gooi en Eemland (MSB) planned ahead. This partnership of independent doctors provides specialist medical care to the hospital and had already bought twenty units in 2018, which could be used for a range of purposes. In 2020, the units proved necessary for a department of Dialysecentrum Tergooi. Wim van der Ven, commercial technical adviser at Dutch Cabin Group, advised on the purchase and returned to deliver the site.
Everyone’s contribution matters
Wim van der Ven: “One of the dialysis centre’s sites is inside the hospital. This site, which serves patients with kidney failure who do not need direct hospital treatment, is on the hospital grounds, connected to the existing hospital.” It became a successful joint project, with MSB as the client, Dialysecentrum Tergooi as the user and Tergooi Hospital as the supporting partner. Wim: “My role was to ensure good communication between all the parties and get everyone pulling in the same direction. Everyone’s contribution matters, even when it concerns a detail such as the position of a socket for the coffee machine.”

A bit of a puzzle
Wim has 35 years’ experience in modular construction and has seen every kind of building project in healthcare. “When I arrived at Tergooi Hospital, it brought back happy memories of when we built the Paaz, the psychiatric department, twenty years earlier.” Once again, for the dialysis centre, Wim and his team came up with the most practical solutions. “The layout took a bit of working out, as the modular building had to fit between the hospital and the trees that had been planted. But it worked out well.” They also found the most cost-effective solutions. “Sometimes something is expensive, and you have to decide whether it is worthwhile given the temporary nature of the site. The comfort of these vulnerable patients was always our priority.”
A dome on the roof
To prevent vibrations from travelling through the building, the plant room was separated from the rest of the building. The reserve water tank for the water treatment system had to be installed on the roof to create natural gravity pressure. Dutch Cabin Group designed a steel structure, a dome on the roof. “Because of the tonnes of weight being moved here, additional foundation points were needed. That’s when you come across existing pipes underground and have to find out what they are for and whether they are still in use.” Alongside issues of this kind, the schedule was crucial.
Delivered with ease
“The medical equipment had to undergo technical inspection before use, and that could take up to two months. You don’t want to lose any time in operation, so we organised everything to allow accreditation to take place during construction.” And did it go smoothly? “Yes, you could say we delivered this project with ease. On time and meeting all expectations.” And what did the parties think? “They felt it was a great collaboration and learned a lot from it. They describe it as a pleasant, well-finished building: everything is in place and it looks immaculate.”
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeFaster, more flexible healthcare construction
- SubjectHospitals